CITY OF LODI
COUNCIL COMMUNICATION
AGENDA TITLE: Acceptance of Improvements Under Well 4R Drilling, X215 Thurman Road
Contract
MEETING DATE: July 21, 1993
PREPARED BY: Public Works Director
RECO14MENDED ACTION: That the City Council accept the improvements under the
"Well 4R Drilling, 1215 Thurman Road" contract, and direct the
Public Works Director to file a Notice of Completion with the
County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Clark Well, Inc., of
Stockton on April 7, 1993 in the amount of $85,945. The
contract has been completed in substantial conformance with
the plans and specifications approved by the City Council.
The contract completion date was June 30, 1993. The final cor'ract price was
$86,445. The difference between the contract amount and the final contract price is
mainly due to extra well development time.
FUNDING: Originally Budgeted:
Budgeted Fund:
Current Appropriation:
Total Project Estimate:
Bid Opening Date:
1990
Water Capital Fund
$248,000
$110,000 (this phase)
March 17, 1993
6ac
a"
L. Ronsko
is Works Director
Prepared by Mark J. Lindseth, Associate Civil Engineer
141
JLR/MJL/lm
cc: Purchasing Officer
APPROVED--4�w
•
THOMAS A PETERSON ,er.yc!ee doer
City Manager
J
CC -1
CWELL04R.2/TXTW.02M (CO.COM) July 9, 1993