AGENDA TITLE: Federal Funding of Street Lighting (information Only)
MEETING DATE: April 6, 1994
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Information only.
BACKGROUND INFORMATION: As indicated in the Capital Improvement Program report made to
the City Council in the fall of 1993, staff has pursued obtaining
federal grants for street lighting projects. We recently received
word from Caltrans, who administers these funds, that we have
competed successfully on two of three applications we submitted under the Hazard Elimination Safety
Program. They are:
• Cherokee Lane Arterial Lighting - Installing 73 additional lights between Pioneer Drive
and Almond Drive, $290,000 at 100% reimbursement.
• Various Arterial and Collector Streets - Installing 167 additional lights on various streets
per the attached list, $289,000 at 100% reimbursement.
We have a number of procedural hoops to go through before we can finally secure the funds, and we
will have to award contracts and be reimbursed afterwards. The biggest concern is that the Program is
over programmed by 25% and project plans and specifications will be approved on a first -come -first-
served basis. This may be a problem on the Cherokee Lane project if we wish to coordinate this project
with the revitalization study. We should discuss this with Michael Freedman in the near future.
This is the first time we can recall that the City has obtained these funds. Thanks and congratulations
should go to Electric Utility engineering and Public Works traffic engineering staff who put together the
applications in a very short time frame in order to meet the submittal deadline.
FUNDING: Hazard Elimination Safety Program.
eL.c
onsko
orks Director
JLRJrs
cc: Electric Utility Director
City Engineer
Traffic Engineer
Michael Freedman
APPROVES.---- �'-- - --� --- ---- ----- —
THOMAS A PETERSON eCy De
City Manager
CC
STUGMTF DOC 03119+
ARTERIAL AND COLLECTOR STREET LIGHTING (PROJECT B)
COST BREAKDOWN
Street Limits Class LUMINAIRE
100 watt 100 watt 250 watt 250 watt
on steel on wood on steel on wood
standard standard standard standard
Cost (ea.)
Lighting
Cost
Engineering/
Contingencies
Date: Sept 29,1993 '
Total Traffic Volume
avg vshktes per
Cost day
Kettleman
west city limit to Hwy 99
arterial
-
- - 15
$400
$6,000
$3,111
$9,111
20,250
Lodi
all
arterial
-
13 -
$2,000
$26,000
$2,794
$28,794
13,000
Ham
Turner to Kettleman
arterial
-
- 17 -
$2,000
$34,000
$3,653
$37,653
12,750
Victor
Cherokee to east city limits
arterial
- 3 -
$2,000
$6,000
$3,889
$9,889
12,500 tr
Lockeford
Hutchins to Cherokee
arterial
-
- 12 -
$2,000
$24,000
$2,579
$26.579
10.000
Lockeford
Hutchins to Cherokee
arterial
-
- 1
$400
$400
$34
$434
10,000
Hutchins
Lockeford to Kettleman
arterial
-
13 - -
$400
$5,200
$447
$5,647
9,000
Stockton
all
arterial
-
10 - -
$400
34,000
$344
$4,344
6,750
Elm
Lower Sac to Ham
arterial
-
- 10 -
$2,000
$20;000
$2,149
$22,149
5,750
Lockeford
Ham to Hutchins
collector
9
- - -
$2,000
$18,000
$4,634
$22,634
9,500
Church
Turner to Lockeford
collector
4
- - -
$2,000
$8,000
$638
$8,638
5,250
Lockeford
Mills to Ham
collector
3
- -
$2,000
$8,000
$478
$6,478
5,25Q
Lockeford
Mills to Ham
collector
-
8 -
$400
$3,200
$204
$3,404
5,250
Pine
Stockton to Guild
collector
-
2 - -
$400
$800
$165
$965
5,000
Central
Locust to Kettleman
collector
4
- - -
$2,000
$8,000
$638
$8,638
4,750
Tokay
all
collector
12
- - -
$2,000
$24,000
$1,913
$25,913
4,250
Elm
Ham to Cherokee
collector
4
- - -
$2,000
$8,000
$2,059
$10,059
3,500
Fairmont
Lodi to Kettleman
collector
4
- - -
$2,000
$8,000
$638
$8,638
3,500
Cluff
all
collector
4
- - -
$2,000
$8,000
$638
$8,638
3,000
Vine
all
collector
13
- - -
$2,000
$26,000
$2,072
$28,072
3,000
Mills
Lodi - south
collector
5
- - -
$2,000
$10,000
$2,060
$12,060
2,000
Mills
Lodi - south
collector
-
1 - -
$400
5400
02
$482
2,000
HES ART.XLS