HomeMy WebLinkAboutAgenda Report - January 7, 2004 E-09AGENDA ITEM , 01 CITY OF LODI COUNCIL COMMUNICATION TM AGENDA TITLE: Adopt Resolution Approving the Addendum to the Improvement Agreement for the Public Improvements of Century Meadows Two, Unit No. 4, Tract No. 3272; and Appropriate Funds ($58,400) MEETING DATE: January 7, 2004 PREPARED BY: Public Works Director RECOMMENDED ACTION: That the City Council adopt a resolution approving the Addendum to the Improvement Agreement for the Public Improvements of Century Meadows Two, Unit No. 4, Tract No. 3272, direct the City Manager and City Clerk to execute the addendum to the improvement agreement on behalf of the City, and appropriate funds for the required reimbursement. BACKGROUND INFORMATION: The Century Meadows Two, Unit No. 4 subdivision is located east of Mills Avenue, north of Harney Lane and south of the Century Meadows Two, Unit No. 3 development, as shown on the attached Exhibit A. Resolution No. 2002-252 approving the improvement agreement for the subdivision was approved by Council on December 18, 2002. As a condition of development, the developer, FCB Building Partners I, L.P., is required to complete the installation of street frontage improvements along Harney Lane. At this time, Century Meadows One, Unit No. 2 subdivision east of Century Meadows Two, Unit No. 4, as shown on Exhibit A, is also under construction. When the two subdivisions are complete, the properties at 1683 and 1749 West Harney Lane, APN 058210-03 and 059-210-03, respectively as shown on Exhibit A, will be the only properties on the north side of Harney Lane between Ham Lane and Mills Avenue without street frontage improvements. In order to provide for orderly development and enhance public safety on Harney Lane, staff recommends that the frontage improvements along these properties be completed at this time. The developer of Century Meadows Two, Unit No. 4 has agreed to include the frontage improvements for these properties in their project. The improvements include curb, gutter and asphalt concrete pavement. The developer is eligible for reimbursement by the City for these improvements in conformance with LMC §16.40 Reimbursement for Construction. Staff estimates the cost of the work to be $49,040.74. The developer will be reimbursed based on verified claims for the work done by the developer's contractor when the improvements are complete and accepted by the City. In order to construct the frontage improvements along 1683 and 1749 West Harney Lane, additional street right-of-way dedication on Harney Lane and public utility easements behind the right of way are required from the owner, Nick Farros. The owner has agreed to dedicate the right-of-way (10 feet) in exchange for the frontage improvements. Installation of the frontage improvements will include the relocation of one existing tree, relocation of a wood fence, and installation of a new driveway (to replace the old gate), as shown on Exhibit B. In addition, a chain link fence will be installed along the existing orchard. The cost of the work on the Faros property is estimated to be $9,340.00. The owner will be reimbursed based on verifiable claims for the improvements when the project is complete. APPROVED: xon Ptynn, City Manager CCImpAgreementAddendundoc 12/22/2003 Adopt Resolution Approving the Addendum to the Improvement Agreement for the Public Improvements of Century Meadows Two, Unit No. 4, Tract No. 3272; and Appropriate Funds ($58,400) January 7, 2003 Page 2 The developer has furnished the City with the necessary agreement (Exhibit C) and provided