AGENDA TITLE: Adopt resolution authorizing the City Manager to execute a professional consulting services
contract with ELS Architecture and Urban Design for design and construction administration
of an Aquatics Facility and appropriate $269,075 for the project
MEETING DATE: February 6, 2002
PREPARED BY: Parks and Recreation Director
RECOMMENDED ACTION: That the City Council adopt the resolution authorizing the City Manager to execute
a professional consulting services contract with ELS Architecture and Urban
Design and allocate $269,075 for the design of the Aquatics Facility project.
BACKGROUND INFORMATION: In response to input from public meetings, community members, potential
user groups and organizations, the Parks and Recreation Commission,
and staff an Aquatics facility project has been identified and approved as
a high priority by the City Council.
On August 15, 2001, the City Council approved staff to proceed with a Request for Qualifications (RFQ) to Provide
Planning and Architectural Services for an Aquatics Facility process to move forward toward design of an Aquatics
Facility.
The RFQ document provided a variety of summary and project description information. Some of the highlights of
this information include the following:
Lodi Parks and Recreation serves an official population of 57,900. To this population we offer over 100
aquatic program opportunities, and a potential 1,800 chances for participants to learn to swim.
The City of Lodi is located 90 miles east of San Francisco, 34 miles south of Sacramento, adjacent to U.S.
Highway 99 and is easily accessible to Interstate 5. As the northern -most city in the San Joaquin County,
Lodi bridges the areas of Northern and Central California. Its location places Lodi in the path of a dynamic
growth corridor ideally situated for business and industry.
In 2000 the Mayor of Lodi appointed a Swimming Pool Task Force. After deliberating the Task Force
envisioned the development of an Aquatic Center. As envisioned, the facility should provide an
atmosphere capable of multi -use. The Swimming Pool Task Force worked with staff and referenced a
copy of the 1994 Master Plan and Conceptual Site Plan that had envisioned the same type of facility. The
Westside Master Plan incorporates the Aquatic Center on a three -acre parcel, west of Lodi. The Task
Force would like to see the following design requirements:
Able to accommodate growth.
Effective and efficient maintenance and operation cost.
Family oriented.
Multi -shut down facility (allow portions to be operating while the remaining facility is not in use).
Beginning in January 2001 public workshops were held with citizens, staff, and the Parks and Recreation
Commission which resulted in an aquatics center being identified as a priority for the City.
APPROVED:
H. Dixon lynn -- City Manager
01/29/02
CITY OF LODI COUNCIL COMMUNICATION
Lodi Parks and Recreation currently operates one Department aquatic facility consisting of two swimming
pools within the city limits. The goal of the Parks and Recreation is to provide the citizens of Lodi with a
family oriented aquatic center. The goal of the Aquatics Center design plan is to provide detailed
information on cost estimates; scale model for the project; concept design; preliminary design; and final
design of the project. Construction plans and specifications will be produced from this work.
In response to the RFQ advertisement the City received roughly forty seven (47) inquiries for information.
Nine (9) firms submitted statements of qualifications by the required deadline. A review group made up of
representatives of the Swimming Pool Task Force, the Parks and Recreation Commission, the Public Works
Department, the Community Development Department, the City Manager's Office, and the Parks and Recreation
Department reviewed the submittals and conducted interviews with six (6) firms.
Through this process ELS Archtecture and Urban Design was selected as the top ranked firm and staff conducted
reference checks. A contract has now been negotitated and is attached for Council consideration for approval.
The professional services contract with this firm is structured as a master contract with specific scope of work
items identified. The design work for the project will move forward in phases with City approval required for each
phase before proceeding.
Significant aspects of the contract include requirements to conduct community meetings for public input, monthly
progress meetings with the City Manager and relevant staff, timeline schedules and rate schedules for scope of
work phases, and regular meetings with a design steering committee.
FUNDING:
$ 233,000 From COP Financing for construction of General Fund Capital Projects for Basic Design Services.
$ 23,300 From COP Financing for construction of General Fund Capital Projects for reimburseables.
$12,775 From COP Financing for construction of General Fund Capital Projects for 5% contingency.
$ 269,075 Total
Funding available:&A,".L
Finance Directo
n 4
Roger Baltz
Parks and Recreation Director
RB:tI
cc: City Attorney
APPROVED:
H. Dixon Flynn -- City Manager
01/29/02
AGREEMENT FOR PROFESSIONAL CONSULTING SERVICES
ARTICLE 1
PARTIES AND PURPOSE
Section 1.1 Parties
THIS AGREEMENT is entered into on by and between the
CITY OF LODI, a municipal corporation (hereinafter "CITY"), and ELS ARCHITECTURE
AND URBAN DESIGN. (hereinafter "CONSULTANT").
Section 1.2 Purpose
CITY selected the CONSULANT to provide the design services required in
accordance with attached scope of services, Exhibit A.
CITY wishes to enter into an agreement with CONSULTANT for design of the
Lodi Aquatics Facility project, (hereinafter "Project") as set forth in the Scope of Services
attached here as Exhibit A.
ARTICLE 2
SCOPE OF SERVICES
Section 2.1 Scope of Services
CONSULTANT, for the benefit and at the direction of CITY, shall perform the
scope of services as set forth in Exhibit A, attached and incorporated by this reference.
Section 2.2 Time For Commencement and Completion of Work
CONSULTANT shall commence work within ten (10) days of executing this
agreement, and complete work under this agreement based on the timeline shown in
Exhibit A.
CONSULTANT shall submit to CITY the design improvement plans, special
provisions, and other project deliverables for the project, as indicated on the project
design schedule attached to the project scope.
CONSULTANT shall not be responsible for delays caused by the failure of CITY
staff or agents to provide required data or review documents within the appropriate time
frames. The review time by CITY and any other agencies involved in the project shall
not be counted against CONSULTANT's contract performance period. Also, any delays
beyond CONSULTANTS reasonable control such as due to weather, vandalism, acts of
God, etc., shall not be counted. CONSULTANT shall remain in contact with reviewing
agencies and make all efforts to expedite the review process and the return of all
comments.
ELS Architecture Agreement - Aquatics 1
Section 2.3 Meetings
CONSULTANT shall attend meetings as indicated in the Scope of Services,
Exhibit A.
Section 2.4 Staffing
CONSULTANT acknowledges that CITY has relied on CONSULTANT's special
capabilities and on the qualifications of CONSULTANT's principals and staff as identified
in its proposal to CITY. The scope of services shall be performed by CONSULTANT,
unless agreed to otherwise by CITY in writing. CITY shall be notified by CONSULTANT
of any change of Project Manager and CITY is granted the right of approval of all
original, additional and replacement personnel in CITY's sole discretion and shall be
notified by CONSULTANT of any changes of CONSULTANT's project staff prior to any
change.
