HomeMy WebLinkAboutAgenda Report - April 17, 1991I—
r
os
CITY OF LODI
COUNCIL COMMUNICATION
AGENDA TITLE: Contract Change Order - White Slough Water Pollution Control Facility
Capacity Expansion Improvements, 12751 North Thornton Road
MEETING DATE: April 17, 1991
PREPARED BY: Public Works Director
RECOMMENDED ACTION: This item is for information only. No action is required.
BACK'GROUND INFORMATION: This information is being given to the City Council
in accordance with the Contract Change Order policy
approved by Resolution 85-72. One of the requirements of
this policy is that we inform the City Council of all
change orders over $25,000.
This attached contract change order No. 3, approved by the City Manager, was in the
amount of $178,296, -which is 1.84% of the contract. The work includes the removal
and replacement of the heating, ventilating, and air conditioning system and other
required modifications to the administrative building. The time of completion was
not affected by this change order.
A recap of change orders to date is as follows:
Number of
Major Items Amount of Total
Included Change Order
Change Order No. 1 6 (6,530)
Change Order No. 2 4 17,244
Change Order No. 3 2 178,296
Total Contract Change Orders $189,010
The original contract amount was $9,681,218. The contract amount including change
orders is $9,870,228.
FUNDING: $300,000 was budgeted for change orders and other contingencies on the
White Slough Water Pollutionol• ac� expansion project.
O�a L. Ronsko
Pub is Works Director
Prepared by Sharon Blaufus, Administrative Assistant
ttachment
APPROVED
THOMAS A. PETERSON
City Manager
cc.1
CWSWPC22/TXTW.02M (CO.COM' April 9, 1991
CITY OF LODI
PUBLIC WORKS DEPARTMENT CONTRACT CHANGE ORDER NO. 3
Sheet 1 of 1
Date March 6, 1571 --
Account No. 17.2-410.60
PROJECT: White Slough Water Pollution Control Facilities
Capacity Expansion Improvements
CONTRACTOR: Alder Engineering and Construction Co.
3939 South 500 West ;
Salt Lake City, UT 84123 -
f�wj
You are directed to make the following changes or do the followfnq�work;not .included
in the Plans and Specifications on this contract.
------------------------------------------------------------------------ -
Description of work to be done, estimate of quantities, and prices to be^ "
paid. Specify whether additional work is at contract price, agreed
price, or force account. Unless otherwise stated, rates for rental of
equipment cover only such time as equipment is actually used and no
allowance will be made for idle time.
DESCRIPTION OF WORK AND BACKUP DATA IS ATTACHED, WITH THE EXCEPTION OF THE
ARCHITECTURAL DRAWINGS. THESE WILL BE KEPT ON FILE AT WHITE SLOUGH WPCF.
Contract Price, Including All Change Orders, will be: $ 9,870,228.00
Time of completion will be adjusted as follows:- No_change to the Contract Time.
Submitted
-By '1�1Ce, -
----- -��1------------Date
3/-71-71 -------
Percent of
Recommended
i
Date_. 4i
ApprovedXPic
Contract
Original Contract Price
9,681.218.00
na r
`�
over r ar r of 5,000 .or
10°c each CCO or 25, 00 total
Total Cost of This Change Order NOT TO EXCEED
S
178,296.00
Date 4 A 1Q r
T-
1.84 'r
Previous Change Orders
$
10,714.00
Total Cost of All Change Orders to Date
$
189,010.00
1.95 =c
Contract Price, Including All Change Orders, will be: $ 9,870,228.00
Time of completion will be adjusted as follows:- No_change to the Contract Time.
Submitted
-By '1�1Ce, -
----- -��1------------Date
3/-71-71 -------
Approval
Recommended
i
Date_. 4i
ApprovedXPic
Works-Direc r ,� �, t
Date 's-ZS-.lI
Approved
na r
`�
over r ar r of 5,000 .or
10°c each CCO or 25, 00 total
CCOs
.
Date 4 A 1Q r
T-
•••
The undersigned contREXM2,rN'Wfng carefully considered the change proposed, agrees,
if this proposal is approved, to provide all equipment, furnish all materials,
except as otherwise noted above, perform all services necessary for the work above
specified, and accept as full payment the prices shown above.
ACCEPTED: Date
Z��,tI���C�� '� f
Contractor
�� ' v- i 11,1c11z'v N4 �, �(1�"
By l^`
RmLl- ----
Title _ I)VV't
A'VVV-k�--
If the Contractor does not sign acceptance of this order, the, ontractor should
refer to the General Conditions regarding filing a written protest within the
specified time.
Mlil
BLACK @ V EAT %
CONSTRUCTION MEMORANDUM
Lodi, California B&V Project 16390.400
White Slough Water Pollution B&V File 1.5, 9.4
Control Facility March 7, 1991
Capacity Expansion Improvements
TO: Jack Ronsko, Public Works Director, City of Lodi
FROM: Vincent R. Miller, Black & Veatch tk-
SUBJECT: Change Order No -3, Description of Work and Backup Data
A brief description and summary of Change Order No.3 is listed
below and the backup data is attached for your review and
acceptance.
Request for Proposal No. 12, 12A and 12B $ 178,296.00
Control Building Modification.
At the request of the City, the Architectural firm of Morris &
Wenell reviewed for the purpose of value engineering, the
Control Building Modification.
The findings from the Architect's review and recommendations
resulted in B&V issuing to the Contractor, RFP No.12, 12A and
12B.
The major items of work addressed by these RFP's were beyond the
scope of the contract, and are listed below:
1) HVAC sys.:em improvement. The original equipment and
system were outdated, inefficient and/or inoperable,
and the recommendation by the Architect was to install
a new system. Several original work items were
subsequently affected. The roof system was modified to
support the new Air Handling Unit, the acoustical
ceiling was extended to conceal the new ductwork,
resulting in modifications in the lighting system,
etc.
2) Restroom facility. Handicap access was improved
beyond that of the original contract requirement.
The Architectural firm of Morris & Wenell provided the
calculations and drawings for the modifications required. B&V
incorporated these details into RFP No.12 dated 8/31/90, 12A
dated 9/25/90, and 12B dated 10/17/90. In a letter dated
1/10/91, the Contractor submitted a proposed cost of $ 205,676
for the additional work. This proposal was review by the
Architect and a meeting was held 1/30/91, between the Architect,
City, Contractor and Engineer to discuss these items. In a
letter dated 2/20/91, the Contractor submitted a second proposal
for $ 181,324. This was again reviewed by the Architect and was
found to have few exceptions. On 2/28/91, the second proposal
was discussed at a job site meeting between the City, Contractor
and Engineer, and the figure of $ 178,296 was tentatively agreed
upon.
BLACK $ VEATC
Page 2 of 2
B&V Project 16390.400
B&V File 9.4
This item is included in Change Order No.3 as an increase in the
Contract Price of $ 178,296.00, with no change in Contract Time.
VRM/lw
Attachments
cc: F.Forkas, City of Lodi
D.Kerlin, City of Lodi
D.Fryer, Alder Construction