HomeMy WebLinkAboutAgenda Report - May 5, 1993 (57)OF
4�
CITY OF LODI COUNCIL COMMUNICATION
T4s
AGENDA TITLE: Contract Change Order - Poplar Street Wastewater Pipe Improvement,
Cherokee Lane to Central Avenue
MEETING DATE: May 5, 1993
PREPARED BY: Public Works Director
RECOMMENDED ACTION: This item is for information only. No action is required.
BACKGROUND INFORMATION: This information is being given to the City Council
in accordance with the Contract Change Order policy
approved by Resolution 85-72. One of the requirements of
this policy is that we inform the City Council of all
change orders over 10% of the contract amount.
The attached contract change order, approved by the City Manager, was in the amount
of $19,322.21, which is 17.3% of the contract. No additional appropriation will be
needed as the contingencies for this project are sufficient to pay for this change
order. The work includes relocating the bore pit and miscellaneous storm drain work
done as part of the project.
Eight working days were added to this project as a result of this change order.
FUNDING: Originally Budgeted: 1991/92
Budgeted Fund: Sewer Utility Fund
Contract Amount: $128,094.21
L,a,�o�
Li Jack L. Ronsko
Public Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLR//lm
Attachment
APPROVED: _
THOMAS A_ PETERSON
City Manager
CiCAI
CPOPLAR.1/TXTW.02M (CO.COM) April 27, 1993
CITY OF LODI
PUBLIC WORKS DEPAR174ENT � CONTRACT CHANGE ORDER NO. 1
Sheet 1 of 1
Date aril 2.7993
Account No. 0.60 -
PROJECT: Poplar Street Wastewater Pipe Improvement
Cherokee Lane to Central Avenue
CONTRACTOR: Jardin Pipeline, Inc.
You are directed to make the following changes or do the following work not included
in the Plans and Specifications on this contract.
Description of work to be done, estimate of quantities, and prices to be paid.
Specify whether additional work is at contract price, agreed price, or force
account. Unless otherwise stated, rates for rental of equipment cover only such
tino as equipment is actually used and no allowance will be made for idle time.
*Relocate bore pit
*Repair catch basin in Cherokee Lane median.
Catch basin was damaged by boring operating.
*Replace storm drain line over sewer line.
*Down time caused by relocation of gas line
and water main.
°Additional work done on sewer laterals
(4 each @ $1,350/lateral)
°Eliminate direct ties to storm drain line
and install storm drain manhole
agreed
upon
price
S 539.69
agreed
upon
price
$1,973.11
agreed
upon
price
$ 362.53
agreed
upon
price
$2,453.87
agreed
upon
price
$5,400.00
agreed
upon
price
$8,593.01
PERCEN"f OF
CONTRACT
Original Contract Price S 111 900.00
Total Cost of This Change Order NOT TO EXCEED $ 19 322.Zl 17.3 %
Previous Change Orders $ -0-
Total Cost of All Change Orders to Date S 17.3 %
Contract Price, including all Change Orders, will be: S 131!222.21_
Time of completion will be adjusted as follows: add 8 working days
Submitted by i Date F -S-93
Approval RecommendedDate
Approved..,Puj�1is hector Date 4--L,
Appro y;� na if over arg o , or each or S25,�L tT COS)
Date 4
Thomas A. Peterson
The under%ignedacawtractor, having carefully considered the change proposed, agrees,
if this proposal is approved, to provide all equipment, furnish all materials, except
as otherwise noted above, perform all services necessary for the work above specified,
and accept as full payment the prices shown above.
ACCEPTED: Date Contractor
By
Title
If the Contractor does not sign acceptance of this order, the Contractor should refer
to Section 4-1.03A of the Standard Specifications regarding filing a written protest
within the specified time.
CC0P0PLA/TXT,.02M