HomeMy WebLinkAboutAgenda Report - April 21, 1993 (64)CITY OF LODE COUNCIL COMMUNICATION AGENDA TITLE: Consider and Select Option for Peach Street Improvements, Cochran Road to Tokay Street MEETING DATE: April 21, 1993 PREPARED BY: Public Works Director RECCMMENDED ACTION: That the City Council approve Option 2 including establishment of a "no-parkirg" zore on the east side of the street to be in-plemented upGn cccspletior of the iwproven:erts. BACKUKUI C IKFORNATIOh: This Frc'Ject hes Frompteri by testincr:v frena arFa residerts during the public hearings or: the expansion. of tke Twir Arbors Athletic Club on Cochran Road. School children and others walk on Peach Street between the residential area south of Tokay Street to Vinewood School and Park. Peach Street was already developed with homes when it was annexed many years ago. Shortly after annexation, an assessment district was formed to install only water and sewer lines for the homes. The street is approximately 24 feet wide with no shoulder improvements. Many residents felt this was a hazard to pedestrians and bicyclists (see Exhibits A and B). Prior to starting the design of the project, staff wished to notify the residents and review the project with the Council. Three improvement opticns have been identified: 1. This option includes installing new curb, gutter, sidewalk and paving on the east side, and installing four street lights on Peach Street. (Exhibit C) 2. This option includes paving and a raised curb on the east shoulder of Peach Street to provide drainage and a walkway. Street lights are also included in the estimate. (Exhibit D) 3. This option includes reconstructing pavement with asphalt concrete and new base, installing new curb, gutter, and sidewalk on both sides of the street, and installing street lights. (Exhibit E) Estimates for each option are shown in Exhibit F. Although 3,000 square feet of asphalt will eventually be replaced with curb, gutter and sidewalk in Option 2, this is the option being recommended. APPROVED: THOMArrlTTERSON City Manager J CC -1 CPEACHST/TXTW.02M (CO.COM) April 13, 1993 Consider and Select Option for Peach Street Improvements, Cochran Road to Tokay Street April 21, 1993 Page 2 The 1992/93 Street Capital Improvement Program, approved by the Council last year, included $23,000 for Option 2. Since the improvements under Options I and 3 are normally borne by the property owner, staff felt it was inappropriate to recommend additional taxpayer funding for these improvements. In addition, three of the four curb return installations will require additional right-of-way. If Option 2 is selected by the Council, it will be necessary that the east side of Peach Street be designated a "no -parking" zone to be implemented upon completion of the improvements. A resolution will be required for establishment of the "no -parking" zone (see attached draft). FUNDING: Measure K Ronsko Public Works Director Prepared by Wesley K. Fujitani, Senior Civil Engineer JLR/WKF/lm Attachments cc: City Attorney Peach Street residents CPEACHST/TXTW.02M (CO.COM) April 13, 1993 CITY OF LODI PUBLIC WORKS DEPARTMENT Nr I al wr . s' r t J I at I 3 r Twil~ 3.a, VIG1�-IiTY MAS' Exhibit A r -/q I 1 Exhibit B CITY OF LODI PUBLIC WORKS DEPARTMENT 5/Rt .� Exhibit Cl to r- —• o H 0 r � --- to r- i OH NVHH000 I ` - N O H EL ZS AVN01__-- 1 I 1 I 1 1 i 1 > w o H n`vz a 1 1 r ui ui W iii 1 1 N 1 K W 1 ui -- 1 J a � --_--__-__ ' f . i 1 ! I 1 I 1 � • 1 .. ,� f • to ! 