Loading...
HomeMy WebLinkAboutAgenda Report - April 3, 2002 I-02COUNCILCITY OF LODI IL 4J / 1 AGENDA TITLE: Aquatics Facility project review and request for direction MEETING DATE: April 3, 2002 PREPARED BY: Parks and Recreation Director RECOMMENDED ACTION: That the City Council review progress to date on the project and provide direction regarding specific design element components. BACKGROUND INFORMATION: On February 6, 2002, the City Council approved a professional consulting services contract with ELS Architecture and Urban Design (ELS) and allocated $269,075 for the design of an Aquatics Facility project. As a reminder to Council, a project estimate of $3,500,000 was discussed at shirtsleeve sessions last year during consideration of COP financing. Actual costs of the project will depend upon its actual design. Also, staff has attempted to estimate annual operations and maintenance costs but this will also vary depending upon actual design. ELS can conduct a detailed economic analysis upon request and for an additional fee. For our project to date, ELS has provided rough estimates of annual operating subsidies based upon their experiences with other similar facilities. The basic services included in the contract include a scope of servicestwork plan to be performed in phases. The City must approve proceeding with each phase and may elect to terminate services at the end of each phase. The phases are as follows: • Planning Phase • Schematic Design Phase • Construction Documents Phase • Bid and Permit Phase • Construction Phase • Post Construction Phase The City established an ambitious timeline for the construction documents phase and has established a goal for construction documents to be at 90% completion by November 1, 2002. The consulting firm (ELS) has been working for several weeks now and clear direction regarding the elements for the project are needed. Specifically, the schematic design phase will require detailed components identified and clear direction for a preferred site plan. APPROVED: <--; H. Dixon Flynn -- City Manager 03!26102 444 To date a variety of actions have occurred with regards to the project. Per the contract, ELS has been working with a steering committee on the project. This group has included representatives of several City departments (Parks & Recreation; Public Works; Community Development; the City Manager's Office), representatives of the Aquatics Task Force, representatives of the Lodi City Swim Club, and a representative from the Parks and Recreation Commission. Field trips have been taken and items considered have included site location and a wide range of program issues and design ideas. ELS has also met with the Aquatics Task Force and the Board of the Lodi City Swim Club. On March 6, 2002, a public workshop was held at the Lodi City Library to encourage input and ideas for the project. One of the primary issues of discussion has been the question of what the purpose of the facility should be for the community. Recreational needs, instructional needs, and competitive needs have all been a focus. The initial construction cost and the ongoing annual operations and maintenance (O&M) costs have also been reviewed for differing designs. Our process has seen strong support among the advocates of competitive swimming for a 50 meter pool component to be included in the design. Our consultants have indicated that it is recreational and instructional water use which has the greatest cost recovery potential for a facility. With these factors in mind our process has focused upon two plans. One which includes a 25 meter pool and roughly the same amount of recreational/instructional water, and one which includes a 50 meter pool and a strong recreational/instructional pool component. There is a very substantial cost difference both in initial construction costs and then in annual operating costs for the two differing plans. I have attached information which ELS has prepared which provides some of the estimated costs for these two plans. would like to remind all that these are only estimates and will change depending upon the various design decisions which are made. We intend to have ELS in attendance at both the April 2, 2002, Parks and Recreation Commission meeting and the April 3, 2002, City Council meeting to present the project status and answer questions. If the Council is able to provide clear direction on the pool sizes, it will allow schematic work to move forward with one preferred site plan rather than two. FUNDING: None 2 Roger Baltz � Parks and Recreation Director RB:tI cc: City Attorney APPROVED: H. Dixon Flynn -- City Manager 0=6/02 L01 Conmunity Aquatics Facility 25yd x 25m pool ti IA Vine Street Conmunity Aquatics Facility 25yd x 25m pool A I , j ISI $.Axis at&228 ;9 P"" *tall* on Ata"L Vine Street Community Aquatics a- 4J 41 CO Facility 50m. pool City of Lodi Aquatics Facility Planning March 28, 2002 Program and Budget Analysis Fro M 4f L� .3 -070a-6) Recovery Rate 1 55% to 65% 1 70°x6 to 80% Annual Subsidy $175k to $225 $100k to $150k Offsite Improvements Direct frontage only) Surface Improvements t.a 7 Pools and Equipment Sanitary Water $152,960 $35,020 Demand 25 meter x 25 yard (sf) Total Off Site 6,150 50 meter x 25 yard (sf) Rec pool: instruction, slide, wet play (sf) Total Pool Area (so _ _ 12,300 7,300 19,600 7,300 13,450 2,000 2,000 175 to 233 100 to 133 -- Cost $/sf $110 $110 $110 