HomeMy WebLinkAboutAgenda Report - May 18, 1994 (44)CIN OF LODI
COUNCIL COMMUNICATION
AGENDA TITLE: Acceptance of Improvements Under Traffic Signal and Lighting Installation.
Turner Road and Lower Sacramento Road/Woodhaven Lane
MEETING DATE: May 18, 1994
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "Traffic Signal
and Lighting Installation; Turner Road and Lower Sacramento Road/
Woodhaven Lane' contract and direct the Public Works Director to file a
Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Richard A. Heaps Electrical
Contractor. Inc. of Sacramento on August 18. 1993 in the amount
of $117,290.00. The contract has been completed in substantial
conformance with the plans and specifications approved by the
City Council.
The contract completion date was April 27, 1994, and the actual completion date was April 27, 1994.
The final contract price was $116,182.40. The difference between the contract amount and the final
contract price is mainly due to a deduct for patch paving repair work over the signal conduit trenches.
The City has issued a purchase order to Richard A. Heaps Electrical Contractor, Inc., for this paving
work which will be done this summer.
FUNDING: Originally Budgeted: 1992/93
Budgeted Fund: Street Development Impact Mitigation Fee (18%)
Intermodal Surface Transportation Efficiency Act (ISTEA) (82%)
Current Appropriation: $146,000.00
Total Project Estimate: $122,000.00
Bid Opening Date: July 21, 1993
x J
L. Ronsko
Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLRA*/Im
cc. Purchasing Officer
Street Superintendent
Public Works Inspector Murdock
APPROVED. �• ��
THOMAS A. PETERSON rKYc,ed PaM
city Manager
CC -1
�.«