1 i 1 t I �• I I 1 ° I OH NVHH000 I ` - Exhibit E m H 1S AVNOI f 1 v 1 --- o j , r 1 0 r 1 � 1 - 1 : N A T 1 t •O N n 1 � " W V � J _ w { { 1 0 1 s s I ,p 1tu t � t t 1 1 t 08 NVUH000 1 based on 4I5 feet of frontage on the east side of Peach Street ' based on 830 feu of frontage on both sides of Peach Str; -t Estimates include 105E for engineering and 205E contingencies_ YEACHSTALS ExhiMt F Peach St. Improvement Estimates 1. Improve East Side Curb, gutter, drainage, paving 519,000 approx. $45.80 per front foot' Sidewalk $6,000 approx. $14.50 per front foot' Street Lights $7,000 approx. $8.40 per front foot2 Total: 532,000 $68.70 2. Pave Shoulder on East Side Paving & drainage $15,000 approx. $36.10 per front foot' Street Lights 1 57,000 approx. $8.40 per front foot' Total: $22,000 $44.50 3. Improve Both Sides & Reconstruct Street Curb, gutter, drainage, paving $54,000 approx. $65.10 per front foot2 Sidewalk $12,000 approx. $14.50 per front foot2 Street Lights $7,000 approx. $8.40 per front foot2 Total: $73,000 $88.00 based on 4I5 feet of frontage on the east side of Peach Street ' based on 830 feu of frontage on both sides of Peach Str; -t Estimates include 105E for engineering and 205E contingencies_ YEACHSTALS RESOLUTION NO. 93-_ azzasas¢:ssssasssaas�s A RESOLUTION OF THE LODI CITY COUNCIL APPROVING THE INSTALLATION OF A "NO PARKING" ZONE ON THE BAST SIDE OF PEACH STREET BETWEEN COCHRAN ROAD AND TOKAY STREET xxasxxxxxaxxxxxx ansa xsx azazzzxasxaaasaszaaza xaaa saxxax xaaaaazsaassasxss BE IT RESOLVED, that the Lodi City Council does hereby approve the installation of a 416 -foot "No Parking" zone on the east side of Peach Street between Cochran Road and Tokay Street, as shown on Exhibit A attached hereto and incorporated herein by reference. Dated: , 1993 aassesaaxasaes=aasssaeaasaaazaseanexxzxaaasssx=_-saaess:asza: _zaaaasssa I hereby r-srtify that Resolution No. 93- was passed and adopted by the City Council of the City of Lodi in a regular meeting held 1993 by the following vote: Ayes: Council Members - Noes: Council Members - Absent: Council Members - Jennifer M. Perrin City Clerk 93- RES93E/TXTA.01V r CITY Co vvCIL PHILLIP A PE..NItip mj%or JACK A SIECLOCK ♦favor Pro Tempore RAY C DAVESPORF SrEPHE'Q I ,t1A\N JOHN R (Rand-) SLIDER CITY OF LODI CITY HALL. 221 WEST PINE STREET P O BOX 3006 LODI. CALIFORNIA 95241.1910 (:091 3.34.5614 r 4% !:091 131 April 14, 1993 THOMAS PETERSON cav Manager JENNIFER .M PERRIN cav Clerk 808 MCNATT Coh AtMrnev SUBJECT: Consider and Select Option for Peach Street Improvements, Cochran Road to Tokay Street Dear Property Owner/Resident: Enclosed is a copy of background information on an item that will be discussed at the City Council meeting on Wednesday, April 21, 1993, at 7:00 p.m. The meeting will be held in the City Council Chamber, Carnegie Forum, 305 West Pine Street. You are welcome to attend. If you wish to communicate with the City Council, please contact Jennifer Perrin, City Clerk, at (209) 333-6702. If you have any questions about the item, please call Wes Fujitani or me at (209) 333-6706. Jack\L. Ronsko ubl' Works Director JLR/lm Enclosure cc: City Clerk NPEACHST.NCC/TXTW.02M &NAME &ADD &CITY MR EARL MOORE 700 PEACH ST LODI CA 95242 MR & MRS MICHAEL DROVIN 701 PEACH ST LODI CA 95242 JERRY MANZEL 711 PEACH ST LODI CA 95242 MR & MRS SCOTT DASKO 712 PEACH ST LODI CA 95242 MRS ROSE GIER 717 PEACH ST LODI CA 95242 MR RUDY SAUSEDA 718 PEACH ST LODI CA 95242 MR & MRS JOHN KEAGY 731 PEACH ST LODI CA 95242 MRS ANN CARLIN 2041 COCHRAN RD LODI CA 95242