HomeMy WebLinkAboutAgenda Report - May 1, 2002 I-02CITY OF LODI COUNCIL COMMUNICATION AGENDA TITLE: Indoor Sports and Activity Complex project review and request for direction MEETING DATE: May 1, 2002 PREPARED BY: Parks and Recreation Director RECOMMENDED ACTION: That the City Council review progress to date on the Indoor Sports and Activity Complex project and provide direction regarding specific design element components. BACKGROUND INFORMATION: On February 6, 2002, the City Council approved a professional consulting services contract with ELS Architecture and Urban Design (ELS) and allocated $681,135 for the design of an Indoor Sports and Activity Complex. As a reminder to Council, a project estimate of $7,500,000 was discussed at shirtsleeve sessions last year during consideration of COP financing. Actual costs of the project will depend upon its actual design. Also, staff has attempted to estimate annual operations and maintenance costs but this will also vary depending upon actual design. ELS can conduct a detailed economic analysis upon request and for an additional fee. For our project to date, ELS has provided rough estimates of annual operating subsidies based upon their experiences with other similar facilities. The basic services included in the contract include a scope of services/work plan to be performed in phases. The City must approve proceeding with each phase and may elect to terminate services at the end of each phase. The phases are as follows: • Planning Phase • Schematic Design Phase • Design Development Phase • Construction Documents Phase • Bid and Permit Phase • Construction Phase • Post Construction Phase The City established an ambitious timeline for the construction documents phase and has established a goal for construction documents to be at 90% completion by November 1, 2002. The consulting firm (ELS) has been working for several weeks now and clear direction regarding the elements for the project are needed. Specifically, the schematic design phase will require detailed components identified and clear direction for a preferred site plan. APPROVED: H. Dixo'n Flynn -- City Manager 04/25/02 CITY OF LODI COUNCIL COMMUNICATION To date a variety of actions have occurred with regards to the project. Per the contract, ELS has been working with a steering committee on the project. This group has included representatives of several City departments (Parks & Recreation; Public Works; Community Development; the City Manager's Office), representatives of the Lodi Sports Foundation, representatives of the Boosters of Boys and Girls Sports (BOBS), and a representative from the Parks and Recreation Commission. Field trips have been taken and items of consideration have included site location and a wide range of program issues and design ideas. On March 7, 2002, a public workshop was held at the Carnegie Forum to encourage input and ideas for the project. One of the primary issues of discussion has been the question of what the purpose of the facility should be for the community. Gymnasium spaces have been a priority focus along with the need for flexibility and multiple uses. The preferred site plan selected will have an impact upon initial costs to construct and cost recovery potential annually. Our process has seen strong support among the advocates for gymnasium space and multi use rooms for programs and rentals to be included in the design. With these factors in mind our process has focused upon two plans which both occupy just over 30,000 square feet. I have attached information which ELS has prepared which provides some of the estimated costs for two plans. I would like to remind all that these are only estimates and will change depending upon the various design decisions which are made. Attached for your information is a variety of supplemental information in response to questions posed at the Council meeting of April 3, 2002. It includes: • A current overview of gymnasium facilities which are utilized by Parks and Recreation for programs_ Please note that the use of the Lodi Grape Pavilion is restricted to five months out of the year. Also, the National Guard Armory five year lease has now been approved by Council and the use of the full size court it contains will occur in the coming months. Participant numbers for basketball are also listed. (Attachment A) • An excerpt from the request for qualifications advertisement which addressed the design concept intended for the