HomeMy WebLinkAboutAgenda Report - April 17, 1991 (63)OF
CITY of Lodi
COUNCIL COMMUNICATION
AGENDA TITLE: Plans and Specifications and Advertisement for Bids for Hutchins
Street Improvements, Pine Street to Lockeford Street
MEETING DATE: April 17, 1991
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council approve the plans and specifications for
the above project and authorize advertising for bids.
BACKGROUND INFORMATION: This project will install 30" storm drain pipe in Hutchins
Street from Pine Street to Elm Street, place a pavement
reinforcing fabric and an asphalt concrete overlay on
Hutchins Street from Pine Street to Lockeford Street,
install six wheelchair ramps, and other miscellaneous and related works. The storm
drain installation and the paving operation for this project wil' require that
Hutchins Street be closed from Pine Street to Lockeford Street.
FUNDING: Originally Budgeted: 1987, 1990
Budgeted Fund: Master Drainage Program Fund, Transportation
Development Act, Special State Fund
Current Appropriation: $187,000
Total Project Estimate: $187,000
Bid Opening Date: May 8, 1991
-, �1
Jac L. Ronsko
Public Works Director
Prepared by Lyman Chang, Junior Civil Engineer
Lr--
JLR/LC/mt
cc: Purchasing Officer
Street Superintendent
APPROVED. _
THOMAS A. PETERSON
City Manager
CC -1
CHUTCH2/TXTW.02M (CO.COM) April 9, 1991