Subtotal -� $2,156,000 $1,479,500 $220,000 Waterslide $150,000 $150,000 _- Wet play structures - -- $100,000 $100,000 Pools Total ---� $2,406,000 $1,729,500 $220,000 Support Buildings 1. Administrative (sf) 1,000 1,000 40 2. Changincl Rooms (sf) 1 3. Concessions (sf) 4. Classroom / Party Room (sf) - 2.800 1 4001 1,300 1.600 4001 0 (400)1 1 5. Pool Equipment (sf) 1,600 1,200 _ 6. Indoor Storage (sf) _ 500 0 7. Covered Bleachers & Breezeway (x 50%) 3,200 1,200 (700) Net Bldg Area (nsf) _ 10,800 5,400 $1,100 Gross Bldg Area (nsf x 1.1 for mech. strut) 11,880 5,940 ($1,210 Cost $/sf $200 $200 $200 Buildinfas Total $2,376,000 $1,188,000 242 000 Sitework" (Design) Hardscape $624,200 $411,500 Softscape --- $299,100 $200,600 Paving $233,340 $194,880 $40,000 1.82_ Underground (incl. dry utilities) $84,340 $82,340 General Conditions (incl. erosion control) $36,500 $36,500 Site Total $1,277,480 $925,820 $40,000 Contingency 16% $908,922 $676,498 ($75,30 Total $6,968,402 $4 419,818 $577 300 Total IncludingFurther Deducts Bud et: 3 842 518 $2,775,000 Recovery Rate 1 55% to 65% 1 70°x6 to 80% Annual Subsidy $175k to $225 $100k to $150k Offsite Improvements Direct frontage only) Surface Improvements $232,810 Storm Drain $185,640 Sanitary Water $152,960 $35,020 General Conditions (Off site) $61,000 Total Off Site 5667.430 ** Earthwork quantities are an allowance only, until property and topographic information is available. Lodi Aquatic Facility PROJECT SCHEDULE Wed 3/27/02 EXHIBIT A ID Task Name Duration 2002 12003 Jan Feb MarlAprkugSep Oct Nov Dec Jan Feb Mar Apr may Jun Jul AugSep Oct Nov Dec 1 City Council Authorization Aquatics Facility Planning Investigation & Site Plan Alternatives Preferred Site Plan Finalize Plan and Report DPR / SteerCom Meetings SteerCom I Task Force Meeting DPR / SteerCom Meetings DPR / SteerCom Meetings Public Meeting P&R Commission Presentation Council Presentation SCHEMATIC DESIGN PHASE Schematic Design Milestone Meetings with DPR Steering Committee Meetings SPARC Presentation P&R Commission Presentation Council Presentation CONSTRUCTION DOCUMENTS DPR Review Funding Target Date PERMIT BIDDING CONSTRUCTION Start Warranty Period Milestone Meetings with DPR 0 days 60 days 18 days 17 days 14 days 0 days 0 days 0 days 0 days 0 days 0 days 0 days 76 days 76 days 0 days 0 days 0 days 0 days 0 days 132 days 7 daysR 0 days 30 days 60 days 335 days 0 days 0 days In , DP . Ste . ♦ stigation & Site Plan Alternatives Preferred Site Plan Finalize Plan and Report 3114 fCom 1 Task Force 2119 PR I SteerCom 315 DPR / SteerCom 3128 irblic Workshop 412 P&R Commission Presentation 413 Council Presentation Schematic Design D IR Meetings . ♦ 3 aercom Meetings t3 SPARC Presentation + /4 P&R Commission Presentation 15 Council Presentation Construction Documents Review ` 10131 Funding Target Date Permit Bidding Construction ♦ ♦ DPR Meetings Start Warranty Period • 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 is 19 20 21 22 23 24 25 26 27 28 29 30 31 Pagel AQUATIC DESIGN GROUP MEMORANDUM DATE: 27 March 2002 TO: David Petta ELS Architects FROM. Randy Mendioroz RE: Lodi Aquatics Complex Cost Recovery Pursuant to your request, we have reviewed the preliminary drawings issued by your office and offer the following opinion of probable cost recovery (percentage of gross revenue compared with operating costs): Base Scheme (25 Yard x 25 Meter Pool with 7,300 SF Recreation Pool): We generally recommend at least a 50/50 split between competition and recreation programming to ensure high cost recovery. Since this scheme is actually 46% competition / 54% recreation we believe that 70-80% cost recovery is achievable, for a total annual subsidy of approximately $100,000 to $150,000. 2. Enhanced Scheme (25 Yard x 50 Meter Pool with 7,300 SF Recreation Pool): Since this scheme is weighted 63% competition / 37% recreation, we would expect 55-65% cost recovery, for a total annual subsidy of approximately $175,000 to $225,000. Please note that these preliminary estimates of cost recovery are based upon our experience with similar facilities statewide and can be extremely subjective. Factors such as local competition, number of operating days, rising energy costs, and methods of operation can produce significant variations in cost recovery ratios. Should the City of Lodi require additional due diligence on this issue, we would recommend that an economist be retained to provide a more detailed analysis of demographics, local competition, projected revenues, projected operating expenses, and ultimately, projected cost recovery. 1950 KELLOGG AVENUE, CARLSBAD, CA 92008 TEL 760.438.8400 FAX 760.438.5251 Memorandum- 26 March 2002 David Petta, ELS Architects RE: Lodi Aquatics Complex Cost Recovery Page 2 of 2 I hope this information is helpful. If you have further questions, please contact me at the earliest convenience. CC: Project File AQUATIC DESIGN GROUP MEMORANDUM DATE: 26 March 2002 TO: David Petta ELS Architects FROM. Randy Mendioroz RE: Lodi Aquatics Complex Pool Construction Costs Pursuant to your request, we have reviewed the preliminary drawings issued by your office and offer the following opinion of probable construction cost: Base Scheme (25 Yard x 25 Meter Pool with 7,300 SF Recreation Pool): We would estimate costs for the 25 yard x 25 meter pool at $676,500 (6,150 SF @ $110/SF); the Recreation Pool at $803,000 (7,300 SF @ $110/SF); and an allowance for waterslide and wet play structure of $250,000 ($150,000 for the waterslide and $100,000 for the wet play structure). This provides for an aggregate total of $1,729,500 for the Base Scheme Pools. 