CONSULTANT certifies that it is prepared to and can perform all services within
the scope of services within the time frame specified in Exhibit A. Owner agrees,
however, that CONSULTANT shall not be responsible for unanticipated changes,
unknown conditions, or delays beyond CONSULTANT'S reasonable control.
CONSULTANT represents and warrants that it has, or will have at the time this
agreement is executed, all licenses, permits, qualifications, insurance and approvals of
whatsoever nature are legally required for CONSULTANT to practice its profession, and
that CONSULTANT shall, at its own cost and expense, keep in effect during the life of
this agreement all such licenses, permits, qualifications, insurance and approvals.
Section 2.5 Subcontracts
CITY acknowledges that CONSULTANT may subcontract certain portions of the
scope of services to subconsultants as specified and identified in Exhibit A. Should any
subconsultants be replaced or added after CITY's approval, CITY shall be notified within
ten (10) days and said subconsultants shall be subject to CITY's approval prior to
initiating any work on the Project. CONSULTANT shall remain fully responsible for the
complete and full performance of said services and shall pay all such subconsultants.
ELS Architecture Agreement - Aquatics 2
ARTICLE 3
COMPENSATION
Section 3.1 Compensation
CONSULTANT's compensation for all work under this agreement shall not
exceed the provisions of Exhibit B and associated charge rate schedule, Exhibit C,
attached and incorporated by this reference.
CONSULTANT shall not undertake any work beyond the scope of this agreement
unless such additional work is approved in advance and in writing by CITY.
Section 3.2 Method of Payment
CONSULTANT shall submit invoices for completed work on a monthly basis,
providing, without limitation, details as to amount of hours, individual performing said
work, hourly rate, and indicating to what aspect of the scope of services said work is
attributable. CITY shall verify the correctness of each invoice and shall notify
CONSULTANTS with ten (10) working days of any questions regarding invoiced items.
CITY shall pay CONSULTANT in a timely manner.
Section 3.3 Costs
The fees shown on Exhibits B and C include costs required for the performance
of the individual work tasks by CONSULTANT and/or subconsultant. Payment of
reimbursable costs directly related to the Project as identified in Exhibit B shall apply.
CONSULTANT charge rates are attached and incorporated with Exhibits B
and C. The charge rates for CONSULTANT shall remain in effect and unchanged for
the duration of the Project unless approved by CITY.
Section 3.4 Auditing
CITY reserves the right to periodically audit all charges made by CONSULTANT
to CITY for services under this Agreement. Upon request, CONSULTANT agrees to
furnish CITY, or a designated representative, with necessary information and assistance.
CONSULTANT agrees that CITY or its delegate will have the right to review,
obtain and copy all records pertaining to performance of this Agreement.
CONSULTANT agrees to provide CITY or its delegate with any relevant information
requested and shall permit CITY or its delegate access to its premises, upon reasonable
notice, during normal business hours for the purpose of interviewing employees and
inspecting and copying such books, records, accounts, and other material that may be
relevant to a matter under investigation for the purpose of determining compliance with
ELS Architecture Agreement - Aquatics 3
this requirement. CONSULTANT further agrees to maintain such records for a period of
three (3) years after final payment under this Agreement.
ARTICLE 4
MISCELLANEOUS PROVISIONS
Section 4.1 Nondiscrimination
In performing services under this agreement, CONSULTANT shall not
discriminate in the employment of its employees or in the engagement of any
subconsultants on the basis of race, color, religion, sex, sexual orientation, marital
status, national origin, ancestry, age, or any other criteria prohibited by law.
Section 4.2 Insurance Requirements
CONSULTANT shall at all times maintain at CONSULTANT's expense
professional liability insurance coverage in the amount of $1,000,000. CONSULTANT's
insurance carrier or CONSULTANT shall provide thirty (30) days written notice to CITY
prior to canceling or changing the terms of such coverage.
In accordance with the provisions of Section 3700 of the California Labor Code,
CONSULTANT shall secure at its own expense and maintain during the life of this
agreement, Workers' Compensation coverage for its employees as necessary to protect
CONSULTANT and its employees under the Workers' Compensation Insurance and
Safety Act. Such insurance shall be in standard form and shall relieve CITY of all
responsibility for such claims and/or liability.
In addition to Workers' Compensation and Professional Liability Insurance,
CONSULTANT shall comply with the insurance requirements set forth in Exhibit E,
which is attached to this agreement and incorporated by this reference.
Section 4.3 Attorney's Fees
In the event any dispute between the parties arises under or regarding this
agreement, the prevailing party in any litigation of the dispute shall be entitled to
reasonable attorney's fees from the party who does not prevail as determined by the
court.
Section 4.4 Successors and Assigns
CITY and CONSULTANT each bind themselves, their partners, successors,
assigns, and legal representatives to this agreement without the written consent of the
others. CONSULTANT shall not assign or transfer any interest in this agreement without
ELS Architecture Agreement - Aquatics 4
the prior written consent of CITY. Consent to any such transfer shall be at the sole
discretion of CITY.
Section 4.5 Notices
Any notice required to be given by the terms of this agreement shall be deemed
to have been given when the same is personally served or sent by certified mail or
express or overnight delivery, postage prepaid, addressed to the respective parties as
follows:
To CITY: City of Lodi
Parks and Recreation Director
221 West Pine Street
P.O. Box 3006
Lodi, CA 95241-1910
To CONSULTANT: ELS ARCHITECTURE AND URBAN DESIGN
Attention: David Petta
2040 Addison Street
Berkeley, CA 94704
Section 4.6 Cooperation of CITY
CITY shall cooperate fully in a timely manner in providing relevant information
that it has at its disposal.
Section 4.7 Consultant is Not an Employee of CITY
It is understood that CONSULTANT is not acting hereunder in any manner as an
employee of CITY, but solely under this agreement as an independent contractor. CITY
shall not under any circumstances be liable to CONSULTANT or any person or persons
acting for or under it for any deaths, injuries, or property damage received or claimed,
unless any such liability arises by virtue of the sole negligence by CITY, its officers,
agents, or employees. CONSULTANT agrees to indemnify, defend and hold CITY free
and harmless from any and all liability therefor which is due to any negligent acts, errors
or omission of CONSULTANT or any of its officers, agents, employees or
subconsultants.
Section 4.8 Termination
Either party may terminate this agreement by giving either party at least ten (10)
days written notice. Where phases are anticipated within the Scope of Services, CITY
may terminate at the conclusion of any such phase. Upon termination, CONSULTANT
shall be entitled to payment as set forth in the attached Exhibit B to the extent that the
work has been performed. Upon termination, CONSULTANT shall immediately suspend
all work on the Project and deliver any documents or work in progress to CITY.
