HomeMy WebLinkAboutAgenda Report - March 20, 2002 E-04AGENDA TITLE: Contract Change Orders No. 1 through 3 and Accept Improvements Under Contract
for Stockton Street Reconstruction, Tokay Street to Lodi Avenue
MEETING DATE: March 20, 2002
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "Stockton Street
Reconstruction, Tokay Street to Lodi Avenue" contract.
BACKGROUND INFORMATION: The project was awarded to Dell Engineering, of Lodi, on June 6, 2001,
in the amount of $792,591.00. The contract has been completed in
substantial conformance with the plans and specifications approved by
the City Council.
The contract completion date was January 29, 2002, and the actual completion date was January 23, 2002.
The final contract price was $844,556.46. The difference between the contract amount and the final
contract price is mainly due to Contract Change Orders No. 1, 2 and 3 (copies attached). These change
orders addressed additional work done by Dell Engineering on our existing water and wastewater mains to
repair broken lines or reroute lines because of our new construction. Contract Change Order No. 3 also
included additional compensation to reconnect the lighting on several side streets to the Stockton Street
lighting. Resolution 85-173 requires staff to inform Council of contract change orders when they exceed
$25,000.00. The total cost of all three contract change orders was $52,638.70.
Following acceptance by the City Council, the City Engineer will file a Notice of Completion with the
County Recorder's office.
FUNDING: Budgeted Fund: Measure K $ 537,436.09
Electric Utility Fund $ 86,857.91
Water Capital Outlay $ 93,410.34
Wastewater Capital Outlay $126,852.12
Contract Amount: $ 844,556.46
Prepared by Wesley K. Fujitani, Senior Civil Engineer
RCP/WKF/lm
attachments
cc: Joel Harris, Purchasing Officer
Street Superintendent
Water/Wastewater Superintendent
APPROVED:
CCCO&ACCEPT
dai
Richard C. Prim Jr.
Public Works Director
H. Dixon Flynn -- City Manager
03/08/02
CITY OF LODI
PUBLIC WORKS DEPARTMENT
PROJECT: Stockton Street Reconstruction
Tokay St. to Lodi Ave.
CONTRACTOR: Dell Engineering
CONTRACT CHANGE ORDER NO. 1
Sheet 1 of 2
Date 1/28/02
Account No: See distribution beow
You are directed to make the following changes or do the following work not included in the
Plans and Specifications on this contract.
----------------------------------------------------------------------
Description of work to be done, estimate of quantities, and prices to be paid. Specify whether
additional work is at contract price, agreed price, or force account. Unless otherwise stated,
rates for rental of equipment cover only such time as equipment is actually used and no
allowance will be made for idle time.
1. Additional work to connect to City water main
at alley S/Lodi Ave. (DEWR 1115)
Account: 181062 Agreed Upon Price $ 3,179.76
2. Remove and Replace existing Storm Drain Manhole at Eden St.
(DEWR 1116)
Account 171062 Agreed Upon Price $ 2,000.94
3. Additional work to correct two homes on one sewer service.
Install new service, disconnect home from existing service and
connect to new line. (DEWR 1117)
Account 171062 Agreed Upon Price $ 1,341.31
4. Reroute 4 -inch sewer line due to grade conflict with existing water main
(DEWR 1118)
Account 171062 Agreed Upon Price $ 871.37
5. Additional work to repair existing water main
(DEWR 1121)
Account 181062 Agreed Upon Price
6. Additional work to expose PacBell conduits at Elm St.
(DEWR 1122)
Account 325062 Agreed Upon Price
TOTAL
CCo1
$ 889.08
$ 873.53
$ 9,155.99
PERCENT OF
CONTRACT
Original Contract Price $792,591.00
Total Cost of This Change Order NOT TO EXCEED $ 9,155.99 1.2%
Previous Change Orders $ 0.00
Total Cost of All Change Orders to Date $ 9,155.99 1.2%
Contract Price, Including All Change Orders, Will Be: $801,746.99
Time of completion will be adjusted as follows: Add five working days
Submitted By Date VZ6/o Z
Approval Recommended Date 1- o-oZ-
Approved, Public Works Director wJ Date ) S) DZ
Approved, City Manager (Per Public Works Policies and Pi cedures, Administration 4.1)
N/A Date
The undersigned contractor, having carefully considered the change proposed, agrees, if this
proposal is approved, to provide all equipment, furnish all materials, except as otherwise noted
above, perform all services necessary for the work above specified, and accept as full payment
the prices shown above.
ACCEPTED- Date
By/t .
77,
Contractor A LL
Title � - /71•
If the contractor does not sign acceptance of this order, the contractor should refer to Section 4-
1.03A of the Standard Specifications regarding filing a written protest within the specified time.
CITY OF LODI
PUBLIC WORKS DEPARTMENT
PROJECT: Stockton Street Reconstruction
Tokay St. to Lodi Ave.