2. Enhanced Scheme (25 Yard x 50 Meter Pool with 7,300 SF Recreation Pool): We would estimate costs for the 25 yard x 50 meter pool at $1,353,000 (12,300 SF @ $110/SF); the Recreation Pool at $803,000 (7,300 SF @ $110/SF); and an allowance for waterslide and wet play structure of $250,000 ($150,000 for the waterslide and $100,000 for the wet play structure). This provides for an aggregate total of $2,406,000 for the Enhanced Scheme Pools. Please note that these preliminary budgets are inclusive of the following: engineered layout; pool and surge tank excavation; pool rough mechanical; pool rough electrical (including rough -in for timing systems); pool and surge tank reinforcing steel; pool and surge tank structures; foundations for waterslide, tower and wet play structure; pool and surge tank finishes (tile and 1950 KELLOGG AVENUE, CARLSBAD, CA 92008 TEL 760.438.8400 FAX 760.438.5251 Memorandum- 26 March 2002 David Petta, ELS Architects RE: Lodi Aquatics Complex Pool Construction Costs Page 2 of 2 plaster for pool, cementitious waterproofing for surge tank); competitive and deck equipment; waterslide structural supports, waterslide tower and wet play structures; pool finish mechanical; pool finish electrical; and clean-up / start-up. Exclusions to these preliminary budgets include: site work and site utilities; building and shade structures; utilities to a P.O.C. within mechanical equipment room; pool decks and deck drainage; landscape and irrigation; site, security and sports lighting; perimeter fencing; site furnishings and spectator seating; and timing system / scoreboard(s). I hope this information is helpful. If you have further questions, please contact me at the earliest convenience. CC: Project File LODI A Q U ATIC S C OMP LEX Parking Standards Parking standards have not been established for this facility type. A generally accepted standard for optimal parking is a ratio of 3 persons per vehicle. With space constraints, some communities have targeted 4:1 with provisions for overflow parking during larger events. Parking demand can also be managed administratively through the scheduling of the facility. The following table provides parking demand based on a conservative 3:1 ratio and the more commonly used 4:1 ratio. Consideration must be given for the change -over when one group of Total Users/Cars 1,140 407 315 Users Per Hour Conservative Estimate Average Estimate Ratio User Number of Ratio User Number of Space Component Peak Time Car Cars Car Cars Competitive Pool 700 3:1 233 4:1 175 Recreation Pool 400 3:1 133 4:1 100 Staff/Service 30 1:1 30 1:1 30 Short Term 10 1 1:1 10 1 1:1 10 Total Users/Cars 1,140 407 315 03/27/2002 16:56 4158366771 SWA:SF March 26, 2002 ELS 2040 Addison Street Berkeley, CA 94704 Attn.: Mr. David Petta Ref.: Lodi Aquatic Landscape, Preliminary Cost Estimate, SWA Job No. ELSN103A David: Attached please find the preliminary cost estimate for the two (2) schemes. Aquatic design is providing the pools, and structural costs for waterslide and footing and all the mech./elec. associated. The comparison In overall sqft. landscape costs are as follows: 1. Basic scheme is :t7.47,/sqft overall, enhanced scheme is roughly VI -V sqft overall. Both without contingency added. 2. Enhanced scheme is: a. both pool areas are depressed requiring more retaining walls at perimeter. b. concrete paving is upscale with color. c. overall, larger tree box sizes are recommended. d. additional site lights are required. e. additional site furniture are required. f. additional railing is required due to added ramps and walls. Please note the items listed under exclusions and we did not provide contingency as requested. Best regards, SWA Grou Roy Imamur , Principal PAGE 02 San Francesco Sausalito Laguna Beach Houston Dallas 630 Mission Street Third Floor San Francisco CA 94103.4015 TO 415.836.8770 Fax 415.836.8771 03/27/2002 16:56 4158368771 SWA:SF PAGE 03 SWA Group — ELSN1O3A Lodi Aquatics Center — Base Scheme Preliminary landscape costs per plan - Developed for 3/28/2002 1. Buildings/Service/Seating 1 8,500 sqft 2. Pools t 13,780 sqft 3. Parking Area t 53,900 sqft 4. Hardscape Area t 36,800 sqft 5. Softscaue Area t 50,000 soft TOTAL Site Area # 162,700 sqft (t 3.7ac) SWA Group —ELSN103A Preliminary landscape cost Base Scheme 1 03/27/2002 16:56 4158368771 SWA:SF Hardscane Concrete paving ( Broom F.) 3,700 0 @ 4.50 - 16,700 Concrete paving @ Veh. (6") 1,650 0 @ 5.00 - 8,300 Concrete paving @ Pool, Main Area 25,650 0 @ 5.50 -141,000 (Sandblast Fin., with glare reducing agent) Concrete seatwall (2' wide) 440LF @ 80.00 - 35,200 Concrete steps 80 0 @ 75.00 - 6,000 Concrete wall (89 (18"high) 15OLF @ 75.00 - 11,300 Precast Concrete bollards 9 each @ 800 - 7,200 Street Lights (30') Standard 5 @ 3,200 - 16,000 Pool Area Pole Lights (301 10 @ 3,500 - 35,000 Parking Area Pole Lights (14') 1502,400 - 36,000 Metal Rail/ Handrail 11OLF @ 50.00 - 5,500 Pool Deck Drains 50 each @ 500.00 - 25,000 Perimeter Metal Fence/ Gates 850LF @ 45.00 - 38,300 Kiosk 1 each @ 10,000 - 10,000 Street Furniture (Allowance) LS - 20,000 Sub, TOTAL 411,500 PAGE 04 5 WA Group — ELS N103A P re llm Inary landscape cost Base Scheme 2 03/27/2002 16:56 4158368771 SWA:SF PAGE 