ELS Architecture Agreement - Aquatics 5
However, CITY shall assume no liability for costs, expenses or lost profits resulting from
services not completed or for contracts entered into by CONSULTANT with third parties
in reliance upon this agreement.
Section 4.9 Severability
The invalidity in whole or in part of any provision of this agreement shall not void
or affect the validity of any other provision of this agreement.
Section 4.10 Captions
The captions of the sections and subsections of this agreement are for
convenience only and shall not be deemed to be relevant in resolving any question or
interpretation or intent.
Section 4.11 Integration and Modification
This Agreement represents the entire integrated agreement between
CONSULTANT and CITY; supersedes all prior negotiations, representations, or
agreements, whether written or oral, between the parties; and may be amended only be
written instrument signed by CONSULTANT and CITY.
Section 4.12 Applicable Law
This agreement shall be governed by the laws of the State of California.
Section 4.13 Contract Terms Prevail
All exhibits and this agreement are intended to be construed as a single
document. Should any inconsistency occur between the specific terms of this
agreement and the attached exhibits, the terms of this agreement shall prevail.
Section 4.14 Authority
The undersigned hereby represent and warrant that they are authorized by the
parties to execute this agreement.
Section 4.15 Ownership of Documents
All documents, photographs, reports, analyses, audits, computer tapes or cards,
or other material documents or data, and working papers, whether or not in final form,
which have been obtained or prepared for this project, shall be deemed the property of
CITY upon payment for services due to CONSULTANT. Upon CITY's request,
CONSULTANT shall allow CITY to inspect all such documents during regular business
hours. Upon termination or completion, all information collected, work product and
documents shall be delivered by CONSULTANT to CITY within ten (10) days.
ELS Architecture Agreement - Aquatics 6
CITY agrees to indemnify, defend and hold CONSULTANT harmless from any
liability resulting from CITY's use of such documents for any purpose other than the
purpose for which they were prepared.
Section 4.16 Hazardous Materials
The CONSULTANT and CONSULTANTS sub -consultants shall have no
responsibility for the discovery, presence, handling, removal, disposal of or exposure of
persons to hazardous materials in any form at the project site, including but not limited
to, asbestos, asbestos products, polychlorinated biphenyl (PCB) or other toxic
substances.
Section 4.17 Electronic Data Files
If the CITY, or others through the CITY, request copies of electronic data files
("CAD Data") prepared by CONSULTANT or its consultants for the Work, the parties
agree to execute the CONSULTANT'S CAD Agreement which is attached as Exhibit D
and incorporated by this reference prior to the transfer of such CAD Data.
IN WITNESS WHEREOF, CITY and CONSULTANT have executed this
agreement as of the date first above written.
CITY OF LODI, a municipal corporation
ATTEST:
By By
SUSAN J. BLACKSTON H. DIXON FLYNN
CITY CLERK CITY MANAGER
APPROVED AS TO FORM:
Dated:
ELS ARCHITECTURE AND URBAN
DESIGN
:
By 1 i ' By:
Ry4N ALL A� YS --
CITY ATTORNEY Its:
ELS Architecture Agreement - Aquatics 7
Lodi Aquatics Facility Agreement
Exhibit A
SCOPE OF SERVICES
1.0 CONSULTANT'S SERVICES
1.1 The Consultant's services consist of those services performed by the Architect and
Architect's consultants as enumerated below. These services shall be performed as
expeditiously as is consistent with professional skill and care and the orderly progress of
the Project. The Consultant shall submit for the City's approval, and periodically adjust a
schedule for the performance of the Consultant's services. Time limits established by this
schedule and approved by the City shall not, except for reasonable cause, be exceeded by
the Consultant or City.
2.0 PLANNING PHASE
2.1 The Consultant shall analyze the City's needs, review existing program information
furnished by the City, and provide a final program for the Project.
2.2 The Consultant shall provide a preliminary evaluation of the City's site for the Project
based on the information provided by the City of site conditions and the City's program
schedule and budget for the Cost of the Project.
2.3 The Consultant shall review the City's proposed method of contracting for construction
services and shall notify the City of anticipated impacts that such method may have on the
City's program, financial and time requirements, and the scope of the Project.
3.0 SCHEMATIC DESIGN PHASE
3.1 Based on the approved Program and any further adjustments in the scope or quality of the
Project or in the construction budget authorized by the City, the Consultant shall begin the
Schematic Design Phase.
3.2 The Consultant shall review with the City alternative approaches to design and
construction of the Project.
3.3 Based on the mutually agreed-upon program, schedule and construction budget
requirements, the Consultant shall prepare, for approval by the City, Schematic Design
Documents consisting of drawings and other documents illustrating the scale and
relationship of Project components.
3.4 The Consultant shall submit to the City a preliminary estimate of Construction Cost based
on current area, volume or similar conceptual estimating techniques.
4.0 CONSTRUCTION DOCUMENTS PHASE
4.1 Based on the approved Schematic Design Documents and any further adjustments in the
scope or quality of the Project or in the construction budget authorized by the Agency, the
Consultant shall prepare, for approval by the City, Design Development Documents
consisting of Drawings and other documents to fix and describe the size and character of
the Project as to architectural, structural, mechanical and electrical systems, materials and
such other elements as may be appropriate.
4.2 The Consultant shall advise the City of any adjustments to the preliminary estimate of
Construction Cost.
Lodi Aquatics Facility Agreement
Exhibit A: Scope of Services
Page 2
4.3 Based on the approved Design Development Documents and any further adjustments in
the scope or quality of the Project or in the construction budget authorized by the City, the
Consultant shall prepare, for approval by the City, Construction Documents consisting of
Drawings and Specifications setting forth in detail the requirements for the construction of
the Project.
4.4 The Consultant shall assist the City in the preparation of the necessary bidding
information, bidding forms, the Conditions of the Contract, and the form of Agreement
between the City and the Contractor.
4.5 The Consultant shall advise the City of any adjustments to previous preliminary estimates
of Construction Cost indicated by changes in requirements or general market conditions.
4.6 The Consultant shall assist the City in connection with the City's responsibility for filing
documents required for the approval of governmental authorities having jurisdiction over
the Project.
5.0 BIDDING OR NEGOTIATION PHASE
5.1 The Consultant, following the City's approval of the Construction Documents and of the
latest preliminary estimate of Construction Cost, shall assist the City on obtaining bids or
negotiated proposals and assist in awarding and preparing contracts for construction.
6.0 CONSTRUCTION PHASE -ADMINISTRATION OF THE CONSTRUCTION CONTRACT
6.1 The Consultant's responsibility to provide Basic Services for the Construction Phase under
this Agreement commences with the award of the Contract for Construction and terminates
at the earlier of the issuance to the City of the final Certificate for Payment or 30 days after
the date of Substantial Completion of the Work.