improvement security for the additional work in Harney Lane. Staff recommends that the City Council approve the addendum to the improvement agreement and appropriate the necessary funds to reimburse the developer for the additional Harney Lane street frontage improvements and the owner for the private improvements necessitated by the Harney Lane work. FUNDING: Local Street Impact Fees $58,400.00 Vicky McAthi , Finance Director iIA2 Richard C. Prima, Public Works Dlrecto Prepared by Lyman Chang, Associate Civil Engineer RCPILCIpmf Attachments cc: Senior Civil Engineer Fujitani Senior Civil Engineer Welch FCB Building Partners I, LP !Vick Farros Baumbach & Piazza MmpAgreementAddendum.doc 12122/2003 I U .+ PUBLICCITY OF LODI • . DEPARTMENT mum []BUNNone NINON0Y 2417 EXHIBIT A 1 M �� !!!!!M MM > N 434 402 149"0 M % 1g16 ^,jp'1' 73.ip I Dr. 25,8 2524 � 2530 2536 2550 2560 N Li Boom 2417 EXHIBIT A 1 M �� !!!!!M MM > N 434 402 149"0 M % 1g16 ^,jp'1' 73.ip I Dr. 25,8 2524 � 2530 2536 2550 2560 N Li 2417 EXHIBIT A 1 M �� !!!!!M MM > N 434 402 149"0 M % 1g16 ^,jp'1' 73.ip I Dr. 25,8 2524 � 2530 2536 2550 2560 N I PUBLICCITY OF LODI • . DEPARTMENT Z ZD O m Z Z Z ZD V N FARRO PROPER IES EXHIBIT B EXISTING EXISTING ORCHARD RESIDENCE PROPOSED It FENOCE co- C AIN LINK I`00 FENCE r ------------ PROPOSED PROPOSED R/W _ 10'._.. ...... _.._. -T. NY --_-- EXISTING R/W� 1 DRIVEWAY GATE HARN EY LANE RELOCATE TREE Lv Q Z ZD 0 m Z } z Lu ., ADDENDUM EXHIBIT C to the IMPROVEMENT AGREEMENT for the PUBLIC IMPROVEMENTS of CENTURY MEADOWS TWO, UNIT NO. 4 TRACT NO. 3272 THIS AGREEMENT is made and entered into by and between the CITY OF LODI, hereinafter referred to as "City", and FCB BUILDING PARTNERS I, LP, hereinafter referred to as "Developer". WITNESSETH: WHEREAS, the parties have entered into an Improvement Agreement dated December 27, 2002, which Agreement covers the responsibilities of City and of Developer for the development of Century Meadows Two, Unit No. 4, Tract 3272; and WHEREAS, the Developer is responsible for installation of public improvements fronting the subject subdivision on Harney Lane; and WHEREAS, the City requested that the Developer install additional street frontage improvements on Harney Lane which include curb, gutter, and street pavement along the properties known as 1649 and 1749 W. Harney Lane (APN 058-210-03 and 058-210-04, respectively); and WHEREAS, the City is responsible for reimbursing Developer for the additional frontage improvements along those properties in conformance with LMC 16.40 Reimbursement for Construction; and WHEREAS, the Developer is required to provide additional improvement security as described in the State Subdivision Map Act for faithful performance and payment of all persons performing labor and furnishing materials for the installation of public improvements. NOW THEREFORE, for and in consideration of the acceptance of the dedications offered, and in order to insure satisfactory performance by Developer of Developer's obligations under State law and City code, the parties agree as follows: 1. That this document is considered an addendum to the original Improvement Agreement between the two parties. 2. That the Developer shall install street frontage improvements along the Harney Lane street frontages of the properties at 1649 and 1749 W. Harney Lane, including curb, gutter, sidewalk and street pavement to the centerline of Harney Lane 3. That the Developer will be reimbursed based on verified claims for work done by Developer's contractor when the development are complete and accepted by the City. The estimated reimbursement amount is shown on the attached Billing Schedule Addendum and Cost Estimate for Additional Improvement Security. The reimbursement includes ten percent (10%) for engineering and administration in conformance with LMC 16.40 Reimbursement for Construction. 