HomeMy WebLinkAboutAgenda Report - August 4, 1993 (42)OCIN OF LODI COUNCIL COMMUNICATION
AGENDA TITLE: Acceptance of Improvements Under Poplar Street Wastewater Pipe
Improvement, Cherokee Lane to Central Avenue Contract
MEETING DATE: August 4, 1993
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "Poplar
Street Wastewater Pipe Improvement, Cherokee Lane to Central
Avenue" contract, and direct the Public Works Director to file
a Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Jardin Pipeline, Inc., of
Hayward on August 19, 1992, in the amount of $111,900.00.
The contract has been completed in substantial conformance
with the plans and specifications approved by the City
Council.
The contract completion date was February 2, 1993, and the actual completion date
was February 2, 1993. The delay in accepting the project was caused by two unpaid
bills from the City. One bill was for repair work done by the Water Division on a
water main broken by the Contractor. The second billing to Jardin Pipeline was for
the Public Works Inspector's weekend overtime work. The cost for both billings will
be deducted from the Contractor's retention.
The final contract price was $131,222.21. The difference between the contract
amount and the final contract price is mainly due to additional work done on
Cherokee Lane to avoid existing utilities.
FUNDING: Originally Budgeted:
Budgeted Fund:
Current Appropriation:
Total Project Estimate:
1992/93
Sewer Capital Outlay Fund
$150,687.85
$145,000.00 l
Jac Leit,
. Ronsko
ub 'c Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLR/WKF/lm
cc: Purchasing Officer
Water/Wastewater Superintendent
APPROVED
THOMAS A. PETERSON 'ecyc4d cave,
City Manager
CC -1
CPOPLAR.2/TXTW.02M (CO.COM) July 28, 1993