6.2 The Consultant shall provide administration of the Contract for Construction as set forth
below. Modifications made to the General Conditions, when adopted as part of the
Contract Documents, shall be enforceable under this Agreement only to the extent that
they are consistent with this Agreement or approved in writing by the Consultant.
6.3 Duties, responsibilities and limitations of authority of the Consultant under this Phase of
the work, shall not be restricted, modified or extended without written agreement of the
City and Consultant with consent of the Contractor, which consent will not be unreasonably
withheld.
6.4 The Consultant shall be a representative of and shall advise and consult with the City
during the administration of the Contract for Construction. The Consultant shall have the
authority to act on behalf of the City only to the extent provided in this Agreement unless
otherwise modified by written amendment.
6.5 Consultant's Proposal includes periodic site visits. These visits are for the purpose of
becoming generally familiar with and to keep the City informed about the progress and
Lodi Aquatics Facility Agreement
Exhibit A: Scope of Services
Page 3
quality of the portion of the Work completed to determine in general if the Work is being
performed in a manner indicating that the Work, when fully completed, will be in
accordance with the Contract Documents. The Consultant shall neither have control over
or charge of, nor be responsible for, the construction means, methods, techniques,
sequences or procedures, or for safety precautions and program in connection with the
Work, since these are solely the Contractor's rights and responsibilities under the Contract
Documents.
6.6 The Consultant shall report to the City known deviations from the Contract Documents and
from the most recent construction schedule submitted by the Contractor. However, the
Consultant shall not be responsible for the Contractor's failure to perform the Work in
accordance with the requirements of the Contract Documents. The Consultant shall be
responsible for the Consultant's negligent acts or omissions, but shall not have control over
or charge of and shall not be responsible for acts or omissions of the Contractor,
Subcontractors, or their agents or employees, or of any other persons or entities
performing portions of the Work.
6.7 The Consultant shall at all times have access to the Work wherever it is in preparation or
progress.
7.0 CERTIFICATES FOR PAYMENT
7.1 The Consultant shall assist City to determine amounts due the Contractor.
7.2 The Consultant's review for payment shall constitute a representation to the City, based on
the Consultant's evaluation of the Work as provided in 7.5 above, and on the data
comprising the Contractor's Application for Payment, that the Work has progressed to the
point indicated and that, to the best of the Consultant's knowledge, information and belief,
the quality of the Work is in accordance with the Contract Documents. The foregoing
representations are subject (1) to an evaluation of the Work for conformance with the
Contract Documents upon Substantial Completion, (2) to results of subsequent tests and
inspections, (3) to correction of minor deviations from the Contract Documents prior to
completion, and (4) to specific qualifications expressed by the Consultant.
7.3 The review of payment amount shall not be a representation that the Consultant has (1)
made exhaustive or continuous on-site inspections to check the quality or quantity of the
Work, (2) reviewed construction means, methods, techniques, sequences or procedures,
(3) reviewed copies of requisitions received from Subcontractors and material suppliers
and other data requested by the City to substantiate the Contractor's right to payment, or
(4) ascertained how or for what purpose the Contractor has used money previously paid on
account of the Contract Sum.
7.4 The Consultant shall have authority to reject Work that does not conform to the Contract
Documents. Whenever the Consultant considers it necessary or advisable, the Consultant
shall have authority to require inspection or testing of the Work in accordance with the
provisions of the Contract Documents, whether or not such Work is fabricated, installed or
completed. However, neither this authority of the Consultant nor a decision made in good
Lodi Aquatics Facility Agreement
Exhibit A: Scope of Services
Page 4
faith to exercise or not to exercise such authority shall give rise to a duty or responsibility
of the Consultant to the Contractor, Subcontractors, material and equipment suppliers,
their agents or employees or other persons or entities performing portions of the Work.
7.5 The Consultant shall review or take other appropriate action upon the Contactor's
submittals, such as Show Drawings, product Data and Samples, reviewed by the
Consultant, but only for the limited purpose of checking for the visual design concept
expressed in the Contract Documents. The Consultant's action shall be taken with
reasonable promptness as to cause no delay in the Work or in the activities of the City,
Contactor or separate contractors, while allowing sufficient time to permit adequate review.
Review of such submittals is not conducted for the purpose of determining the accuracy
and completeness of other details such as dimensions and quantities, or for substantiating
instructions for installation or performance of equipment or systems, all of which remain
the responsibility of the Contractor as required by the Contract Documents. The
Consultant's review shall not constitute approval of safety precautions or, unless otherwise
specifically stated by the Consultant, of any construction means, methods, techniques,
sequences or procedures. The Consultant's review of a specific item shall not indicate
approval of an assembly of which the item is a component.
7.6 If professional design services or certifications by a design professional related to systems,
materials or equipment are specifically required of the Contractor by the Contract
Documents, the Consultant shall specify appropriate performance and design criteria that
such services must satisfy. Shop Drawings and other submittals related to the work
designed or certified by the design professional retained by the Contractor shall bear such
professional's written approval when submitted to the Consultant. The Consultant shall be
entitled to rely upon the adequacy, accuracy and completeness of the services,
certifications or approvals performed by such design professionals.
7.7 If approved as an Additional Service, the Consultant shall prepare Change Orders &
Construction Change Directives with supporting documentation and data if deemed
necessary by the Consultant, for the City's approval and execution in accordance with the
Contract Documents, and may authorize minor changes in the Work not involving an
adjustment in the Contract Sum or an extension of the Contract Time which are consistent
with the intent of the Contract Documents.
7.8 The Consultant shall conduct inspections to determine the date or dates of Substantial
Completion and the date of final completion, shall receive from the Contractor and forward
to the City, for the City's review and records, written warranties and related documents
required by the Contract Documents and assembled by the Contractor, and shall review a
final Certificate for Payment based upon a final inspection indicating the Work complies
with the requirements of the Contract Documents.
8.0 ADDITIONAL SERVICES
8.1 The services described in this Section 9 are not included in Basic Services and they shall
be paid for by the City as provided in this Agreement, in addition to the compensation set
forth in Consultant's Proposal. The services described under this section shall only be
Lodi Aquatics Facility Agreement
Exhibit A: Scope of Services
Page 5
provided if authorized or confirmed in writing by the Agency.
8.2 If more extensive representation at the site than is described in Paragraph 7.5 is required,
such additional project representation shall be provided, including services required due to
delays in construction not due to the fault of Consultant.
8.3 Making revisions in drawings, specifications or other documents when such revision are:
8.3.1 inconsistent with approvals or instructions previously given by the City, including
revisions made necessary by adjustments in the City's program or Project budget
after final construction cost estimate is obtained;
8.3.2 required by the enactment or revision of codes, laws or regulations subsequent to
the preparation of such documents; or
8.3.3 due to changes required as a result of the City's failure to render decisions in a
timely manner.