05 Softscaae Trees (36"box) 110600.00 Trees (24"box) 67 @ 275.00 Trees (15 gal.) 56 @ 95.00 - 6,600 - 18,500 - 5,400 Shrub/G.0 Area 14,000 sgft ® 5.00 - 70,000 Lawn (SOD) 22,800 sgftC .70 - 16,000 Lawn (SEED) 13,200 sgftQ .35 - 4,600 Irrigation (AUTO) 50,000 sgft @ 1.50 - 75,000 90 day Maintenance 50.000 soft @ .04 4.500 Sub. TOTAL 200,600 Summary Hardscape 411,500 S oftscage 200,600 Total 612,100 (7A7/sgft) Exclusions: Main drainage structures & lines, parking area paving, curbs/ gutters, public sidewalk, elec. circuitry of site lights, signage / graphics, sculptures / special garden structures, fountains, grading cut/fill, building service area/encl., viewing stands. SWA Group— ELSN103A Preliminary landscape cost Base Scheme 3 03/27/2002 16:56 4158368771 SWA:SF PAGE 07 SWA Group — ELSN103A Lodi Aquatics Center — Enhanced Scheme Preliminary landscape cost estimates per plan - Developed for 3/28/2002 1. Buildings/Service/Seating t 14,000 sqft 2. Pools t 19,780 sqft 3. Parking Area t 54,800 sqft 4. Hardscape Area t 46,700 sqft 5. Softscane Area t 58.500 soft TOTAL Site Area 1193,700 sqft (t 4Aac) SWA Group— ELSN103A Preliminary landscape cost Enhanced Scheme 1 03/27/2002 16:56 4158368771 SWA:SF Hardscane Concrete paving (Broom F.) 3,000 0 @ 4.50 - 13,500 Concrete paving @ Veh. (611) 2,050 0 @ 5.00 - 10,300 Concrete paving @ Pool, Main Area 36,600 0 @ 7.00 -256,200 (Sandblast Fin., with color, saw cutJTS) Concrete seatwall (2' wide) 435LF @ 80.00 - 34,800 Concrete steps 19000 75.00 - 14,300 Concrete wall (89 (18"high) 60OLF @ 75.00 - 45,000 Concrete wall (89 (3'high) 80LF @150.00 - 12,000 Precast Concrete bollards 6 each @ 800 - 4,800 Pedestrian Pole Light (109 202,200 - 4,400 Street Lights (301) Standard 7 @ 3,200 - 22,400 Pool Area Pole Lights (30') 11 @ 3,500 - 38,500 Parking Area Pole Lights (14' 18 @ 2,400 - 43,200 Metal Rail/ Handrail 290LF @ 50.00 - 14,500 Pool Deck Drains 60 each @ 500.00 - 30,000 Perimeter Metal Fence/ Gates 895LF @ 45.00 - 40,300 Kiosk 1 each @ 10,000 - 10,000 Street Furniture (Allowance) LS - 30,000 Sub. TOTAL 624,200 PAGE 08 SWA Group— ELSN103A Prel ImInary landscape cost Enhanced Scheme 2 03/27/2002 16:56 4158366771 SWA:SE PAGE 09 Softscaoe Trees (60"box) 1 @ 3,500 - 3,500 Trees (36"box) 50 @ 600.00 - 30,000 Trees (24"box) 1080275.00 - 29,700 Trees (15 gal.) 17 @ 95.00 - 1,600 Shrub/G.0 Area 23,800 sqft @ 5.00 -119,000 Lawn (SOD) 28,900 sqft @ .70 - 20,200 Lawn (SEED) 5,800 sqft @ .35 - 2,000 Irrigation (AUTO) 58,500 sqft @ 1.50 - 87,800 90 day Maintenance 55,500 sqft @ .09 - 5,300 Sub. TOTAL 299,100 Summary Hardscape 624,200 Softscave 299,100 Total 923,300 (9.21/sqft) Exclusions: Main drainage structures & lines, parking area paving, curbs/ gutters, public sidewalk, elec. circuitry of site lights, signage /graphics, sculptures /special garden structures, fountains, grading cut / fill, building service area / encl., viewing stands. SWAG roup — E LSN103A Preliminary landscape cast Enhanced Scheme 3 03/26/2002 09:01 2093686610 BALHBACH & PIAZZA PAGE 02 QD0W a 323 West Elm U Lodi, California 95240-t u � cg) � U - � 2b03 Phone (209) 560-6618 SAUM 13ACH 8� PIAZZA, ilNe. pax (meg) she-sslo JOB NO. 0208 March 27, 2002 CITY OF LODI PROPOSED AQUATICS CENTER. PRELIMINARY COST ESTIMATE - CIVIL WORK Note: This estimate is based on preliminary Site plan supplied by ELS on March 25, 2002 A_ BASE SCHEME ON-SITE Surface Work 1 Each $3,000.00 $3,000.00 ITEM QUANTITY UNIT TOTAL 1. Parking Asphalt Concrete 180 L.F. $20.00 $3,800.00 Section 53,900 S.F. $2.00 $107,800.00 2. Concrete Curbs 1,715 L.F. $14.00 $24,010.00 3. Earthwork & Mobilization Lump Sum $34,000.00 $34,000.00 4. Site Grading & Compaction 330 L.F. $28.00 $9,240.00 (other than parking area) 58,800 S.F. $0.40 $23,520.00 5. Clearing & Grubbing 3.7 Acres $1,500.00 $5,550.00 Subtotal Lump Sum $8,400.00 $194,880.00 underground 6. 4" Water Service 1 Each $3,000.00 $3,000.00 7. 6" Sanitary Sewer 380 L.F. $17.50 $6,650,00 8. 8" Sanitary Sewer 180 L.F. $20.00 $3,800.00 9. Sewer Manhole 3 Each $1,600.00 $4,800.00 10. 24" Storm Drain Line 75 L.F. $50.00 $3,750.00 11. 15" Storm Drain Line 240 L_F_ $35.00 $8,400.00 12.12" Storm Drain 330 L.F. $28.00 $9,240.00 13, Misc. 10" Area Drain Lines 250 L.F. $20.00 $5,000.00 14_ Drop Inlet Catch Basins 4 Each $750.00 $3,000.00 15. Sand/ail Separator Lump Sum $8,400.00 $8,400.00 Subtotal $55,840.00 TOTAL BASE SCHEME, ON-SITE WORK $250,720.00 B. ENHANCED SCHEME: ON-SITE Surface Imomyernents ITEM QUANTITY UNIT TOTAL 1. Parking Area Pavement Section 54,800 S.F. $2.00 $109,600.00 2. Concrete Curbs 2,070 L.F. $14.00 $28,980.00 3. Earthwork & Mobilization Lump Sum $56,000.00 $56,000.00 4: Site Grading & Compaction 80,400 S.F. $58,000.00 $32,160,00 5. Clearing & Grubbing 4.4 Ac $1,500.00 $6,600.00 Subtotal $233,340.00 03/26/2002 09:01 2093686610 BALiMBACH & PIAZZA PAGE 03 Underground Improvements 6. Base Scheme Underground Lump Sum 7. Additional 10" Area Drain Line 100 L.F. Subtotal TOTAL - ENHANCED SCHEME, ON-SITE WORK C. GENERAL EXPENSE (Design, Staking, Supervision, etc_ for On-site Portion) $55,840.00 $55,840.00 $20.00 $2,000.00 $57,840.00 $291,180.00 $28,000.00 D. OFF-SITE IMPROVEMENTS (Along site frontage based on enhanced scheme only; includes sewer & storm drain pump station) Note: Street work includes full street width to opposite side curb and gutter. Surface improvements ITEMUCS ANTI UNIT TOTAL 1. Curb, Gutter & 5' Sidewalk 810 L.F. $34.00 $27,540.00 2. Curb & Gutter Only 1,005 L.F. $15.00 $16,080.00 3. Special Commercial Driveway 2 Each $3,500.00 $7,000.00 4. Street Pavement Section 44,220 S.F. $2.80 $123,816.00 5. Earthwork Lump Sum $17,000.00 $17,000.00 G. Final Grading & Compaction 52,810 S,F. $0.40 $21,124.00 7. Street Signs Lump Sum $400.00 $400.00 6. Remove Exist_ Barricade 1 Each $500.00 $500.00 Q. Install Dead End Barricade 2 Each $900.00 $1,800.00 10. Street Lights 7 Each $2,250.00 $15,750.00 11. Striping Lump Sum $1,800.00 $1,800.00 Subtotal $232,810.00 Storm Drain Svstem 12. 