HomeMy WebLinkAboutAgenda Report - April 21, 2004 G-02 PHAGENDA ITEM Gr2m
CITY OF LODI
W COUNCIL COMMUNICATION
TM
AGENDA TITLE: Public Hearing to Consider Redesign Concept for C -Basin (Pixley Park) and
the Exchange of Properties with GREM, Inc., to Allow the Relocation of
C -Basin
MEETING DATE: April 21, 2004
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council conduct a public hearing to consider the
redesign concept for C -Basin (Pixley Park) and the exchange of
properties with GREM, Inc., to allow the relocation of C -Basin.
BACKGROUND INFORMATION: The present design concept and approximate 27 -acre configuration
for C -Basin was established by the Council on September 28, 1988.
In addition to the recreation component, the park is required to store
131 acre-feet of storm drainage runoff. The Park, Recreation and
Open Space Plan adopted by the Council on January 19, 1994, designates the site as a 43.7 -acre major
sports field complex for adult softball, soccer and tennis. The Plan identifies a need to acquire an
additional 17.7 acres at this site. However, in subsequent action, the Council decided not to acquire
additional vacant land to the east.
Recreation needs in the area have recently refocused upon development of an adult tournament softball
complex. Due to the longer field dimensions and parking needs required for tournament play, the present
site configuration does not lend itself to that type of use. The present site will accommodate only three
softball fields. The proposed redesigned park/basin concept plan being recommended for Council
approval will provide four softball fields with expanded parking and spectator areas. The storm drainage
storage requirement can be met with either site configuration. The proposed concept plan was approved
by the Parks and Recreation Commission at their December 2, 2003, meeting.
An exchange of property requested by GREM, Inc., would facilitate the proposed concept plan. The
proposed exchange would provide a reconfigured City of Lodi park/basin site having essentially the same
area as the current site but superior dimensions for development of the adult tournament softball
complex. The existing property lines, acreage and ownership for the properties affected by the proposed
exchange are shown on Exhibit A. The proposed property lines, acreage and ownership after the
exchange are shown on Exhibit B. The property lines and acreage of the land to be exchanged are
shown on Exhibit C. The slight differential in the land exchange results from a combination of City
standard design criteria for Auto Mall Drive and fixed intersection locations at Beckman Road and
Pixley Parkway.
To facilitate the proposed land exchange process, GREM, Inc., at its expense and with direction and
review by City staff, has provided the proposed park/basin concept plan. In addition, as part of the land
APPROVED:
CPHLandExchange_ doc
H. DixonTlynn, City Manager
4/14/2004
Public Hearing to Consider Redesign Concept for C -Basin (Pixley Park) and the Exchange of Properties
with GREM, Inc., to Allow the Relocation of C -Basin
April 21, 2004
Page 2
exchange, GREM, Inc., will construct improvements, at its expense, at the new site and deliver to the City
a rough -graded site that will be superior to the existing basin because the entire site will be graded. The
following requirements have been agreed upon by GREM, Inc., and the related improvements are
diagrammatically shown on Exhibit D:
1. Provide engineered improvement plans, specifications, construction cost estimates and a
current geotechnical report for all required improvements, all in conformance with City of Lodi
Public Improvement Design Standards.
2. Perform rough grading construction for the entire park/basin site to final design grades.
3. Construct basin inlet piping from east of Beckman Road to the new basin.
4. Construct basin outlet structure.
5. Construct perimeter fencing around the entire site.
6. Dedicate street and public utility easements on Auto Mall Drive.
7. Install full street frontage improvements (curb, gutter, sidewalk, driveways, utilities, street
lighting and asphalt concrete pavement) in Auto Mall Drive.
GREM, Inc., has also agreed to perform the following services with cost reimbursement by the City from
the Storm Drainage and Parks and Recreation Impact Mitigation f=ee funds:
1. Prepare engineered plans, specifications, and construction cost estimates for the future storm
drainage pump station and inlet structure to allow discharge from the basin to Cluff Avenue.
2. Prepare slope erosion protection, turf and irrigation plans, specifications and construction cost
estimates for the entire Pixley Park site.
3. Construct a temporary inlet channel from Auto Mall Drive to the basin.
In addition to the City improvements described above, staff will discuss with the City Council the
displacement of the model airplane club facilities at Pixley Park. With continued development of the
adjacent property, this use is less viable at this location.
State law regarding disposition or acquisition of park land requires a finding as to General Plan
conformity by the Planning Commission, which was approved by the Planning Commission on
March 10, 2004.