8.3.4 due to Contractor's recommendations to vary from Contract Documents or
Contractor's proceeding with work inconsistent with Contract Documents.
8.4 Providing services required because of significant changes in the Project including, but not
limited to size, budget, quality or complexity.
8.5 Preparing Drawings, Specifications and other documentation and supporting data,
evaluating Contractor's proposals, and providing other services in connection with Change
Orders.
8.6 Providing services in connection with evaluating substitutions proposed by the Contractor
and making subsequent revisions to Drawings, Specifications and other documentation
resulting therefrom.
8.7 Providing services directly attributable to and required as a result of extension in the
design schedule of more than 10%, or construction schedule, for reasons outside the
control of the Consultant, except as a result of formal suspension or termination.
8.8 Providing consultation concerning replacement of Work damaged by fire or other cause
during construction and furnishing services required in connection with the replacement of
such Work.
8.9 Providing services made necessary by the default of the Contractor, by major defects or
deficiencies in the Work of the Contractor, or by failure of performance of either the City or
Contractor under the Contract for Construction.
8.10 Providing services in evaluating an extensive number of claims submitted by the
Contractor or others in connection with the Work.
Lodi Aquatics Facility Agreement
Exhibit A: Scope of Services
Page 6
8.11 Providing services in connection with a public hearing arbitration proceeding or legal
proceeding except where the Consultant is a party thereto.
8.12 Preparing documents for alternate, separate or sequential bids or providing services in
connection with bidding, negotiation or construction prior to the completion of the
Construction Documents Phase.
8.13 Financial feasibility studies, market analyses, and revenue, operating and maintenance
cost projections.
8.14 Providing presentation models or professional renderings or artwork.
9.0 CITY'S RESPONSIBILITIES
9.1 The City shall designate a representative authorized to act on the City's behalf with respect
to the Project. The City or such authorized representative shall render decisions in a
timely manner pertaining to documents submitted by the Consultant in order to avoid
unreasonable delay in the orderly and sequential progress of the Consultant's services.
9.2 The City shall furnish surveys to describe physical characteristics, legal limitations and
utility locations for the site of the Project, a written legal description of site. The surveys
and legal information shall include, as applicable, grades and lines of streets, alleys,
pavements and adjoining property and structures, adjacent drainage, right-of-way
restrictions, easements, encroachments, zoning, deed restrictions, boundaries and
contours of the site locations, dimensions and necessary data with respect to existing
buildings, other improvements and trees, and information concerning available utility
services and lines, both public and private, above and below grade, including inverts and
depths. All the information on the survey shall be referenced to a Project benchmark.
9.3 The City shall furnish the services of geotechnical engineers when such services are
requested by the Consultant. Such services may include but are not limited to test
borings, test pits, determinations of soil bearing values, percolation tests, evaluations of
hazardous materials, ground corrosion tests and resistivity tests, including necessary
operations for anticipating subsoil conditions, with reports and appropriate
recommendations.
9.4 The City shall furnish the services of consultants other than those designated in ELS'
proposal when such services are requested by the Consultant and are reasonably required
by the scope of the project.
9.5 The City shall furnish structural, mechanical, and chemical tests; tests for air and water
pollution; tests for hazardous materials and other laboratory and environmental tests,
inspections and reports required by law or the Contract Documents.
9.6 The City shall provide prompt written notice to the Consultant if the City becomes aware of
any fault or defect in the Project, including any errors, omissions or inconsistencies in the
Lodi Aquatics Facility Agreement
Exhibit A: Scope of Services
Page 7
Consultant's Instruments of Service.
9.7 Consultant will incorporate into the work plan and bid documents if necessary, all
information provided by Agency regarding the discovery, analysis and mitigation of
hazardous materials.
10.0 CONSTRUCTION COST
10.1 The Construction Cost shall be the total cost or, to the extent the Project is not completed,
the estimated cost to the City of all elements of the Project designed or specified by the
Consultant.
10.2 The Construction Cost shall include the cost at current market rates of labor and materials
designed and or specified by Consultant and as approved or furnished by the City and
equipment design, specified, selected or specially provided for by the Consultant, including
the costs of supervision of construction or installation provided by a separate contractor,
plus a reasonable allowance for their overhead and profit. In addition, a reasonable
allowance for contingencies shall be included for market conditions at the time of bidding
and for changes in the Work.
10.3 Construction Cost does not include the compensation of the Construction Manager, the
Project Manager, the Consultant and the Consultant's consultants, the costs of the land,
rights-of-way and financing or other costs that are the responsibility of the City.
11.0 RESPONSIBILITY FOR CONSTRUCTION COST
11.1 Evaluations of the City's project budget, and any estimates of Construction Cost by the
Consultant, represent the Consultant's judgment as a design professional familiar with the
construction industry. It is recognized, however, that neither the Consultant nor the
Agency has control over the cost of labor, materials or equipment, over the Contractor's
method of determining bid prices, or over competitive bidding, market or negotiating
conditions. Accordingly, the Consultant cannot and does not warrant or represent that bids
or negotiated prices will not vary from the City's project budget or from any estimate of
Construction Cost or evaluation prepared or agreed to by the Consultant.
Lodi Aquatic Facility Agreement
Exhibit A
LTUG1:1:i1"X-1
Refer to attached preliminary project schedule
PLANNING PHASE
Task I: Startup
Meet with Project Manager, and other key staff from the Parks and Recreation Department. Afterwards,
hold a Kickoff Meeting with all concerned City departments and key individuals one-on-one or
collectively to get broad input that is pertinent to the project, and to establish points -of -contact. Agenda
for these staff meeting/s may include the following:
• Project vision and goals statements, if any
• Status of program for pools and support spaces
• Review progress towards site acquisition
• Project budget, outside fundraising (if any), financial parameters and energy/sustainability goals, if any
• Refine schedule and work plan
• Discuss alternative project delivery methods
Convene Steering Committee Meeting No.1 as soon as possible after, or on the same day as the staff
kickoff meeting. Design Team representatives will include ELS key individuals and Aquatic Design
Group. Agenda for this meeting may include the following:
• Summarize project vision and goals statements, if any
• Brief presentation of ELS team qualifications, from interview, including an expanded site analysis
• Discuss national/regional trends in community aquatic facilities
• Program for pools and support spaces
• Review progress towards site acquisition
• Project budget, financial parameters and energy/sustainability goals, if any
• Schedule and work plan
• Discuss possible field trip to comparable projects, in operation
Client tasks:
• Assemble and notify Steering Committee
• Provide relevant background information to ELS
• Provide site topographic and boundary survey
• Define site boundaries
• Establish working budget
ELS Work Product: Memo report of proceedings and conclusions
Task 2: Investigation and Site Plan Alternatives
Review background materials, including utility plans. Visit points of particular project interest or relevance
in Lodi. Meet individually or in small groups with City staff, City officials and facility users to clarify points
of program or process. Attend field trip for Steering Committee and other interested individuals to
comparable facilities.