4. That the Developer shall furnish additional Improvement Security of at least 100% of the estimated cost of the above referenced public improvements for the faithful performance of said work; and an amount equal to at least 50% of the above costs as security for the payment of all persons performing labor and furnishing materials in connection with this agreement as more fully described in the State Subdivision Map Act. impagmt (rev. 12/17/2003) The City has determined these additional security amounts to be as follows: Faithful Performance $49,040.74 Labor and Material $24.520.37 IN WITNESS WHEREOF, Developer and City have caused their names to be hereunto affixed and the City of Lodi has caused its corporate name and seal to be hereunto affixed by its proper officers thereunto duly authorized. FCB BUILDING PARTNERS I, LP Date (CORPORATE SEAL) CITY OF LODI, A MUNICIPAL CORPORATION By: H. Dixon Flynn, City Manager Date ATTEST: Susan J. Blackston, City Clerk Date APPROVED AS TO FORM: Randall A. Hays, City Attorney impagmt (rev. 12/17/2003) City of Lodi Publics Works Department COST ESTIMATE F( ADDITION IMPROVEMENT SECURI Development: Century Meadows Two, Unit No. 4 Acres: 15.15 Developer: FCB Building Partners I, LP Date: 12/15/03 Engineer: Baumbach & Piazza Subtotal $730,859.95 Subtotal $668,777.82 Subtotal Street System $59,292.12 10% Engineering & Administration 5,929.21 Total Street System $65,221.33 Future Park Site Improvements (Parcel"A") TOTAL COST OF PROJECT IMPROVEMENTS A. DEVELOPER COST B. COST OF CITY -FUNDED FACILITIES TO BE BUILT BY DEVELOPER Item Description Quanti Unit Price Total Quanti Total Quantity Total 546.52 Street System 6.33 3459.47 4 Compact Original Ground (0.67') 6,373 SF 0.60 3823.80 5 Aggregate Base, Class II (0.35') 1 Clearing & Grubbing 12.46 AC $500.00 $6,230.00 12.16 $6,080.00 0.3 $150.00 2 Lot Grading 12.49 AC 3,748.58 46,819.76 12.49 46,819.76 0 0.00 3 Roadway Excavation 9,731.48 CY 6.33 61,600.27 9,053.48 57,308.53 678 4,291.74 4 Sawcut & Remove Existing AC (interior) 336 SF 0.75 252.00 336 252.00 0 0.00 5 Sawcut & Remove Existing AC (Harney L• 4,330 SF 0.75 3,247.50 0 0.00 4,330 3,247.50 6 Compact Original Ground (0.50') 24,320 SF 0.28 6,809.60 7,782 2,179.07 16,538 4,630.53 7 Compact Original Ground (0.67') 99,497 SF 0.28 27,859.16 99,497 27,859.16 0 0.00 8 Compact Native Material (0.50') 24,320 SF 0.28 6,809.60 7,782 2,179.07 16,538 4,630.53 9 Aggregate Base, Class II (0.30') 25,348 SF 0.49 12,420.52 25,348 12,420.52 0 0.00 10 Aggregate Base, Class II (0.35') 64,829 SF 0.60 38,897.40 64,829 38,897.40 0 0.00 11 Aggregate Base, Class II (0.50') 2,950 SF 0.71 2,094.50 2,950 2,094.50 0 0.00 12 Aggregate Base, Class II (0.60') 24,320 SF 0.81 19,699.20 7,782 6,303.75 16,538 13,395.45 13 Asphalt Concrete, Type B (0.20') 93,463 SF 0.76 71,031.88 93,463 71,031.88 0 0.00 14 Asphalt Concrete, Type B (0.40') 24,320 SF 1.48 35,993.60 7,782 11,517.97 16,538 24,475.63 15 Rolled Curb, Gutter, & Sidewalk 211 LF 34.00 7,174.00 211 7,174.00 0 0.00 16 Vertical Curb & Gutter 5,575 LF 10.90 60,767.50 5,245 57,170.50 330 3,597.00 17 Sidewalk (4') 5,003 LF 8.00 40,024.00 5,003 40,024.00 0 0.00 18 Meandering Sidewalk (5') 242 LF 25.00 6,050.00 242 6,050.00 0 0.00 19 Curb Return (R=25') Incl. Compaction 2 EA 1,865.00 3,730.00 2 3,730.00 0 0.00 20 Curb Return (R=20') Incl. Compaction 11 