HomeMy WebLinkAboutAgenda Report - March 3, 1993 (89)� OR
CITY OF LODE
-COUNCIL COMMUNICATION
AGENDA TITLE: Acceptance of Improvements Under Well 3-R Drilling, 144 South Rose
Street (Southwest Corner of Hutchins Street Square) Contract
MEETING DATE: March 3, 1993
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the
"Weil 3-R Drilling, 144 South Rose Street (Southwest Corner of
Hutchins Street Square)" contract, and direct the Public Works
Director to file a Nctice of Completion with the County
Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Maggiora Bros. Drilling, Inc.,
of Watsonville, on September 2, 1992, in the amount of
$68,370.00. The contract has been completed in substantial
conformance with the plans and specifications approved by
the City Council.
The actual completion date was February 9, 1993. The final contract price was
$80,972.50. The difference between the contract amount and the final contract price
is mainly due to extra work required in developing the well.
FUNDING: Originally Budgeted: 1992
Budgeted Fund: Water Utility
Current Appropriation: $230,000
Total Project Estimate: $280,000
Bid Opening Date: August 19, 1992
Prepared by Mark Lindseth,
JLR/ML/lm
6ubl-J-4e�--z
L. Ronsko
c Works Director
Associate Civil Engineer
cc: Purchasing Officer
Water/Wastewater Superintendent
Community Center Director
APPROVED .---�—f
THOMAS A. PETERSON Iecyaw Papel
` 1" iy Manager J
CWELL3R.4/TXTW.02M (CO.CON)
CCA
February 22, 1993