Finalize program, including space allocation, adjacencies, priority weighting, phasing considerations, and
general finishes, materials and building systems. Produce at least 3 alternative site plans. Estimate the
range of probable construction costs. Meet with PRD project manager to preview work in progress
(typical, prior to each Steering Committee meeting).
Lodi Aquatic Facility Agreement
Exhibit A: Work Plan
Page 2
Convene Steering Committee Meeting No. 2. The City and consultants will summarize work progress
since the first meeting. The Design Team will present and look for guidance from the Steering
Committee regarding the following:
• Final draft of space program
• Site plan alternatives; selection of preferred alternative
• Progress report on probable construction costs
Client tasks:
• Facilitate arrangements for interviews, meetings and field trip
• Confirm program priorities, act as "tie-breaker'
• Confirm construction budget
ELS Work Product: Memo report, including preliminary program, and site plan options.
Task 3: Develop Preferred Site Plan
Finalize the preferred site plan, including floor plans, elevations, 3-dimensional sketch. Update
construction cost projection to conform to preferred plan. Meet with PRD project manager to preview
work.
Convene Steering Committee Meeting No. 3. The City and consultants will summarize work progress
since the first meeting. The ELS team will present and receive comments regarding the following:
• Preferred plan, with elevations and sketches
• Final draft of probable construction costs
Conduct Public Workshop
Client tasks:
• Setup Public Workshop
• Provide information needed for a full project budget, including administrative costs
• Provide schedule input regarding project review and approvals process
• Determine fundraising strategies
• Approve progress to date
ELS Work Product: Complete the final Project Planning Report consisting of all previous memo reports,
meeting minutes, reduced drawings and budget and schedule information. The report will be 8'/2 x 11 in
black and white, suitable for photocopy reproduction. Following the Steering Committee meeting, the
ELS team with all concerned City departments and key individuals one-on-one or collectively to update
them on progress to date.
SCHEMATIC DESIGN PHASE
Upon the City's written authorization to proceed, the Schematic Design will pick up from the approved
project site plan, starting with a kickoff meeting with PRD to confirm final Planning Phase comments.
Convene Steering Committee Meeting No. 4. At 50% Schematic Design, presentation will include:
• General building massing
• Illustrative landscape plan
• Enlarged pool plans and sections; floor plans
Lodi Aquatic Facility Agreement
Exhibit A: Work Plan
Page 3
• Building elevations with colors and finishes
• Design images from similar projects
• Comparative cost analysis of any alternatives
Client tasks:
• Provide soils report
• Design guidelines, if any, for systems specifications
• Design assessment, from an operational and maintenance perspective
• Designate and begin to involve construction phase Project Manager
• Start selection process for if project delivery is to be via Construction Manager
• Approval of design direction
ELS Work Product: Meeting notes with attached reduced graphic materials
At completion of 100% Schematic Design Steering Committee Meeting No. 5 will be held to review:
• Final documents, including engineering documents
• Cost estimate
• Presentation model
ELS Work Product: Schematic drawings and outline specifications; full-size and reduced plans;
schematic levet cost estimate.
Following the meeting, the ELS team will meet with all concerned City departments and key individuals
one-on-one or collectively to update them on progress to date. Presentation will be made to
Commissions and Council.
Client task: Approval of final work products
CONSTRUCTION DOCUMENTS PHASE
Upon the City's written authorization to proceed, the Construction Documents Phase will proceed from
the approved Schematic Design documents, starting with a kickoff meeting with PRD staff to evaluate
final Schematic Phase comments.
Client tasks:
• Comment on 90% construction documents
• Provide front end specification sections
• Approval of final work products
Products: Full size 90% complete and 100%, Final Bid documents, including specifications. Final CD
phase cost estimate.
At the conclusion of the CD phase, the ELS team will meet with all concerned City departments and key
individuals one-on-one or collectively to update them on progress to date. Plans will be made available
for review and comment by Steering Committee members. Plans will be submitted for permit. Upon
approval by Commissions and Council, bid/negotiation sets will be reproduced.
BID AND PERMIT PHASE
The Bid and Permit phase will proceed from the approved Construction Documents. ELS will submit
plans for permitting and provide final revisions as may be required. Originals of bid documents will be
provided to the City for reproduction and distribution. The ELS team will conduct a pre-bid walkthrough,
respond to bidders' questions, issue addenda as necessary, attend the bid opening, and assist PRD in
evaluating bid results.
Lodi Aquatic Facility Agreement
Exhibit A: Work Plan
Page 4
Client tasks:
• Distribute documents, including bid period information and addenda
• Submit permit and plan check fees
• Make arrangements for walk-through and bidder meetings
Products: Addenda as may be necessary.
CONSTRUCTION PHASE
The Construction phase will commence with the Notice to Proceed to the Contractor or CM, and will
conclude with the approval of final payment. ELS will make monthly, or twice monthly site visits that will
include attending construction progress meetings. Oral communications, meeting deliberations, and
visual observations will be clearly summarized in writing, and serve as a permanent record of daily
construction oversight activity.
Client tasks: Provide a project manager to attend meetings and provide prompt direction and approvals
to the Architect and the Contractor during construction
Product: Site visit notes, clarification sketches and RFI responses. Written review of change proposals
and substitutions.
POST CONSTRUCTION PHASE
Post construction phase will include building commissioning sessions with Contractor and building
manager and design consultants. Post occupancy review will take place at one-year anniversary of
occupancy, and will mark the end of the major contractor warranty period. Evaluation will include how
well the project achieved its goals, which may include financial, cost, energy, and the original vision.
Client tasks: Assist with arrangements to set up meetings
Product: Site visit notes; evaluation memo report.
End of Work Plan
>v
N
W
1
0
N
O
A
O
A
3
O
W
O
N
T
O
ELS
ARCHITECTURE AND URBAN DESIGN
2040 Addison Street Berkeley, CA 94704
510.549.2929 510.843.3304 fast
January 29, 2002
Mr. Roger Baltz
Parks and Recreation Department,
City of Lodi
125 North Stockton Street
Lodi, CA 95240
SUBJECT: Aquatic Facility
Proposal for Design Services
Dear Mr. Baltz:
EXHIBIT B
ELS is pleased to present this proposal to provide planning and design services for the City of Lodi's new
Aquatic Facility. This proposal includes services for Planning, Schematic Design, Construction Documents,
Bidding/Negotiation and the Construction Phase as outlined in this Proposal.