EA 1,635.00 17,985.00 11 17,985.00 0 0.00 21 Bow -out Curb Return (R=20') Incl. Compacti, 6 EA 2100.00 12,600.00 6 9810.00 0 0.00 22 Concrete Subgrade Compaction 45,317 SF 0.55 24,924.35 44,492 24,470.60 825 453.75 23 Residential Driveway 1,556 LF 15.00 23,340.00 1,528 22,920.00 28 420.00 24 Commercial Driveway 31 SF 64.50 1,999.50 31 1,999.50 0 0.00 25 Survey Monument 12 EA 230.00 2,760.00 12 2,760.00 0 0.00 26 Sidewalk Dead End Barricade 2 EA 158.00 316.00 2 316.00 0 0.00 27 Dead End Barricade (Standard Plan 139) 3 EA 1,565.00 4,695.00 3 4,695.00 0 0.00 28 Remove Existing Barricade 4 EA 250.00 1,000.00 4 1,000.00 0 0.00 29 Remove Temporary Fire Turnaround 2 EA 500.00 1,000.00 2 1,000.00 0 0.00 30 Street Sign Posts/Block Signs 11 EA 236.00 2,596.00 11 2,596.00 0 0.00 31 Concrete Block Retaining Wall 776 LF 26.00 20,176.00 776 20,176.00 0 0.00 32 Masonry Wall 296 LF 70.00 20,720.00 296 20,720.00 0 0.00 33 Landscaping & Irrigation 2,370 SF 4.00 9,480.00 2,370 9,480.00 0 0.00 34 Pedestal Street Lights (100W) 34 EA 2,360.00 80,240.00 34 80,240.00 0 0.00 35 Street Lights (100W) 1 EA 1,940.00 1,940.00 1 1,940.00 0 0.00 36 Street Lights (250W) 2 EA 1,970.00 3,940.00 2 3,940.00 0 0.00 37 Traffic Striping 1 LS 5,600.00 5,600.00 1 5,600.00 0 0.00 38 Painted Stop Bar & Legend 2 EA 130.00 260.00 2 260.00 0 0.00 39 Regulatory Signs (RI) 2 EA 157.00 314.00 2 314.00 0 0.00 40 Erosion Control/Winterization 1 LS 3,800.00 3,800.00 1 3,800.00 0 0.00 41 G -Basin Excavation 10,390 CY 3.24 33,663.60 10,390 33,663.60 0 0.00 Subtotal $730,859.95 Subtotal $668,777.82 Subtotal Street System $59,292.12 10% Engineering & Administration 5,929.21 Total Street System $65,221.33 Future Park Site Improvements (Parcel"A") 1 Clearing & Grubbing 2.99 AC $500.00 $1,495.00 2 Lot Grading 2.66 AC 3,748.58 9,971.23 3 Roadway Excavation 546.52 CY 6.33 3459.47 4 Compact Original Ground (0.67') 6,373 SF 0.60 3823.80 5 Aggregate Base, Class II (0.35') 6,373 SF 0.60 3823.80 6 Asphalt Concrete, Type B (0.20') 6,373 SF 0.76 4843.48 7 Concrete Subgrade Compaction 3,309 SF 0.55 1819.95 8 Vertical Curb & Gutter 509 LF 10.90 5,548.10 9 Sidewalk (4') 509 LF 8.00 4,072.00 10 Pedestal Street Lights (100W) 2 EA 2,360.00 4,720.00 11 Side Inlet Catch Basin 0.50 EA 850.00 425.00 12 12" Storm Drain 89 LF 21.50 1913.50 13 48" Storm Drain Manhole 0.25 EA 1130.00 282.50 14 6" Sanitary Sewer Pipe 24 LF 21.20 508.80 15 8" Sanitary Sewer Pipe 49.50 LF 23.10 1,143.45 16 Sanitary Sewer Manhole 0.50 EA 1,580.00 790.00 17 10" Water Pipe 127.50 LF 16.00 2040.00 18 4" Water Service w/Meter Box 1 EA 4,000.00 4,000.00 Subtotal $54,680.08 Storm Drain System 0 $0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 0 0.00 Subtotal $0.00 2.99 2.66 546.52 6,373 6,373 6,373 3,309 509 509 2 0.50 89 0.25 24 49.50 0.50 127.50 1 Subtotal Park Site Improvements 10% Engineering & Administration Total Park Site Improvements $1,495.00 9,971.23 3,459.47 3,823.80 3,823.80 4,843.48 1,819.95 5,548.10 4,072.00 4,720.00 425.00 1,913.50 282.50 508.80 1,143.45 790.00 2,040.00 4,000.00 $54,680.08 $5,468.01 $60,148.08 TOTAL COST OF PROJECT IMPROVEMENTS A. DEVELOPER COST I B. COST OF CITY -FUNDED FACILITIES TO BE BUILT BY DEVELOPER Item Description Quanti Unit Price Total Quanti Total Quantity Total 1 12" Storm Drain Pipe 1,773 LF $21.50 $38,119.50 1,773 $38,119.50 0 $0.00 2 15' Storm Drain Pipe 197 LF 21.20 4,176.40 197 4,176.40 0 0.00 3 48" Storm Drain Manhole 6.75 EA 1,130.00 7,627.50 6.75 7,627.50 0 0.00 4 Side Inlet Catch Basin 13.50 EA 850.00 11,475.00 13.50 11,475.00 0 0.00 Subtotal $61,398.40 Subtotal $61,398.40 Subtotal Storm Drain System $0.00 10% Engineering & Administration 0.00 Total Storm Drain System $0.00 Sanitary Sewer System 1 6" Sanitary Sewer Pipe 1,232 LF $21.20 $26,118.40 1,212 $25,694.40 20 $424.00 2 8" Sanitary Sewer Pipe 1,941.50 LF 23.10 44,848.65 1,941.50 44,848.65 0 0.00 3 Sanitary Sewer Manhole 8.50 EA 1,580.00 13,430.00 8.50 13,430.00 0 0.00 4 Sewer Cleanout 1 EA $200.00 $200.00 0 $0.00 1 $200.00 5 Sanitary Service with Cleanout 67 EA 375.00 25,125.00 67 25,125.00 0 0.00 6 Remove Existing Lamphole 1 EA 100.00 100.00 1 100.00 0 0.00 7 Lamphole 1 EA 460.00 460.00 1 460.00 0 0.00 Subtotal $110,282.05 Subtotal $109,658.05 Subtotal Sanitary Sewer System $624.00 10% Engineering & Administration 62.40 Total Sanitary Sewer System $686.40 Water System 1 6" Water Pipe 445 LF $13.50 $6,007.50 445 $6,007.50 0 $0.00 2 8" Water Pipe 2,118 LF 16.00 33,888.00 2,118 33,888.00 0 0.00 3 8" Water Pipe (Cl. 200) 171 LF 16.00 2,736.00 171 2,736.00 0 0.00 4 10" Water Pipe 1,147.50 LF 18.60 21,343.50 1,147.50 18,360.00 0 0.00 5 10" Water Pipe (Cl. 200) 40 LF 19.00 760.00 40 640.00 0 0.00 5 10" Water Pipe Oversizing Costs 1,315 LF 19.00 24,985.00 0 0.00 1,315 3,435.00 6 6" Water Valve 1 EA 550.00 550.00 1 550.00 0 0.00 7 8" Water Valve 17 EA 770.00 13,090.00 17 13,090.00 0 0.00 8 10" Water Valve 7 EA 1,050.00 7,350.00 7 5,390.00 7 1,960.00 9 Fire Hydrant Assembly 7 EA 1,850.00 12,950.00 7 12,950.00 0 0.00 10 Blowoff 3 EA 300.00 900.00 3 900.00 0 0.00 11 Remove Blowoff 5 EA 2,000.00 10,000.00 5 10,000.00 0 0.00 12 1" Water Service w/Meter Box 67 EA 400.00 26,800.00 67 26,800.00 0 0.00 13 1" Water Service w/Meter Box (Hamey Lane 1 EA 400.00 400.00 1 400.00 0 0.00 14 3" PVC Conduit (Irrigation Street Crossing) 180 LF 7.00 1,260.00 180 1,260.00 0 0.00 Subtotal $163,020.00 Subtotal $132,971.50 Subtotal Water System $5,395.00 10% Engineering & Administration 539.50 Total Water System $5,934.50 Total $1,065,560.40 Total $972,805.77 Total Construction Cost Subject to Engineering Fee Calculation (A. Developer Cost) $972,805.77 Less Previousl Total Construction Cost Subjectto Engineering Fee Calculation ($972,805.77) ($82,949.58) TOTAL COST FOR ENGINEERING FEE CALCULATION A. Total $0.00 B. Total $49,040.73 TOTAL ADDITIONAL IMPROVEMENT SECURITY AMOUNTS: Faithful Performance: 100% ofA, B & C $49,040.74 Labor & Materials: 50% of A & B $24,520.37 3INTI2191&Y6la:IBill 4 W_1CCA21Bill 8 Developmen Century Meadows Two, Unit No. 4 Gross Acreage: 15.15 Developer: FCB Building Partners I, LP No. of Units: 60 Engineer: Baumbach & Piazza Date: 12/15/03 DEVELOPER COST CREDITS STREET SYSTEM Reimbursement by City Street Improvements per Item B of attached Cost Estimate for Additional Improvement Security (327004.7720;MTS1014) $ 48,354.34 STREET SYSTEM SUBTOTAL $0.00 $48,354.34 SEWER SYSTEM Reimbursement by City Sanitary Sewer System per Item B of attached Cost Estimate for Additional Improvement Security (327004.7720;MTS1014) 686.40 SEWER SYSTEM SUBTOTAL $0.00 $686.40 DEFERRED DEVELOPMENT IMPACT MITIGATION FEES Police Protection Facilities (12151.6122) 12.16 AC @ $1,130.00 $13,465.98 (12141.6127) $274.82 Fire Protection Facilities (12161.6122) 12.16 AC @ $540.00 $6,435.07 (12141.6127) $131.33 Parks & Recreation Facilities (12171.6122) 12.16 AC @ $11,830.00 $140,975.74 (12141.6127) $2,877.06 Less Future Park Site Improvements (1217004.1836.2400;MPR059) ($60,148.09) General City Facilities (12181.6122) 12.16 AC @ $6,830.00 $81,391.74 (12141.6127) $1,661.06 DEVELOPMENT IMPACT MITIGATION FEES SUBTOTAL $187,064.71 HARNEY LANE LIFT STATION FEES Estimate based on lift station construction cost estimate available $90,387.00 