CONTRACTOR: Dell Engineering
CONTRACT CHANGE ORDER NO. 2
Sheet 1 of 1
Date 2/25/02
Account No: 325065
You are directed to make the following changes or do the following work not included in the
Plans and Specifications on this contract.
----------------------------------------------------------------------
Description of work to be done, estimate of quantities, and prices to be paid. Specify whether
additional work is at contract price, agreed price, or force account. Unless otherwise stated,
rates for rental of equipment cover only such time as equipment is actually used and no
allowance will be made for idle time.
1. Remove Trees and Stumps S/Flora (DEWR 1034)
Agreed Upon Price $ 694.12
2. Adjust Sidewalk Grades E/Side Stockton St. at Flora.
(DEWR 1030 and 1031)
Account 325065 Agreed Upon Price $ 7,931.32
3. Remove Manhole, Install new Manhole and reconnect three
Wastewater Mains (DEWR 1119)
Account: 325065 Agreed Upon Price $ 8.921.23
TOTAL $17,546.67
PERCENT OF
CONTRACT
Original Contract Price $792,591.00
Total Cost of This Change Order NOT TO EXCEED $ 17,546.67 2.2%
Previous Change Orders $ 9,155.99
Total Cost of All Change Orders to Date $ 26,102.66 3.3%
Contract Price, Including All Change Orders, Will Be: $819,293.66
Time of completion will be adjusted as follows: Add seven working days
Submitted ByDate 2 - 96 -02
Approval Recommended'Date -S - z'7 —a?-
Approved, Public Works Director Date Z. Zb •«L
Approved, Cit=Mn (Per ubl' orks Policies a d Procedures, Administration .1)
Date o'2
The undersigned contractor, having carefully considered the change proposed, agrees, if this
proposal is approved, to provide all equipment, furnish all materials, except as otherwise noted
above, perform all services necessary for the work above specified, and accept as full payment
the prices shown above.
ACCEPTED: Date Feb o2 O, O 1 Contractor �D e I( F n g i n -e -e, r c:e ucl
By v) ; _( tin IL( j 'A r -t ac Gl. Title �re5 1 d-��
If the contractor does not sign acceptance of this order, the contractor should refer to Section 4-
1.03A of the Standard Specifications regarding filing a written protest within the specified time.
CCO2
CITY OF LODI
PUBLIC WORKS DEPARTMENT
PROJECT: Stockton Street Reconstruction
Tokay St. to Lodi Ave.
CONTRACTOR: Dell Engineering
CONTRACT CHANGE ORDER NO. 3
Sheet 1 of 1
Date 3/5/02
Account No: 3S
1fo4oG2
You are directed to make the following changes or do the following work not included in the
Plans and Specifications on this contract.
----------------------------------------------------------------------
Description of work to be done, estimate of quantities, and prices to be paid. Specify whether
additional work is at contract price, agreed price, or force account. Unless otherwise stated,
rates for rental of equipment cover only such time as equipment is actually used and no
allowance will be made for idle time.
1. Perform additional electrical work on side streets to connect Stockton St. lighting
to existing lighting system (DEWR 1302)
� -1 ` "r° 2 Wf Agreed Upon Price $ 17,424.91
2. Install posts at 1J2 E. Lodi Ave. (DEWR 1137)
"t 3�5c "'F Agreed Upon Price $ 311.13
3. Compensation for lost time due to paving delay (DEWR 1179)
"`-i' 3�SCIA-AF Agreed Upon Price $ 4,000.00
4. Additional compensation to work around existing water main N/Tokay St.
(DEWR 1032) PST 325o�&-4 Agreed Upon Price $ 4.800.00
TOTAL
$ 26,536.04
PERCENT OF
CONTRACT
Original Contract Price $792,591.00
Total Cost of This Change Order NOT TO EXCEED $ 26,536.04 3.3%
Previous Change Orders $ 26,102.66
Total Cost of All Change Orders to Date $ 52,638.70 6.6%
Contract Price, Including All Change Orders, Will Be: $ 845,229.70
Time of completion will be adjusted as follows: Add twenty-nine working days
Submitted By i'' Date -5-02-
Approval Recommende vi Date %-? �-
Approved, Public Works Dire ' - Date 3 )r uz
Approved, City 1oaWger r P b}ic Works Policies a Procedures, Administration 4.1)
The undersigned contractor, having carefully considered the change proposed, agrees, if this
proposal is approved, to provide all equipment, furnish all materials, except as otherwise noted
above, perform all services necessary for the work above specified, and accept as full payment
the prices shown above.
ACCEPTED: Date 1-7 1 b z Contractor 3)'P_
I
r
By Title A_L4-� pp
If the contractor does not sign acceptance of this order, the contractor should refer to Section 4-
1.03A of the Standard Specifications regarding filing a written protest within the specified time.
CCO3
3250r.2 �_p
L -P