(CITY OF LODE COUNCIL COMMUNICATION
AGENDA TITLE: Acceptance of Improvements Under Industrial Substation
Construction Contract (EUD 89-18)
MEETING DATE: March 6, 1991
PREPARED BY: Electric Utility Director
RECOMMENDED ACTION: That the City Council accept the improvements under
Industrial Substation Construction contract and direct the
Electr-c Utility Director to file a Notice of Completion
with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Kinetic Engineering 8
Construction Inc., Loomis, CA, in joint venture with Chapek
Construction, Sacramento, CA, on January 17, 1990, in the
amount of $1,790,514 with subsequently approved Change
Orders (3) bringing the final contract price to $2,101,713. The contract has been
completed in substantial conformance with the plans and specifications approved by
the City Council.
The contract completion date was January 11, 1991, and the actual completion date
was January 4, 1991.
FUNDING: Funding for this project has been made
available from the Department's reserves.
4tn `,
enryRicer•
Electric Utility Director
Prepared by: Hans Hansen, Assist. Elec. Utility Director
cc: Assist. Electric Utility Director
Purchasing Officer
Power Engineers, Inc.
APPROVED'-.c—
THOMAS
PPROVED:THOMAS A. PETERSON
City Manager
CCEUD89.18/CO.COM CC''