Our preferred Design Team includes the following subconsultants:
Pool Design
Aquatic Design Group, Carlsbad
Civil
Baumbach & Piazza, Lodi
Landscape
SWA Group, San Francisco
Structural
SOHA Engineers, San Francisco
Mechanical
Capital Engineering, Sacramento
Electrical
The Engineering Enterprise, Alameda
Estimating
Davis, Langdon Adamson, Sacramento
We have not yet requested proposals from these subconsultants, until the completion of the planning phase,
including final programming and further site investigations. At that point enough detail will be available for them
to accurately assess the full scope of their work. We will make every effort to negotiate agreements with each
subconsultant, and will not make any change in this team without the City's concurrence.
ASSUMPTIONS
General
• The site for the Aquatic Facility is the approximately 3 acre parcel indicated on the attachment to the City's
Request for Qualifications (however, the exact extent of pools and buildings indicated on that attachment is
yet to be determined).
• The City of Lodi will be responsible for providing all reports and information necessary for ELS and our
consultants to complete our work including, but not limited to soils and geophysical reports for the site.
• Progress meetings with DPR staff are included as may be necessary, throughout the overall timeframe
shown on the schedule.
• Specific allowance has been included for meetings and presentations to steering committees, public
workshops, Commissions, SPARC and Council as per the attached work plan and schedule.
• A maximum of 17 (one monthly, plus 4 additional) site visits for ELS during bid and construction phases is
included, including all pre-bid, bid review, start-up, completion/punch list and post construction activities.
Visits by individual subconsultants will be enumerated in their individual proposals at the conclusion of the
planning phase.
Lodi Aquatics Facility Agreement
Exhibit B: Proposal Letter
January 25, 2002
Page 2 of 2
• Financial feasibility studies, market analyses, and revenue, operating and maintenance cost projections may
be provided as an Additional Service.
• Increases to overall construction budget of $2,775,000 may result in Additional Services.
Aquatics Facility Com ensation:
Fees by
Pool Design
Landscape
Civil Architecture, Struct /
Total
Phase
Mech / Elect
Engineering, Cost
Estimating
Survey
$7,150
$7,150
Planning
$3,500
1 $6,000
$2,000 1 $13,500
$25,000
Schematic
(Landscape, civil, pool, structural, mechanical, electrical engineering and
$30,000
Design
cost estimating included, but detailed breakdown not yet available
Construction
(Landscape, civil, pool, structural, mechanical, electrical engineering and
$120,000
Documents
cost estimating included, but detailed breakdown not yet available
Bidding
(Landscape, civil, pool, structural, mechanical, electrical engineering and
$10,000
cost estimating included, but detailed breakdown not yet available
Construction
Detailed breakdown not yet available; allow for 400 hours total
$40,000
Total
(Landscape, civil, pool, structural, mechanical, electrical engineering and
$232,150
cost estimating included, but detailed breakdown not yet available
Professional fees are "not -to -exceed" amount, billed hourly. Not -to -exceed amounts are intended to be
cumulative, as each phase is completed, such that unbilled portions of any single phase may be applied to
subsequent phases. The City and Consultant agree that the not -to -exceed amount for the Construction Phase
is an estimate only, and may be subject to a request for increase, since the level of construction phase services
required are often beyond the control of Consultant and difficult to anticipate.
Reimbursable expenses will be billed per the ELS rate schedule (Agreement Exhibit C). Expenses shall not
exceed 10% of the amount of the fee, or $23,000, without advance notice and prior written approval.
Presentation model and professional renderings are in addition to the basic compensation above.
Please give me a call with any questions you may have. We look forward to our work with the City of Lodi and
will start immediately upon acceptance of an agreement.
Sincerely,
ELS
David Petta Clarence Mamuyac
Principal and Project Manager Resource Principal and Project Designer
EXHIBIT C
ELS
RATE AND EXPENSE SCHEDULE
CITY OF LODI
HOURLY BILLING RATES BY CLASSIFICATION FOR APPROVED ADDITIONAL
SERVICES:
PRINCIPALS
$120.00 - 180.00
ASSOCIATE PRINCIPALS
100.00 - 140.00
ASSOCIATES
80.00 - 120.00
PROFESSIONAL STAFF
60.00 - 110.00
TECH NICAUSUPPORT STAFF
50.00 - 80.00
Rates are subject to revision on January 1, 2004 in accordance with cost of living adjustments.
Individual billing rates and/or classifications may change during the year to reflect a change in
status and/or merit salary adjustments.
REIMBURSABLE EXPENSES:
Reimbursable expenses shall be billed at cost times 1.1 and shall include actual expenditures
made in the interest of the project, in the following categories:
Outside consultants
Expense of transportation and living expenses in connection with out-of-town travel, as
pre -authorized by the Client (international flights shall be business class)
Long distance communications and facsimiles
Reproduction and photography
Postage, shipping and delivery
Fees paid for securing approval of authorities having jurisdiction over the project
Professional renderings and models as requested by the Client and approved in writing
Invoices will be submitted monthly and are due upon receipt. Invoices more than 60 days
overdue will be subject to a handling charge of 1.5 percent per month. If the Owner fails to
make payment when due, the Architect may, at its option, upon seven days' written notice to the
Owner, suspend performance of services.
GA/Rate & Expense/Prov 2001
ELS
ARCHITECTURE AND URBAN DESIGN
January 29, 2002
Mr. Roger Baltz
Parks and Recreation Department
City of Lodi
125 North Stockton Street
Lodi, CA 95240
SUBJECT: Lodi Aquatic Facility
ELS Project No. 200118
Electronic Files Transfer Agreement
Dear Mr Baltz:
2040 Addison Street Berkeley, CA 94704
510.549.2929 510.843.3304 fax
EXHIBIT D: Sample CAD Agreement
City of Lodi ("Owner') asked ELS ("ELS") to provide Owner with copies of certain CAD data files ("CAD
Data") prepared by ELS in connection with the above referenced project ("Project"). ELS agrees to do
so pursuant to the following terms:
1. Owner will reimburse ELS any time, costs and expenses in connection with the CAD transfer. Owner
acknowledges that the transfer of CAD Data is not a sale; the CAD Data represents instruments of
professional service. As instruments of professional service, ELS makes no representations or
warranties, expressed or implied, of merchantability or fitness for a particular purpose or with respect to
the CAD Data's quality, adequacy, completeness or sufficiency, or any results to be or intended to be
achieved as to its use.
2. Owner's use of CAD Data is limited to (Click here and describe use in Detail) Owner agrees that CAD
Data may not be suitable for any other purpose.