30 inch Storm Drain 500 L.F. $55.00 $27,500.00 13. 12 inch Storm Drain 180 L.F. $28.00 $5,040.00 14. Storm Drain Manhole 3 Each $1,700.00 $5,100.00 15, Side (nisi Catch Basin 5 Each $900.00 $4,500'.00 16. Storm Drain Pump Station Lump Sum $85,000.00 $85,000.00 17.12" Farce Main 1,000 L.F. $26.00 $26,000.00 18. Bored 12" Force Main 130 L.F. $250.00 $32,500.00 Subtotal $185,640.00 Sanitary Sewer stem 13. Sewer Pump Station Lump Sum $95,000.00 $95,000.00 26. 10" Force Main 1,380 L.F. $22.00 $30,380.00 21. Bored 10" Force Main 120 L.F. $230.00 $27,800.00 Subtotal $152,960.00 03/28/2002 09:01 2093686610 BAUMBACH $ PIAZZA PAGE 04 Water Svstem 22. Remove Existing Blow -off 2 Each $550.00 $1,100.00 .23. 8" Water Main 1,020 L.F. $21.00 $21,420.00 24. Fire Hydrant Assembly 3 Each $2,600.00 $7,800.00 25. 8" Valves 4 Each $850,00 $3,400.00 26. Install Blow -off 2 Each $650.00 $1.300.00 Subtotal $35,020.00 TOTAL - OFF-SITE IMPROVEMENTS ADJACENT TO SITE FRONTAGE PLUS SEWER AND STORM DRAIN PUMP STATIONS $606,430.00 Note: Cost of 30" Storm Drain ($27,500) should be reimbursed as credit toward the master storm drainage development impact fee. E. GENERAL EXPENSE (Design, Staking, Supervision, etc.) for Off-site Portion $61,000.00 ADDITIONAL ITEMS WHICH APPLY TO OVERALL_ PROJECT: F. DRY UTILITIES (Gas, Telephone, CATV, Electrical) $26,500.00 G. EROSION AND SEDIMENT CONTROL $8,500.00 -�L AQUATICS COMPLEX PUBLIC WORKSHOP MARCH 6, 2002 MINUTES Meeting was called to order at 7:02 p.m. by Roger Baltz. • Mr. Baltz opened the meeting with an introduction of the topic and the objectives of the meeting. • Mr. Baltz introduced David Petta and Clarence Mamuyac from ELS; and Randy Mendioroz from Aquatic Design Group. • David Petta stated ELS has been directed by the City of Lodi to have design for Aquatics Complex completed by 10131102. • The budget for the Aquatics Complex is $2.77 million. • Mr. Petta stated that the Aquatics Complex should be something that is enjoyed by the whole community. • Randy Mendioroz introduced himself and stated that Aquatics Design Group has completed between 100 & 150 projects including: • Roseville • Folsom • Pannell • UC Davis • UC Berkeley • Pools for the 2004 Olympic Trials • Mr. Mendioroz explained that the role of Aquatics Design Group was to assist City staff and the community to build the project. • Clarence Mamuyac polled the audience as to how many there were interested in a competitive pool and how many were interested in a recreational pool. Out of 45 attendees (excluding staff) all were interested in the competitive pool with one interested in the recreational pool. • Clarence Mamuyac explained that ELS has been in business for 30 years in Berkeley; David Petta has been with the firm 20 years and Mr. Mamuyac has been with the firm 15 years. • Mr. Mamuyac started the presentation by going over the components of the project which include: AQUATICS COMPLEX PUBLIC WORKSHOP MARCH 6, 2002 MINUTES Page 2 • Balance Design, Function & Economic — • Context • Project Image & Perception • Place Making • Durability & Ease of Maintenance • Pool Flexibility & Operations • Heat, Wind, Sun & Shade • Sustainable & Energy Efficient Design Aquatics Experience - • Positive experience for all involved • Lodi Aquatics Project — • Current Lodi Aquatics Facilities are Enze/Field Pools • Site — • End of Vine Street • Neighbor & Partnership Opportunities — • Shared parking with the adjacent church • Site Factors - • 3 acre site • Water feature • Planned residential • Church • School • Budget Scheme includes - • 150 parking spaces • Staff parking • Recreational pool — slide/lap lanes/water feature • 25m x 25 yard competitive pool • Berm • No concessions AQUATICS COMPLEX PUBLIC WORKSHOP MARCH 6, 2002 MINUTES Page 3 Budget Plus (50m pool) includes - • 150 parking spaces • Buildings with class room/party room • 50m pool Recreational pool • Berm • Concessions Mr. Petta explained design boards and costs associated with each pool. ELS and Aquatics Design were done with their presentation and asked for questions. QUESTION AND ANSWER - Is the cost of an odd shaped pool more than a flat pool? Mr. Mendioroz stated, "No" What are the pool depths in the Budget scheme and the Budget Plus scheme? Mr. Mendioroz replied the Budget scheme depth is 6'4" and the Budget Plus depth is 13 ft. What is the rate of return? Mr. Mendioroz stated that no economic feasibility study has been done and he is not aware of one being done Will the costs for materials be taken into consideration and will the most cost effective materials be used? Can the berm be terraced to save costs? Mr. Petta explained that material costs will be taken into consider. He also explained why there is a need for some higher quality materials in the construction. What is the deck size between the deck and the berm in the Budget Pius design? Mr. Mendioroz