project. (Attachment B) • A listing of program offerings which might be possible with an indoor sports complex facilitbby. (Attachment C) • A listing of possible sites which are under consideration as possible locations to utilize the Breakaway Sports donated surfaces. (Attachment D) APPROVED: H. Dixon Flynn -- City Manager 04/25/02 We intend to have ELS in attendance at the May 1, 2002, City Council meeting to present the project status and answer questions. If the Council is able to provide clear direction regarding which concept it prefers, it will allow schematic work to move forward with one preferred site plan. FUNDING: None Roger Baltz Parks and Recreation Director RB:tI cc: City Attorney APPROVED: H. Dixon Flynn -- City Manager 04/25/02 �-Mtmr_- im"WRIM 1��AIIIWA 0 MMMM him ME s SAN 1 M 6ILMOMM AVA ;0 IqBTA � k 'J 04 04 4149 0 10 LOCU DOWntOVn COMUZ13-r-Y Iizdoar Sports Complex scheme B site plan x tMRS, .. K cafe/juice bar cardio reception meeting martial arts yoga basketball activities multi-purpose spaces north light in gym cafe/ lobby view to Main St from lobby naturally illuminated interior spaces nighttime exterior entrance exterior transparency circulation /volume Lodi Downtown Community Indoor Sports Complex pedestrian bridge/ hall bridge plaza architectural character City of Lodi Indoor Sports Complex April 23, 2002 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 OT -1 Program and Budget Analysis Program Areas Plan A Plan B Indoor Sports Building (Same Program as Plan A) A. Support Spaces 4,800 B. Large Gym: 2 x 50'x 84' 15,230 C. Activity Rooms _ Divisible Multi Use for 80 2,925 Cardio /Aerobics Studio 2,250 Climbing Wall 300 Babysit Room 750 _ D. Food Catering Kitchen 600 Cafe 250 Total Net Area 27,105 Gross Area 31,825 Cost $/sq.ft. $190 Cost $6,046,750 $6,046,750 Small Gym 1 x 50'x 84' 7,150 Net Area Gross Area 7,280 Cost $/sq. ft. $175 Cost $1,274,000 Site Work Civil $500,000 $500,000 Landscape $357,000 $357,000 Contingency 15% Total Recommended Budget $1,035,563 $7,939,313 $1,226,663 $9,404,413 0 CITY OF LODI YOUTH BASKETBALL Junior Basketball League (City) Comet/Cardinal Basketball (BOBS) City owned gymnasiums - NONE 1995 2002 711 1055 (70 teams) (105 teams) 140 253 (14 teams) (24 teams) Facilities used (rented or leased) - Lodi Grape Pavilion ( 2 city owned wood floors) - Lodi High School - when available on Saturdays - Tokay High School - when available on Saturdays - Lodi Middle School (tile floor) - when available - Lawrence School (tile floor) - when available - Lodi Boys and Girls Club - Monday through Thursday, 6:00p.m: 9:00p.m. and Saturdays Notes: Game lengths are constricted because of gym availability. Comet/Cardinal teams (7th & Sth grade) receive only 3 hours and 45 minutes of preseason practice time. JBL receives only 30 minutes practice time with slightly more pre -season time inside. The JBL and Comet/Cardinal programs need longer game times and practice time in order to teach the sport. What we are accomplishing is barely adequate. Compared to other sports, basketball falls short. Soccer, baseball and softball have 4 1/2 to 6 hours a week of practice time. Adults must begin play between 8:00p.m. and 9:00p.m. in the evenings. We are not able to run other programs such as Open Gym because we have no time due to lack of facilities. CITY OF LODI ADULT BASKETBALL Winter Basketball League Late Night Basketball League Spring Volleyball League Facilities used (rented or leased) 20 teams 220 participants 131 participants 25 teams 250 participants Lodi Grape Pavilion: basketball Tokay High Gymnasium: volleyball Note: The game times available for adult basketball have negatively impacted the popularity of the program, with games beginning at 8:00 and 9:00 pm. Two-thirds of all adult games begin at 9:00 pm. The adult volleyball league now begins later in the year and has a shorter season due to the limited availability of the high school gym. Late night basketball operates during the limited season available at the Grape Pavilion. The popularity of this program by the participants would be met with additional opportunities at a year-round facility. We know that the Police Department supports this program as "crime - prevention," as it provides a Saturday late night activity for at -risk older teens and younger adults. COUNCIL• - ! The City of Lodi Parks and Recreation Department currently operates indoor gymnasium facilities owned by San Joaquin County through joint use agreements