3. Owner acknowledges that anomalies and errors can be introduced into CAD Data when it is transferred
or used in an incompatible computer environment. Further, data stored on electronic media can
deteriorate over time and become corrupted. Owner acknowledges and solely accepts the risks
associated with and/or the responsibility for CAD Data including, but not limited to, any damages to
hardware, software or computer systems or networks related to any use of the CAD Data. The CAD
Data is being furnished "as is". Owner hereby releases and holds ELS harmless from any damages or
losses of any kind, including, but not limited to, damages or losses to property or persons, including
injuries or death, or economic losses, or any consequential, special, indirect or incidental damages,
resulting from the transfer or use, reuse or modification of the CAD Data.
4. Owner is responsible for modifying its computer system to properly use the CAD Data. Owner
acknowledges that Project, as built, may vary from the CAD Data transferred to the Owner. Owner and
any users of the Data shall verify all dimensions in connection with the Data. ELS does not represent
that all of the information contained in the Data is complete or to scale. ELS shall have no duty to
modify or update the CAD Data and ELS reserves the right to retain an archival copy of the CAD Data
delivered to Owner which shall be referred to and shall be conclusive proof and govern in all disputes
over the form or content of the CAD Data furnished to Owner.
5. To the fullest extent permitted by law, Owner agrees to indemnify, defend and hold ELS and its
consultants harmless from and against any and all claims, liabilities, suits, demands, losses, costs and
expenses, including, but not limited to, reasonable attorneys' fees and all legal expenses and fees
incurred on appeal, and all interest thereon, accruing or resulting to any and all persons, firms or any
Lodi Aquatic Facility Agreement
Exhibit D: Electronic Files Transfer Agreement
January 23, 2002
Page 2of2
other legal entities on account of any damages or losses to property or persons, including injuries or
death, or economic losses arising out of the use, reuse or modification of the CAD Data, except to the
extent ELS is found to be solely or partially liable as between the parties hereto for such damages or
losses by a court or forum of competent jurisdiction.
6. (Not Used)
7. This Agreement shall be governed by California law.
B. Should any legal proceeding be commenced between the parties to this Agreement seeking to enforce
any of its provisions, the prevailing party in such a proceeding shall be entitled, in addition to such other
relief as may be granted, to a reasonable sum for attorneys' fees which shall be determined by the court
or forum in such a proceeding or in a separate action brought for that purpose.
Signing this letter indicates your agreement to the terms stated above. Unless otherwise explicitly agreed
to in writing by both parties, this Agreement shall govern any and all future transfers or use of new data, if
any, to Owner by ELS.
Accepted and agreed by
ELS
Signature
Name
Title
Date
Accepted and agreed by
(City of Lodi)
Signature
Name
Date
NOU-14-2001 14:54 CITY OF LODI PW DEPT P.16
CITY OF LODI ! LtA"Jff.JI E
221 West Pine Street, P.O. Box 3006, Lodi, Califor�hia, 95241-1910
INSTRUCTIONS/REOUIREMENI"S FOR INSURANCE COVERAGE
1. All contractors/developers who have contracts or agreements with the City are required to carry general
liability/automobile insurance.
2. A duplicate or certificate of insurance shall be delivered to the Cityprior to starting any work on a project
3. Each certificate shall contain satisfactory evidence that each carrieris required to give the City of Lodi
notice 30 days prior to the cancellation or reduction in coverage of any policy.
4. The insurance certificate must state, on its face or as an endorsement, a description of the project that it
is insuring.
5. All requirements herein provided shall appear either in the body of tie insurance policies or as
endorsements and shall specifically bind the insurance carrier.
6. The CiTY OF LODI, iTS ELECTED AND APPOINTED BOARDS, CbMMISSIONS OFFICERS
AGENTS AND EMPLOYEES, must be named as additional insured;on the face of the insurance
certificate OR as an endorsement attached to the certificate of insurance. (THE CITY OF LODI iTS
ELECTED AND APPOINTED BOARDS._COMMISSiONS. OFFICERS. AGENTS AND EMPLOYE•S,
MUST BE NAMED THE ADDITIONAL INSURED.)
7. Both the street address and the post office box of the CITY OF I.OQi must be shown along with
Number 6 above: 221 West Pine Street, P.O. Box 3006, Lodi, California, 95241-1910.
8. In addition to the additional named insured endorsement on the poliey.of insurance, said insurance policy
shall be endorsed to include the following language:
"Such insurance as is afforded by the endorsement for the additional insureds shall apply as
primary insurance. Any other insurance maintained by the Citi+ of Lodi or its officers and
employees shall be excess only and not contributing with the Coinsurance afforded by this
endorsement." ;
9. The minimum limits of such insurance shall be $1,000,000 Bodily lni�wry each occurrence/aggregate,
$1,000,000 Property Damage each occurrence/aggregate, or $1,000,000 combined single limit
Automobile insurance $1,000,000:
Contractors must carry automobile insurance;
Developers must carry only if their vehicles are used on site.
10. If the limits of coverage are not the amounts specified in Number 9 above, and/or if the City is not named
as an additional insured on the certificate of insurance, the City will not accept the certificate of insurance
and a corrected certificate of insurance must be furnished to the Citi.
11. Contractor/Developer agrees and stipulates that any insurance coverage provided to the City of Lodi
shall provide for a claims period following termination of coverage wkich is at least consistent with the
claim period or statutes of limitations found in the California Tort Clalms Act (California Government
Code Section 810 et seq.).
12. "Claims made" coverage requiring the insureds to give notice of any!potential liability during a time period
shorter than that found in the Tort Claims Act shall be unacceptable]
13. No contract agreement will be signed nor will � work begin on a pibject until the proper insurance
certificate is received.
14. If you have any questions, please call Sandy Nickel, Human Resourpes Department, at
(209) 333-6704 x2133.
TOTAL P.16
RESOLUTION NO. 2002-30
A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING THE
CITY MANAGER TO EXECUTE A PROFESSIONAL CONSULTING
SERVICES CONTRACT WITH ELS ARCHITECTURE AND URBAN
DESIGN FOR DESIGN AND CONSTRUCTION ADMINISTRATION OF
THE AQUATICS FACILITY PROJECT, AND FURTHER ALLOCATE
$269,075 FOR THE PROJECT
NOW, THEREFORE, BE IT RESOLVED, that the Lodi City Council does hereby
authorize the City Manager to execute a professional consulting services contract with ELS
Architecture and Urban Design for design and construction administration of the Aquatics
Facility Project; and
BE IT FURTHER RESOLVED, that funds in the amount of $269,075.00 be
appropriated from the Certificate of Participation Financing for construction of General Fund
Capital Projects.
Dated: February 6, 2002
---------------------------------------------------------------------
---------------------------------------------------------------------
I hereby certify that Resolution No. 2002-30 was passed and adopted by the Lodi
City Council in a regular meeting held February 6, 2002 by the following vote:
AYES: COUNCIL MEMBERS — Hitchcock, Howard, Land, Nakanishi, and
Mayor Pennino
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
SUSAN J. BLACKSTON
City Clerk
2002-30