stated that typically it is between 20 — 25 feet. Will the 50m pool be available to the public as well as the Lodi Swim Club? Mr. Mendioroz stated that in his experience there is very little use of the competitive pool by the public due to the depth of the water. Statement only — City needs to have a competitive pool. AQUATICS COMPLEX PUBLIC WORKSHOP MARCH 6, 2002 MINUTES Page 4 Statement only — There are not enough swim facilities in Lodi to share. How many of the other facilities that Aquatics Design have developed have the same demographics as Lodi? Mr. Mendioroz stated that the facilities were across the board as far as size. Could the monies allocated for this project be explained? Roger Baltz explained how the figures were arrived at for the three projects and how much was allocated for design. Statement only — the needs of the Community need to be met by this project. Statement only — The need for berms on the church side of the property might be looked at because of noise. ELS will look at this issue. Statement only — The competitive pool will be a stimulus for the community because of monies generated due to competitive meets and the amount of people brought in by these meets. Statement only — 50m pool could be used for multiple uses i.e. water polo, swim lessons, scuba diving Mr. Petta stated that construction could start the beginning of 2003. It takes approximately 8 — 12 months to build a pool. What does $2.77 million represent? Mr. Petta stated the cost of construction. What is the average cost to building a 50m pool? Mr. Mendioroz stated it is between $100 and $110/sq. foot which equals $1,353,000, What about handicapped accessibility? Mr. Mendioroz stated that a lift is what is required by State codes. A ramp is viewed as violating the spirit of A.D.A. as a handicapped person cannot access the water on his own. AQUATICS COMPLEX PUBLIC WORKSHOP MARCH 6, 2002 MINUTES Page 5 Will there be only one water slide? Mr. Petta stated that is up for discussion. What type of lighting will there be? Mr. Mendioroz stated there would be 10 foot standards for a recreational pool and 100 foot for competitive. Will there be a scoreboard? Mr. Mendioroz stated that electrical will be roughed in for a scoreboard. The cost for a scoreboard is approximately $35,000 - $50,000. Has a secondary site been identified? Mr. Baltz stated this is the only site being considered. Mr. Baltz explained that a preferred design needs to be selected and then taken to Council. He further explained that he welcomed all input. Mr. Baltz felt that the preferred design should go to the Parks and Recreation Commission for their recommendation to the City Council. Bob Johnson concurred with Mr. Baltz as to what the procedure should be. How does a final design get selected? Mr. Baltz stated that the Steering Committee would make the final design decision. He further stated that the Steering Committee was made up of representatives from the community including the Lodi City Swim Club and the Swimming Pool Task Force. Statement only — the biggest component that is missing is that you will get fitness swimmers to utilize the pool as well. Currently fitness swimmers drive to facilities such as UOP to swim. Who found sponsors for Folsom slide? Mr. Mendioroz stated that City staff did. Meeting adjourned at 9:10 p.m. Lodi Aquatic Center Some people live to swim, others swim to live. Summer Swim League Growth In 2001 a total of 776 swimmers ■ Six Teams ■ Turned away aprox, 50 participants r ■ 31 participants on the waiting list Swim Lessons ■ Mommy and Me ■ Youth ■ Adult Current Parks and Recreation Programs ■ Summer Swim ■ Water polo League ■ Lifeguard Training ■ Swim Lessons ■ It. Lifeguard ■ Wading Tales ■ Water Aerobics ■ Tot Water Play ■ Community Water Safety Summer Swim League Wading Tales ■ Story time at Lodi Lake ■ Arts and Craft ■ Water Play 1 Tot Water Play ■ 2-5 Years of age ■ Water games include; ■ Water Tag ■ Hide and Seek ■ Slide through the hula hoop ■ Find the missing object American Red Cross ■ Lifeguard Training 36 hours ■ Jr. Lifeguard Training ■ Community Water Safety Additional Programs would include: ■ Diving ■ Scuba ■ Snorkeling ■ Kayak ■ Canoe ■ Synchronized Swimming • Water polo (competitive & recreational) ■ Summer Swim League ■ City Swim Club ■ Long Course Meets ■ Swim meets ■ Physical Therapy s Water Aerobia New Programs ■ Water polo ■ Waterfit ■ SSL ■ Water Aerobia ■ Teams in the City . Tae Bo . MddxwN . Stretching Why more water? Additional Programs Aquatic Programs IJ Aquatic Programs MAYOR'S TASK FORCE UNANIMOUSLY RECOMMENDS LARGER POOL FACILITY TASK FORCE RECOMMENDATION ■ Only the larger pool capacity allows Flexible/multiple use programs and meets future needs ■ Comparable facilities are being successfully operated (Folsom, Roseville) TASK FORCE RECOMMENDATION ■ Lodi has very limited public pool availability ■ Demand exists now for more pool water and the demand will continue to increase LODI RECREATION/FAMILY SUMMER SWIM FACILITIES (MAY - SEPTEMBER) ■ 1979 - Lodi Population 32,932 ■ Lodi Lake - Open For Family Summer Swim/With Diving ■ Blakely/Enze - Open For Family Summer Swim ■ Lodi High - Open for Family Summer Swim/With Diving ■ Tokay High - Open for Family Summer Swim/With Diving 3 LODI RECREATION/FAMILY SUMMER SWIM FACILITIES (MAY - SEPTEMBER) is 2002 - Lodi Population (2001) 58,600 m Lodi Lake - Improved Facility --No