at time of execution of improvement agreement. Actual fee to be determined by City Council and paid prior to project acceptance. TOTAL AMOUNT OF BILLING SCHEDULE ADDENDUM $277,451.71 $49,040.74 ADDITIONAL NET AMOUNT TO BE PAID BY DEVELOPER $228,410.97 TO CITY PRIOR TO PROJECT ACCEPTANCE 1 A RESOLUTION OF THE L TO THE IMPROVEMENT OF CENTURY MEADOW AUTHORIZING THE CITY IMPROVEMENT AGREE FURTHER APPROpi W WHEREAS, Century Meadows Two, Unit No. 4 Subdivision is located east of Mills Avenue, north of Harney Lane and south of the Century Meadows Two, Unit No. 3 development; and WHEREAS, as a condition of development, the developer, FCB Building Partners 1, L4P.,. is reqluire . d to complete the installation of street frontage improvements along Harney Lane; and WHEREAS, at this time, Century Meadows O.ne,.Unit No. 2 Subdivision east of Century Meadows TW6,.Unit. No. 4, as shown on exhibit xhibit A attached, is also under construction, and whoa both subdivisions are complete, the properties at 1683 and 1749 West Harney lLane will beffie onlyproperties on the north side of Harney Lane between Ham Lane and Mills Avenue without street ftontage.improvement.8; and WHEREAS, staff recommends that the frontage improvements along these properties be completed at this is time, and the developer of Century Meadows Two, Unit No, 4 has agreed to include :th . e frontage improvements for these properties in its project; and WHEREAS, the improvements include curb, gutter, and asphalt concrete pavement, and the developer is eligible for. reimbursement by the City for these improvements in conformance with Lodi Municipal Code §16.40 "Reimbursement for Construction"; and WHEREAS, staff estimates the cost of the work to be $49,040.74, and the developer will be reimbursed based on verified claims for the work done by the developer's contractor when the improvements are complete and accepted by the City; and WHEREAS, in order to construct the frontage improvements along 1683 and 1749 West Harney Lane, additional street right-of-way ded ica.ti on on Harney Lane and public utility easements behind the right of way are required from the owner, Nick Farros; and WHEREAS, the owner has.agreed to dedicate the right-of-way (ten feet) in exchange for the frontage improv . ements, which include relocation of one existing tree, relocation of a wood fence, and installation of a new driveway as shown on Exhibit B attached hereto; and WHEREAS, in addition, a chain link fence will be installed along the existing orchard. The cost of the work on the Farro.s property is estimated to be $9,340.00, and the owner will be reimbursed based on verifiable claims for the improvements when the project is complete; and WHEREAS, the. developer has furnished the City with the Addendum Agreement and has provided improvement security for the additional work in Harney Lane; and WHEREAS, staff therefore recommends that the City Council take the following action with regard to the Century Meadows Two, Unit 4, Tract Na. 3272, development: Approve the Addendum to the Improvement Agreement for the Public Improvements of Century Meadows Two, Unit 4, Tract No. 3272, and direct the City Manager and City Clerk to execute the Addendum to the Impr ovement Agreement on behalf of the City; and 2. Appropria.te.$58,400.00 from the Local Street Impact Fees fund to reimburse the developer for.the additional Harney Lanestreet frontage impr . ovements and the owner for the private improvements necessitated by the Harney Lane work. NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Lodi hereby finds as follows: 1 That the Addendum to the Improvement Agreement for the Public Improvement of Century M . eadows Two, Unit 4, Tract No. 3272, is hereby approved and further authorizes the City Manager and City Clerk to execute said Addendum. 