HomeMy WebLinkAboutAgenda Report - January 6, 1993 (68)� os
CITY OF LODI
COUNCIL COMMUNICATION
AGENDA TITLE: Contract Award for Construction of Berms and
Transformer Pad (EUD 92-9)
MEETING DATE: January 6, 1993
SUBMITTED BY: Electric Utility Director
RECOMMENDED ACTION: That the City Council adopt the attached resolution
awarding the contract for construction of oil containment
berms and transformer pad to the low bidder, Case
Construction Co., Inc., Lodi, California in the amount of
$45,153.00.
BACKGROUND INFORMATION: On December 3, 1992, the City Council approved specifica-
tions and authorized advertisement for bids. Bids were
opened on December 22, 1992 with the following results:
Case Construction Co., Inc. $45,153.00
H. Max Lee, Inc. 55,300.00
Neth Construction, Inc. 58,670.00
Diede Construction, Inc. 64,882.00
The oil containment structures will be installed at McLane Substation around oil -
filled electrical equipment to confine an oil spill or leak. Recent Environmental
Protection Agency regulations require that equipment storing oil in volumes, as in
this case., be equipped with a confinement system that will prevent an oil spill or
leak to extend beyond the immediate area of the equipment and not migrate into the
soil, the water table or the site drainage system.
The transformer pad will be constructed for the recently purchased McLane Substation
No. 1 bank transformer.
FUNDING: Included in the Department's 1992-93 fiscal year budget
4!: -_ i ��k
Henry J. Ce�
Electric Utility Director
Prepared by: Mel Grandi, Electrical Engineer
c: City Attorney
Assist. Electrical Utility Director
Electric System Supervisor
Purchasing Officer
00
APPROVED L. — {/� bz -- — — Lw►
THOMAS A. PETERSON recyciea paper
City Manager
CCEUD92.9A/CO.COM CC -1
RESOLUTION NO. 93-1u
A RESOLUTION OF THE LODI CITY COUNCIL
AWARDING THE CONTRACT FOR CONSTRUCTION OF OIL CONTAINMENT BERMS
AND TRANSFORMER PAD FOR THX ELECTRIC UTILITY DEPARTMENT
(EUD 92-9)
xxxxaxxassxxssxssxxxaxasxxaxaxxxasxasxssa:xxssssxxsasaxaxasssaaxsaxxass
WHEREAS, in answer to notice duly published in accordance with
law and the order of this City Council, sealed bids were received and
publicly opened on December 22, 1992 at 11:00 a.m. for the contract
for construction of oil containment berms and transformer pad for the
Electric Utility Department, described in the specifications therefor
approved by the City Council on December 3, 1992; and
WHEREAS, said bids have been compared, checked, and tabulated and
a report thereof filed with the City Manager as follows:
Case Construction Co., Inc. $45,153.00
H. Max Lee, Inc. 55,300.00
Neth Construction, Inc. 58,670.00
Diede Construction, Inc. 64,882.00
WHEREAS, the City Manager re:ommends that award of the contract
for construction of oil containment berms and transformer pad be made
to the low bidder, Case Construction Co., Inc.;
NOW, THEREFORE, BE IT RESOLVED by the Lodi City Council that
award of contract for construction of o,' e-ontainment berms and
transformer pad be and the same is hereby aw.:ded to Case Construction
Co., Inc., the low bidder, in the amount of $45,153.00.
Dated: January 6, 1993
I hereby certify that Resolution No. 93-10 was passed and
adopted by the Lodi City of Lodi in a regular meeting held January £,
1993 by the following vote:
Ayes: Council Members - Davenport, Mann, Sieglock, Snider and
Pennino (Mayor)
Noes: Council Members - None
Absent: Council Members - None/�����