with the County. In 1994, a Park, Recreation and Open Space Plan was developed. From a survey and workshop meetings revealed considerable interest for an indoor recreatio center. The need assessment indicated a seecific need for a gymnasium. The plan spe s out the followingdesign requirements for a successful Indoor Recreation Facility. (1) The facility should provide a wide range of facil' J and acti ' ' of interest to all a e groups. (2) Spaces should, be provided for competitive and active snorts, passive activities, rece tion and general leisure. (3) Multi -use space hould be favored over single purpose spaces. Flexibility is very important. In the fall of 1996, the City of Lodi commissioned a feasibility study for constructing and operating facilities for indoor sports and recreational activities within the community of Lodi. A committee of citizens and City representatives was assembled for the purpose of defining project parameters and to provide leadership, direction and representation during this process. The following goal statement written by the committee expresses the overall mission of facility: To enhance the quality of life for all residents by providing affordable and accessible indoor facilities and sports activities. The center must beflexible to accommodate future growth and trends and designed for cost effective maintenance and operations. The center should provide a friendly, inviting atmosphere that fosters a sense of community. The center must provide a secure environment for participants of all a42g and abilities. to pursue .fitness and recr� eati�on opportunities in the City of Lodi. Beginning In January 2001 public workshops were held with citizens, staff, and the Parks and Recreation Commission which resulted in and indoor sports and activity center facility being identified as a priority for the City. The City is attempting to acquire property located near the current Parks and Recreation offices to create a "campus" effect to an indoor sports complex. The goal of the Indoor Sports and Activity Center design plan is to provide detailed information regarding cost estimates; scale model for the project; concept design; preliminary design; and final design of the project. Construction plans and specifications will be produced from this work. In response to the RFQ advertisement the City received roughly forty four (44) inquiries for information. Thirteen (13) firms submitted statements of qualifications by the required deadline. A review group made up of representatives of the Boosters of Boys and Girls Sports (BOBS), the Lodi Sports Foundation, the Parks and Recreation Commission, the Public Works Department, the Community Development Department, the City Manager's Office, and the Parks and Recreation Department reviewed the submittals and conducted interviews with six (6) firms. Through this process ELS Archtecture and Urban Design was selected as the top ranked firm and staff conducted reference checks. A contract has now been negotiated and is attached for Council consideration for approval. APPROVED: H. Dixon Flynn -- City Manager 0112910: Indoor Sports Center Future Activities Sports Activities Adult Basketball Youth Basketball Adult Volleyball Youth Volleyball Tournaments Badminton Rock Climbing Wall Classes Karate Yoga Tai Chi Gymnastics Judo Aerobics/Fitness Cooking Babysitter Training First Aid/CPR Cooking Crafts Kite Making Photography Chess Cheerleading Bridge Financial Planning Emergency Preparedness Meetings Teen Nights Boys and Girls Scouts Coaches Training Community Groups Rental Opportunities Banquets Birthday Parties Receptions Kitchen Use c LJ BREAK AWAY SPORTS DONATION: (As a reminder, the list of items follows this page) Staff has discussed possible uses of these items. No final or approved uses of the donated items have been made as yet. Some possible uses and locations which may be available might include: Soccer -Hockey Field Surfaces: • A surface may be utilized as part of the campus master plan and designed by ELS. • A surface may be utilized at the comer of Lockeford and Stockton near the Armory building. Staff has determined that adequate space does exist at this site to accommodate a surface area. • The City owns a wedge shaped piece of property next to Salas Park which might also be utilized for a surface. This is a site which has also been discussed as a possibility for a bicycle BMX track as well. • Public — Private partnerships may be possible