2. That. $58,400.00 is hereby appropriated from the Local Street Impact Fees fund to reimburse the developer for the additional Harney Lane street frontage improvements and the owner for the private improvements necessitated by the Harney Lane work. Dated: January 7, 2004 I hereby certify that Resolution No.. 2004-0.4 was .passed. and adopted by the City Council of the City of. Lodi in a regular meeting hold January 7, 2004, by the following vote: AYES: COUNCIL MEMBERS — Beckman, Hitchcock, Howard, Land, and Mayor Hanson NOES- COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS — None ABSTAIN: COUNCIL MEMBERS SUSAN J. BLACKSTON City Clark I U .+ PUBLICCITY OF LODI • . DEPARTMENT mum []BUNNone NINON0Y 2417 EXHIBIT A 1 M �� !!!!!M MM > N 434 402 149"0 M % 1g16 ^,jp'1' 73.ip I Dr. 25,8 2524 � 2530 2536 2550 2560 N Li Boom 2417 EXHIBIT A 1 M �� !!!!!M MM > N 434 402 149"0 M % 1g16 ^,jp'1' 73.ip I Dr. 25,8 2524 � 2530 2536 2550 2560 N Li 2417 EXHIBIT A 1 M �� !!!!!M MM > N 434 402 149"0 M % 1g16 ^,jp'1' 73.ip I Dr. 25,8 2524 � 2530 2536 2550 2560 N I PUBLICCITY OF LODI • . DEPARTMENT Z ZD O m Z Z Z ZD V N FARRO PROPER IES EXHIBIT B EXISTING EXISTING ORCHARD RESIDENCE PROPOSED It FENOCE co- C AIN LINK I`00 FENCE r ------------ PROPOSED PROPOSED R/W _ 10'._.. ...... _.._. -T. NY --_-- EXISTING R/W� 1 DRIVEWAY GATE HARN EY LANE RELOCATE TREE Lv Q Z ZD 0 m Z } z Lu ., CITY COUNCIL LARRY D. HANSEN, Mayor JOHN BECKMAN Mayor Pro Tempore SUSAN HITCHCOCK EMILY HOWARD KEITH LAND CITY OF LODI PUBLIC WORKS DEPARTMENT CITY HALL, 221 WEST PINE STREET P.O. BOX 3006 LODI, CALIFORNIA 95241-1910 (209)333-6706 FAX (209) 333-6710 EMAIL pwdeptQlodi.gov http:k%www.lodi.gov December 31, 2003 H. DIXON FLYNN City Manager SUSAN J. BLACKSTON City Clerk RANDALL A. HAYS City Attorney RICHARD C. PRIMA, JR. Public Works Director FCB Building Partners I, LP Nick Farros Baumbach & Piazza clo Frontiers 1619 W. Harney Lane 323 W. Elm Street 3247 W. March Lane, Ste. 220 Lodi, CA 95242 Lodi, CA 95240 Stockton, CA 95219 SUBJECT: Adopt Resolution Approving the Addendum to the Improvement Agreement for the Public Improvements of Century Meadows Two, Unit No. 4, Tract No. 3272; and Appropriate Funds ($58,400) Enclosed is a copy of background information on an item on the City Council agenda of Wednesday, January 7, 2004. The meeting will be held at 7 p.m. in the City Council Chamber, Carnegie Forum, 305 West Pine Street. This item is on the consent calendar and is usually not discussed unless a Council Member requests discussion. The public is given an opportunity to address items on the consent calendar at the appropriate time. If you wish to write to the City Council, please address your letter to City Council, City of Lodi, P. O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the mail. Or, you may hand -deliver the letter to City Hall, 221 West Pine Street. If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's card (available at the Carnegie Forum immediately prior to the start of the meeting) and give it to the City Clerk. If you have any questions about communicating with the Council, please contact Susan Blackston, City Clerk, at 333-6702. If you have any questions about the item itself, please call Lyman Chang, Associate Civil Engineer, at 333-6800, extension 2665. Richard C. Prima, Jr. Public Works Director RCPIpmf Enclosure cc: City Clerk NCCIMPAGRE£MENTADDENDUM.DOC