Additional Capacity/No Diving is Blakely/Enze - Improved Facility --With Additional Capacity/No Diving ■ Lodi High - No Family Swim Or Diving ■ Tokay High - No Family Swim Or Diving (In Addition WSD's Primary Use Is Curriculum & Special Ed Programs) 2002 - Two Pods, Lodi &Tokay ■ Lodi - Mens & Womens - Swimming (Frosh/Soph & Varsity) -4 Teams Mens - Water Polo (FroWSoph & Varsity) - 2 Teams Mens & Womens - Diving (Frush/Soph & Varsity) - 4 Teams Womens Water Polo (Frosh/Soph & Varsity) -2 Teams Tokay - Mens & Womens - Swimming (Frosh/Soph & Varsity) - 4 Teams Mens- Water Polo (Frosh/Soph & Varsity) - 2 Teams Mens& Womens- Diving (rmsh/Soph & Varsity) - 4 Teams Womens Water Polo (Frosh/Soph & Varsity) - 2 Teams NEW/EXPANDED PROGRAMS FOR SOM POOL (In Addition to Parks And Rec. Programs) (1) Family Recreational Swimming (2) Open Lap/ Fitness Swimming (3) Synchronized Swimming Clubs (4) Diving Clubs 1m+3m (5) Masters Swim (6) Masters Water Polo (7) Club Swim Teams (U.S. Swimming) (8) U.S. Water Polo (USWP) Mens & Womens 18u, 16u, 12u (In Addition WSD'sPrimary Use Is Curriculum & Special Ed Programs) 1978 - Two Pools, Lodi & Tokay at Lodi - Mens & Women - Swimming (Frosh/Soph & Varsity) - 4 Teams Mens - Water Polo (Frosh/Soph & Varsity) - 2 Teams Mens & Womens - Diving (Frosh/Soph & Varsity) - 4 Teams ■ Tokay - Mens & Women - Swimming (Frosh/Soph & Varsity) - 4 Teams Mens - Water Polo (Frush/Soph & Varsity) - 2 Teams Mens & Womens - Diving (Frosh/Soph & Varsity) - 4 Teams SCHOOL DEMAND ON FACILITIES HIGH SCHOOL SPORTS ONLY (In Addition LUSD's Primary Use Is Curriculum & Special Ed Programs) Bear Creek - Mens & Womens - Swimming (Fresh/Soph 0, VarAW) — 4 Trams Mens - Water Polo (Frosh/Soph & Varsity) — 2 Teams Mens & Womens - Diving (Frosh/Soph & Varsity) - 4 Teams Womens Water Polo (Frosh/Soph It Varsity) - 2 Teams 2006 - (Estimated) Add New High School, Add 12 Teams, Add one new 25 x 25 pool (subject to Joint Use Agreement with City or Stockton) TASK FORCE RECOMMENDATION What we can't do with 25 x 25 pool an Cannot maintain diving area during water polo and swim practice at Cannot run two & three water polo courses for practice at the same time as Cannot run more than one summer swim league team or club practice at same time 4 TASK FORCE RECOMMENDATION What we can't do with 25 x 25 pool ■ Cannot maintain lanes for fitness or recreation swimming while water polo & swim teams practice ■ Cannot run any combination of three activities Budget, Schedule and Process 19 • Budget: $2,775,000 • Schedule, for funding: Complete Working Drawings 10/31/02 Complete Schematic Design 6/1/02 • Public Process y U cC W m U 7 C Ea 0 a Public Process •Steering Committee 211402 • Task Force 2/1902 •Swim Club Board 2/2802 *Steering Committee 3002 *Public Workshop 3602 •Steering Committee 32802 L S] rR Xiiiiou,3 soilvnb-Vipo7 Pool Combination Options L.mug,.,. Siie am Gott - See Cosi.- Rewya ;: s 1 50m x 25 yd (12.000 sq Ion, worse swim $1.35m 2,000 sf wet playground $0.35m $1.7m 50% -BD% $250-$350 ,M l*w end 4'$ 201anes x 25 yd nap depth "try entry w 0. floating goals �mUltt-U50' warm up laps 2 35m x 25 yd(8.4005f) 141amux 25 yd $Q.Om 2,000 sf wet playground $0.5111 $1.4m 60%-70% $125-$175 .hallow end 3'.6' class area for 62 zero depth -" = mul"se- warm up laps water slide I w p. bstMg goals 3 Som x 25 yd (.200 sq 121.— x 25 yd $0.8m 3,000 sf w.t Wyqwml $0.6m $1.4m 60%-70% E 125-$175 -strellav end 3'-6' class area for 31 zero depth entry mulva w.p. wan capes w.ter slide 425. x 25 yd (6,000 a t) 10 tars x 25 yd $0.7m 3.D005f wetplaygrow,d 50.7m $1.4m 70%-80% E1W-$150 -shallow ord 3'-6' w.p, wall capes zero depth -by 2 water s6tlee .$ CompIRecC..binwlP.0 10 lanesx25yd Ind incl. wet playground ins. $1.3m 70%-80% $100.$150 (10,000 sf'PanneB'rnode0 w. p. wall cages zero depth miry WAM19sde 5, CWVRaC Cmft.-.d Pod rR Xill!ouj soijunbV 1po-I O tn Xilljo-e j sotjrnbV ipo-I :i.LS R NifE14am0 HMMMRM mi4IIEaAw OM2`?MMpq To S q Q L FI MIEl Flo AR a[MO ME10 LV Ca _To a wF 0I0I0 LUQ Cin City of Lodi Aquatics Facility Planning April 2, 2002 Program and Budget Analysis program Area `m.Scheme , .. ZSy x ?5m Scheme Parlung-, Pools and Equipment $152,960 Water (Demand) 25 meter x 25 yard (sf)_ 12,300 - 7;300 19,600 $110 $2,156,000 6,150 _ -- -- 7,300 13,450 $110 $1,479,500 175 to 233 -------- 100 to 133 50 meter x 25 yard (sf) Rec pool: instruction, slide, wet play (sf) Total Pool Area (sf) Cost $Jsf Subtotal Waterslide $150,000 $100,000 $2,406,000 $150,000 $100,000 $1,729,500 Wet Play Structures Pools Total Support Buildings 1. Administrative (sf) 1,000 - 2,8_002,000 400 1,000 1,600 400 800 8,000 8,800 $200 1,000 _ 40- 2. Changing Rooms (sf) 3. Concessions (sf) _ 400 _ 4. Classroom / Party Room (sf) 1000 5. Pool Equipment (sf) - - 1,200 _ _ 400 800 6,800 _ 7,480 6. Indoor Storage (sf) _ 7. Covered Breezeway (x 50%) Net Bldg Area (nsf) Gross Bldg Area (nsf x 1.1 for mech, struct) Cost $/sf $200 Buildings Total $11760,000 $1,496,000 Sitework** Desi n Landscaping (Planting & Flatwork) $68_4,0_00 $233,340 _ $84,340 $36,500 $1,038,180 $563,000 Paving $194,880 182 Underground (incl. dry utilities) $82,340 General Conditions (incl. erosion control) $36,500 Site Total $876,720 Contingency 15% $780,6271 $615,3331 Total 1 $6,984,8071 $4,717,553 Budget: $2,775,000 Operating Costs Recovery Rate 1 55% to 65% 1 70% to 80% Annual Subsidy I $175k to $225 $100k to $150k Off-site Improvements (Direct frontage only Surface Improvements Storm Drain $232,810 $185,640 Sanitary $152,960 Water $35,020 General Conditions Off site) $61,000 Total Off-site $667,430 ** Earthwork quantities are an allowance only, until property and topographic information is available. 