HomeMy WebLinkAboutAgenda Report - February 5, 2003 E-07CITY OF LODI COUNCIL COMMUNICATION AGENDA TITLE, Contract Change Order No. 2 - DeBenedetti Park/G-Basin Project Design MEETING DATE- February 5, 2003 PREPARED BY_ Parks and Recreation Director RECOMMENDED ACTION: That the City Council be informed of Change Order No. 2 for DeBenedefti Park/ -basin Project Design. BACKGROUND INFORMATION- Resolution No. 85-173 specifies that contract change orders may be approved by the City Manager and that the change order and amount will be reported to the City Council. The Resolution is attached for review and information. Contract Change Order No. 2 for the DeBenedetti Park design project in the amount of $39,300 is attached. The Change Order details are attached as well. In summation, the design work on this project has been proceeding with the project to move forward in three distinct steps or phases. They are: Phase I - Mass Grading Phase I — Park Construction Phase 11 — Park Construction As YOU may recall, this project site is 49 acres and will serve as a drainage basin and outdoor, lighted athletic fields and support facilities. As noted above, the first step will be let a contract for mass grading to proceed with removal of a very large volume of dirt from the site. It is anticipated that the more time which can be allowed for the dirt removal that the more cost effective to the City the contract may be. Attached is the concept plan for the project which was approved by Council. The change order which is attached will benefit the project in several ways. They are: The low flow area will be expanded to the west and one football field will be eliminated. This expansion of the low flow area will allow for a dramatic increase in water storage. Other athletic field surfaces will benefit due to less flooding. This will also allow for several retaining ells to be eliminated from the project design. Although this change to the project will also result in two trees being removed it is recommended due to the benefits to the overall project. This expansion of the low flow area and elimination of the football field has been reviewed by staff, potential user groups, and the Parks and Recreation Commission and is recommended for the project, APPROVED� _Akcg!�� x Iynn -- City Manager CITY OF LODI COUNCIL COMMUNICATION The project design change will result in several athletic fields being built at grade (on high ground), Some re -positioning of the field features will also occur which will allow for walkways and turf areas to blend weR with anticipated street improvements. As design work submittals of 50% completion have occurred, the change order will include adjustments to plans prior to the 90% submittal. No additional allocation of funding is required for the change order, The Council has allocated $6261,500 for this project design work which includes a contingency amount which wilt cover the cost of this Ghange order, It is anticipated that the mass grading design work will be completed soon so that a bid process can occur and thus begin the dirt excavation step of the project quickly, None required. The Change Order amount of $39,300 will be paid out of the prior Council approved appropriation of $626,500 for design work for the project. Richard Prima Roger ltz .m" Public Works Director Parks and Recreation Director RB�fl r -c: City Attorney APPROWD- H. Dixon Flynn -- City Manager OV27 F RESOLUTION NO. 85-173 R� SOLVM, that the City Council of the City of Lodi does hereby adopt a fox7ml policy and procedure to govern contract change orders as shown on iibit "A" attached hereto and thereby made a part hereof. Date. December 4, 1985 I hereby certify that Resolution No. 85-173 was passed and adopted by the City Council of the City of Lodi in a Regular Meeting held December 4, 1985 by the following vote: AYES: Council. Members - Olson, Pinkerton, Reid, Snider and RinchTen (Mayor) NOES. Council Members - None ABSE�T: Go=cil Mmbers None ABST.kINm Council €ber w None 4 ALICE M. REIMCHE City Clerk To establish formal policy and procedures to govern contract change orders. Definition As. us.ed in this policy, a change order shall mean a written order to change the amount of work to be done on a formal contract awarded by the City Council which is anticipated to result in an increase or decrease in contract price. Change orders may not inQrease or change the scope of the project specified in the contract plans and specificat-ions approved by the City Council. Department Head Authority The re5ponsible Department Head shall be authorized to approve and issue individual change orders to increase the contract price up to $5,000 or 10% of the formal contract, whichever is larger, The aggregate total of all change orders to each contract may not exceed $25,000. Authority: of the City Manager The City Manager may authorize change orders in excess of 10% of the formal contract or in excess of $25,000 to avoid extraordinary delay of work or to protect the safety of human life and the environment at or near the work site. The City Manager shall report the change orders and the amounts to the City Council at its next regular meeting. Procedure written change orders shall be submitted to the Finance Department to be added to the construction contract and encumbered against the specific appropriation prior to payment to the contractor. In the event unencumbered funds are not available a special allocation must be processed to increase the applicable appropriation. Sheet 1 of 4 Date 01/15/03 Account No1211717 PRO,1 CT: DeBenedefti Park resign Project CONTRACTOR: Stantec, Consulting, Inc. You are directed to make the following changes or do the following Mork not included in the scope of work on this contact. -___-----v____._________________.