for utilizing these surfaces as well. Basketball Court Surfaces: It may be possible to place one or both surfaces inside facilities at the Grape Festival Grounds. Our City currently leases the Pavilion building and Cabernet Hall for parts of each year. It may be possible to place one the surfaces in a leased building in our City.. It may be possible to work together to utilize the court surfaces in partnership with the School District or other agencies. As an additional reminder, the donated items will be stored at no cost to the City for up to twelve months. If any of the major items are not put to use or are not a key component of a City capital project, approved by Council including funding for construction, within 24 months of the date the donation was accepted, then all equipment/items will be returned. Breakaway Sports Centers, LLC Fixed Asset Schedule As of: 11/30/01 Description Equip ID # Date Acquired Asset Cost Furniture & Fixtures: Pro -Shop Fixtures 11/01/99 4,509.06 Party Room Furniture 11/01/99 903.38 Total Fumiture & Fixtures 8,258.35 Equipment: Soccer Arena #1 11/01/99 54,850.00 Scoreboard 11/01/99 3,555.75 Turf - Arena #1 11/01/99 64,102.34 Turf - Arena #2 11/01/99 33,731.00 Benches 11/01/99 614.18 Nets 11101/99 3,823.21 Misting Fans 11/01/99 18,232.09 Hockey Arena #2 11/01/99 67,965.75 Scoreboard 11/01/99 3,555.75 Hockey Floor (Icecourt) 11/01/99 34,325.00 Benches 11/01/99 614.18 Nets 11/01199 3,900.00 Basketball Floor- NBA 11/01/99 99,215.38 Floor - NCAA 11/01/99 29,487.00 Brass Floor Plates 11/01/99 480.00 Benches 11/01/99 581.36 Scoreboards 11/01/99 5,902.86 Standards (Hoops) 11/01/99 22,234.70 Other Snack Bar - Kiosk 11/01/99 56,284.00 Sales Tax on Kiosk Equipment 04/01/00 1,136.07 Snack Bar - Equipment 11/01/99 25,580.66 Party Roon Dasherboard System 11101/99 6,133.00 Bleachers 11/01/99 2,171.90 Cooling System 11/01/99 3,450.00 Gas Heaters 11/01/99 30,812.00 Murals 11/01/99 47,800.00 Padding on Structual Poles 11/01/99 5,749.98 Pro Shop Displays 11/01/99 2,000.00 Benches 04/01100 858.72 Bleachers-M.A.S.A 05/31/00 2,179.50 Bleachers 02/28/01 1,344.12 Bleachers 03/31/01 590.48 Total Equipment 748,734.74 Breakaway Sports Centers, LLC Fixed Asset Schedule As of: 11/30/01 Date Asset Description Equip ID # Acquired Cost Computer Equipment: Smartcard I.D. System 11/01/99 9,002.05 Total Computer Equipment 12,840.78 Buildings: Modular Buildings 11/01/99 292,788.00 Permits 11101/99 6,790.00 Total Buildings 299,578.00 Grand Total 1,069,411.87 •, 0 • • The City of Lodi's Family Recreation Center .......... .......... .......... . . • We Create Community through • People • Parks • Programs a s • Provide recreational experiences • Promote health and wellness • Strengthen Safety and Security • Protect Natural Resources • Strengthen Community Image • Support Economic Development • • • Youth & Teen Basketball (Grape Pavilion, Boys &Girls Club, and high school gyms as available) • Adult Basketball (Grape Pavilion) • Late Night Basketball (Grape Pavilion) • Adult Volleyball (Tokay Gym as available) • • • • • Grape Pavilion — Nov through Feb use — limited weekday hours — brief practice times for youth teams — 2/3 of all adult games start at 9 pm • High School and Middle School Gyms — limited Saturday use — City programs are secondary priority — volleyball offerings only when the school's activities allow • . a • 0 • • • • • • Yoga This large space • Karate allows for only one • Rental s activity at a time • Meetings • Staff Training 0 0 4 Cld O 00 r� cd O pCfj y Cd • r-1 [:l i i • A i Cld O cd [:l i i • A i • • • Karate Yoga • Judo Tai Chi • Fitness Aerobics • First Aid CPR • Cheerleading Chess • Bridge Photography • Rock Climbing Cooking • Babysitter Training • M • a • • •Teen Nights and Dances • Game Nights • Boy and Girl Scout meetings • Coaches Training • Community group meetings . _ ........ i ! ! •Wedding Receptions • Birthday Parties • Quinceneras • Baptism Receptions • Banquets ! ! ! • • M • ! MAY -01-2002 12:06 May 1, 2002 LAM CITY COUNCIL P. 02/03 4999 W. Hwy 12, Lodi. Ca 95242 Ph! 209-369-7664, Fox: 209-3670572 1,01— I am nimble to attend the May 1" meeting of the Lodi City Council And wish to inform the C Weil members that ad Agenda Item, E-6, I support the adoption of the Scheme B Site Plan with a minimum of throe (3) baslcetbsil courts for the Lodi Downtown Community Indoor Sports Compks. This is a long overdue project and should be started as soolt as possible. Frank C. Alegre W Id Ll