11iC I L 1 I `i' F'LkNH 11,16 y 2093:3600? N0. 619 1 11 tom:; ttllicd qI.l�t��if ll�etlirf Eacility Planning Department faao-V-4� 4- MA�� EMORANDUM TO: Superintendent Huyett FROM: Mamie Starr, Assistant Superintendent Facilities and Planning DATE: Marcia 29, 2002 RF: City of Lodi Aquatics Center On March 28, 2002, I attended the meeting of the City of Lodi Aquatics Task Force, of which I ann a community member (not specifically representing the District). The Task Force was asked to make a recommendation to the Parks and Recreation Commission and the City Council regarding the size of the main pool to be included in the project. The question was a 25 teeter pool or. a 50 meter pool? The critical issues were an additional $2,000,000 construction cost and the incrementally higher operational cost. I was asked about the Joint Use Agreement, future school facilities (especially switnrnittg pools), and the probability of there being more time available for City use of the 50 )teeter pool at Tokay High School. I responded as follows, per our discussion prior to the meeting: • We anticipate building a pool at the fourth high school (as part of the total project) out of Measure K; however, it is a "lower priority" expenditure. • A pool for .Dear Creek is desired, but Measure K will be used for a theater and other program spaces. There are presently no funds assigned to a pool at that site and it is not specifically included in the 10 year Facilities Master Plan. . • Bear Creek is currently using THS, as well as Blakely on occasion. • Even with the Fourth High School, we will still have 4 high schools sharing 3 pools for an indefinite period of time, • The District will make the THS pool available per the provisions of the use agreement; however, we will commit to improving the scheduling so that it might accommodate more City hours. • We acknowledge that the current bulkhead is a barrier to maximizing flexible use of the TNS Pool, but we have not been able to commit funds for its replacement. • The primary purpose of our pools is the educational program, specifically PE swimming for both regular education and special education students. The second purpose is the competitive athletic program. For these purposes, we do not need a 50 meter pool. • i acknowledged that we have concerns about diving and the depths of the pools (which is why we no longer have 3 rneter boards) and we are aware of the Ls.4ucs relative to the depths of the pools for water polo. + Regardless of the size of the City pool, we will continue to have our pools available under the provisions of the Agreement (I did twt discuss the priority that the City of Stockton will have for the Fourth High School Pool under the provisions of our joint development agreement with them). 1306 last Vine Street - Lodi CA 95240 - 209.331.7219 (Lodi) - 209-063.8218 (Stoekton) - 209.331.7229 (FAX) 1i-:;. 11! 1k, I,I:I ►t'_iLi I I'Ud11It1J1_, -0 L'IYJ ;i- ,`-Ye IJI I, (Ali 1J413 a Our school teams (especially water polo) would probably be interested in using the City pool; however, there are issues related to having a USA -approved facility. We concluded that the District's use of the school pools, even with the addition of a third pool, leaves relatively little time for City use, particularly for long -course swinuning. The members of the Task Force present voted unanimously to recommend a 50 meter pool, with the following rationale: ✓ The Tokay High pool can not come close to mating the existing, latent, and future demand for pool space (especially for long -course) in the City of Lodi, even with maximizing scheduling. ✓ This is a community with a strong swinuniug interest - having a second 50 meter pool in the City will allow that interest to grow and provide opportunities for more youth and adults to participate in swim activities. ✓ The initial cost may seem substantial; however, amortized over time, it becomes inconsequential. ✓ This is a once-in-a-lifetime opportunity to provide a facility that will meet community needs. ✓ District pools will continue to be available, broadening the opportunities for programs as well as major aquatic functions which bring dollars into the commercial sector of the City. ✓ A significant portion of the operational cost of the center (with the larger ) pool can be recouped through fees. ✓ The larger pool, particularly with a functional bulkhead, provides more water area, which results in more program accommodation. ✓ The larger pool ovnied by the City will allow long -course progranLi to grow which have been stymied because the Tokay Pool is so heavily used for school programs. ✓ There is a documented demand for more pool area. The members of the Task Force, and Parks and Recreation Director Baltz, asked if the District could have representation at the Commission meeting on Tuesday evening, April 2"d and at the Council meeting on Wednesday evening, April 3" for the purpose of responding to questions related to the District's position. cc: Members of the Board of Education Dixon Flynn Janet Kceter Roger lIaltz Jennifer Pinnell Randy Studer (Task Force Chair) Max Steinheimer (Task Force Representative)