-____.__._-__-__—_ee_---------.-___-.___-__.------_____-____--__-__---_-_------_--__--. Description of work to be dome, estimate of quantities, and prices to be paid. Specify whether additional work is at contract prig.; agreed price, or force account. Unless otherwise stated, rates for rental of equipment cover only such time as equipment is actually used and no allowance will be made for idle time. Provide for continued design of the project: .Changes to lass Grading Plan Final Coign Grading Construction Documents Lighting Design Redesign Tat Lot/Play yard Additional Meetings as indicated and incorporated on Exhibit A, attached. Original; contract price Total cost of this change. order NOT TQ EXCEED Previous change orders Total cost of all change larders to date Contract price, including all change orders, will be Time of completion will be adjusted as follows; N/A Submitted by: Approval recornme Agreed upon price: $39,300 TOTAL $39, 300 PERCENT OF CONTRACT $4934936 $ 39,399 8% $ 81,500 17% $120,840 25% $613,836 Date Cate Approved, Parks and Recreationit G, br _ Date --L- f Approved, public Works Director ' 6 (�n Date*Ie Approved, City Manager Dat The under -signed contractor, having carefully considered the change proposed, agrees, if this proposal is approved, to provide all equipment, furnish all materials, except as otherwise noted above, perform all servicers necessary for the work above specified, and accept as full payment the prices shown above. ACCEPTED; bate: Cantractor_Stae a ntec,Consulting, Inc. By Tifle Stantec Consulting Inc. 2590 Ven'turp Oaks Way Sif ramento CA 95833 Tel: (916) 925-555G Fax: (916) 92i-9274 stanW.coT January 14, 2003 He' 843 00103 City of Lodi Parks and Recreation Department 125 North Stockton Street Lodit CA 95240 Dear Roger: I i F 1 11 1 1 1 1 1 1 1 1 11 1 1 1 M�* �-�,, . 1 1111 111111111111111 1111 R11111 111 111 RECEIVED, PARKS & RECREATIO(� Tel: (916) 925-5550 Fax: (916) 921-0274 ,fpostiewait@st, ntec.com I am in receipt of your letter of January 2, 2003 — responding to our most recent change order request. It appears that we are now on common ground with the City as to the required Scope of the additional services. The following updated table summarizes the out of scope design services as we currently see them: a Changes to Mass Grading Plan The mass grading plan will be redesigned to reflect City comments. The low flow area. will be increased in surface area (eliminating a football field) and decreased in depth. All baseball facilities will be left at grade. Additional storage will also be obtained by continuing some excavation outside of the property boundary as defined by the street right-of-way information the City recently provided. The topsoil storage area will be redefined. The changes to this III will be presented to the City as a part of the forthcoming 90% submittal, 1=7 January 14, 2003 Roger Saltz Page 2ref3 Reference, D.ebenedetti Park 41 Final Design Grading $10,000 Soccer fields will be regraded to reflect a 1.5% cross slope running from east to unrest with an earthen berm separating the two fields. The soccer fields will be at different elevations from each other. All of the baseball fields will be designed with a crown in the middle and 1% (max,) cross slopes, Retaining walls shall be removed. Subsurface 1 drainage systems will be added to all of the fields as required. The low flow area will be expanded and the access will be redesigned to reflect the new configuration, All ballfields will move to take advantage of the expanded boundary and reduced grading slopes, where applicable. Tops and toes of all excavated areas will also change. Pathways and sidewalks shall be relocated and re -graded as appropriate. r Construction Documents ,00 Charges to the construction documents will be made to reflect the changes to the site development boundary and the expansion of the low flog area.. This will include redesign of fencing and walkway layouts, additional planting and irrigation areas, detail design of a new flood control weir structure, and design of subsurface b llfield drainage systems, Specifically, planting, irrigation, layout, drainage and construction detail sheets will need to be modified. Lighting Design 00 Stantec shall coordinate with the electrical engineer responsible for designing lighting configurations outside of the park boundary. It is understood that electrical engineering services for the design of streetlights Acing Louver Sacramento and Century Blvd. is not part of our current Scope of Work. Redesign Tot lot/Play yard _ o charge Tot lot configuration will be redesigned to better serve the project as defined by the new grading arrangement. Two play areas shall be consolidated into one facility and relocated to the northwest quadrant of the ballfield area. m« Additional Meetings $6,500 Project design duration has increased, necessitating the need for l additiona meetings. An additional 4 meetings are anticipated. january 14, 2003 Roger Baltz Page 3 of 3 Reference: Debenedetti Park As we have discussed, please note that in addition to the above Change Order request, a separate Purchase Order is being negotiated with the Department of Public Works for project related hydrological work. Stantec is very much looking forward to resuming the design process for Debenedetti Park and we are looking forward to meeting with the City next week to reevaluate: the project schedule, As always, we appreciate the opportunity of working with the City on. this project, Mark. Hall, ASLA, Stantec, Consulting Inc James Nelson, P.E., Stantec Consulting Inc