Staff will return to Council at a later date for approval of the improvement agreement(s) covering the
installation of the park site and other public improvements and appropriation of funds for any applicable
reimbursements.
FUNDING: Not applicable.
('da?'4
Richard C. Prima, Jr.
Public Works Director
Prepared by F. Wally Sandelin, City Engineer
RCP/FWS/pmf
Attachments
cc: Interim City Attorney
CPMLandExchange_.doc 4117/2004
CITY OF LODI
PUB L I CWORKS DEPART ME NT
EXHIBIT A
EXISTING LOT LINES
CITY OF LODI
PUB L I CWORKS DEPART ME NT
EXHIBIT B
PROPOSED PROPERTY LINES
CITY OF LODI
PUB L I CWORKS DEPART ME NT
EXHIBIT
LAND EXCHANGE
ERRar
�► _
-----------
CITY
Y'• -•,
i CITY TO G REM
l 7.0 ACRES ,•
!4• '
.[ � - i •Fi
r ...
1 F---1
w 4 6Fr K
Ill 1 -•I �-�u� lL G REM TO CITY,
7.0 ACRES••
ti
E P
!p
�vco
m c
a � v
fn
C3. I C
o l l
I
r.
CITY OF •D
PUB L I CWORKS DEPART ME NT
EXHIBIT D
IMPROVEMENTS
STORM DRAIN PIPE___
FENCE
III I ITE R4 )GRAD NG
Lp
ryi s I , ��R MA I QQ(� ��• ��.-_vim' �.�Y JJJ!!I
g
FRONTAGE
IMPROVEMENTS
� g r
�co�
fn
I C
l l
LARRY C„ HANSEN, Mayer
Mayr P;0-.l..eIni)urEe
SUSAN HFI -CH O�CK
EMILY 110WARD
KLDTH LAND
April 8, 2004
Dale N. Gillespie
--ie Ince
F1,0. Box 1210
Lodi, CA 95241
C T1K 11
OFLODI
C l"Y HALL, 221 WEST VINE: S- RECT
Po. BOX 3006
LODI, CALIFORNIA 95241-1910
(209) 333-6702
I AX (209) 333--6807
rityclri<@fodi.gov
. City Council Public Hearings to consider:
He DIXON FLYNN
City Manager
SUSAN 1, R.ACKSTON
City Clerk
interin-i City Attorney
(1) Appeal received from Key Advertising, Eno., regarding the Planning Commission's
decision, to deny the request of Key Advertising for a Use Permit to allow a 75 -foot -high
electronic display sign and a Variance to double the maximum allowable sign area
troiTj 480 square toe( to 960 square feet to be located at 1251 South BeokmaiI Road
Redesign concept for C -Basin (Pixley Park) and the exchange of properties with
GREM, inc., to allow the relocatiori of C -Basin
This is to notify you that. on April 7, 2064 the City Council voted to continue the
ab ,-e public hearings (pursuant to your request) to April 21, 2004 at 7:00 p.m.
or as soon thereafter as the matter can be heard, in the Council Chambers, at
earn°#egg e Forum, 305 West Eine Street, Lodi,
NOTE: If you challenge the proposed action in court, you may be limited to raising
only three issues you or someone else raised at the public hearing described in
this notice, or in written correspondence delivered to the City Council at., or prior
to, the Publics hearing. Written correspondence for the City Council may be mailed
C/0 The City Cled,�'s Office, 221 West Pine Street, Lodi, California, 952401,
haus d you have any questions, please contact me at 333-6702.
Susan J, Blackston
City Clea
cry: Community Development Director
Public Warks Director
Kell; Higgs, Key Advertising, Inc.
NOTICE OF RE -CONTINUED PUBLIC HEARING,
CITY COUNCIL
CITY OF LODI
NOTICE IS HEREBY GIVEN that the public hea n of the City Council of the City of Lodi
to consider L� �si n_qc�ncqp_tor C-BasinJEL _yx Le I
Eark ars dthe exe
_
QA, Ingtea allow relocation of C -Basin originally scheduled for March 17, 2004 and
continued to April 7, 2004 has been re -continued to April 21, 2004 at the hour of
7.-00 p.m. in the Council Chamber, Carnegie Forum, 305 W. Pine Street, Lodi, California.
Posted .April 8, 2004
C:
SUSAN J. BLACKS 6N
CITY CLERK
Of the City of Lodi