CITY OF LODI
00
COUNCIL COMMUNICATION
AGENDA TITLE: Acceptance of Improvements Under Aboveground Vaulted Fuel
Storage Tank, 125 North Stockton Street, Contract
MEETING DATE: February 17, 1993
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the
"Aboveground Vaulted Fuel Storage Tank, 125 North Stockton
Street" contract, and direct the Public Works Director to file
a Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to SEMCO of Modesto, California,
on September 2, 1992, in the amount of $14,543.65. The
contract has been completed in substantial conformance with
the plans and specifications approved by the City Council.
The contract completion date was December 15, 1992, and the actual completion date
was January 21, 1993. The final contract price was $15,710.65. The difference
between the contract amount and the final contract price is mainly due to adding
another shutoff switch with some additional wiring, and equipping the gas pump with
Phase II Recovery hardware to conform to the San Joaquin County Air Pollution
Control District's regulations.
FUNDING: Originally Budgeted:
Budgeted Fund:
Current Appropriation:
Total Project Estimate:
Bid Opening Date:
1989/90
Capital Outlay Reserve
$29,850.86 (March 1992)
$18,500.00 (this phase)
August 19, 19
ensko
ks Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLR//lm
cc: Purchasing Officer
Parks and Recreation Director
Building and Equipment Maintenance Superintendent