HomeMy WebLinkAboutAgenda Report - October 17, 2001 E-09AGENDA TITLE: Contract Change Orders for Elm Street improvements, Church Street to Sacramento Street; and Appropriate Additional Funds MEETING DATE: October 17, 2001 PREPARED BY: Public Works Director RECOMMENDED ACTION: Contract Change Orders 1 through 9 are for information only; however, Council is being asked to authorize appropriation of $493,000.00 additional Capital funds to cover the remaining, anticipated construction costs associated with the Elm Street Improvements, Church Street to Sacramento Street Project. BACKGROUND INFORMATION: In accordance with the Contract Change Order Policy, the City Council is being informed of change orders for this project. The original appropriation for this project was $1,187,400.00 which included an estimated contract amount and an allowance for City -furnished materials. To expedite the completion of the work, this amount was estimated based on very preliminary architectural concept drawings, not completed construction documents. The contract was to be executed by the City Manager and included change order provisions recognizing that the plans were incomplete. The contract that was signed was for $1,160,139.04, leaving little funds for changes and contingencies. The total cost of change orders to date is $178,824.99, revising the contract amount to $1,338,963.54. We anticipate an additional $40,000 in remaining change orders. The project is approximately 95% complete with only the streetlight installation and minor punch list items remaining. Detailed below is a complete description of the work involved in the change orders to date. More detailed descriptions and backup information for these change orders are available in the Public Works Department. Proposed Change Order No. 1 - This change order is for additional underground work required to modify and work around existing, very old underground utilities not previously documented. ($33,680.73) Proposed Change Order No. 2 - This change order is for the traffic signal modification work at the intersection of Church Street and Elm Street to accommodate the new intersection geometry. ($51,855.44) Proposed Change Order No. 3 - This change order is for additional subgrade and finish grade preparation in Elm Street between Church Street and School Street. ($10,229.58) Proposed Change Order No. 4 - This change order covers the cost of reconstructing the alley north of the theater and between Church Street and School Street to improve drainage and properly repair the utility cuts. ($16,446.36) Proposed Change Order No. 5 - This change order covers the cost of additional electrical improvements, such as conduit for outdoor speakers, larger streetlight footings, and working around existing, very old underground utilities not previously documented. ($35,191.33) APPROVED: N FLYNN -- CITY MANAGER CCCO&APPROPRIATE DI 10711/01 Contract Change Orders for Elm Street Improvements, Church Street to Sacramento Street; and Appropriate Additional Funds October 17, 2001 Page 2 Proposed Change Order No. 6 - This change order covers the cost of additional paving work at the intersection of Church Street and Elm Street, and modifying the existing Elm Street parking lot entrance to F&M Bank. ($11,355.98) Proposed Change Order No. 7 - This change order covers additional grading and sawcutting to tie in the proposed Sacramento Street design with the new Elm Street design. This work was not in original contract. ($1,799.38) Proposed Change Order No. 8 - This change order covers additional paver work on the westerly side of the intersection of Elm Street and School Street. ($4,107.50) Proposed Change Order No. 9 - This change order is to cover the basement access door at Legends, driveway slabs, basement vent reconstruction, and additional alley bollards. ($14,158.69) In addition, City -supplied materials, testing, and miscellaneous expenses will increase the funding requirements ($301,000). FUNDING: Capital Funds: Street $ 285,000.00 Water $ 33,000.00 Wastewater $ 45,000.00 Electric Utility (Street Lighting Account) $130,000.00 $ 493,000.00 Funding Available: Vicky M hie, Finance Director Richard C. Prima, Jr. n Vallow Public Works Director Electric Utility Director Prepared by Charlie Swimley, Senior Civil Engineer RCP/CS/lm CCCO&APPROPRIATE 10111/01