AGENDA TITLE: Acceptor= of Improvements Under Lodi Jaid Painting and Plumbing Retrofit,
230 West Elm Street
MEETING DATE: February 2,1994
PREPARED BY. Public works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "Lodi Jail
Painting and Plumbing Retrofit. 230 West Elm Street contracd and
direct the Public Works Director to file a Notice of Completion with the
County Recorder's Office.
BACKGROUND INFORMATION: The contract was awarded to Charles J. Faszer, Inc., of Lodi, on
July 7,1993, in the amount of $42,693.40. The contract has been
completed in substantial conformance with the plans and
specifications approved by the City Council.
The contract completion date was January 12, 1994, and the actual completion date was
January 12, 1994. The final contract price was $47,241.30. The difference between the contract
amount and the final contract price is due to nine change orders totaling $4,547.90 as outlined below:
Change
Order No.
Description
Amount
1
Cell Block A - Paint Floors
$1,265.70
2
Janitor's Closet - Paint
293.08
3
Paint Gate 02 and Booking -Area Gate
733.33
4
Paint Doors and Jambs
616.61
5
Paint Booking Area
249.94
6
Paint Ceiling and Hallway Walls
372.50
7
Change Lavatory Shut-off Valves
153.23
8
Flush Valve
219.19
9
Additional Lavatory Faucet
644.32
Total $4.547.90
THOMAS A PETERSON ret,o.a pipe.
City Manapa
UL 1
011!4%1
Acceptance of ImprovemeMnder Lodi JaiPain" and Plumbin OMAR, 230 West On Street
FeW nary 2. 1994
Pape 2
FUNDING: OrIckwNy budgeted:
Budgeted Fund:
Cuffwd A�
Total Project Estimate:
Bid Opening Date:
.19901'81
10.0.351.01(331 and 334)
$47,000.00
$43,000.00
June 5,1993
Prepared by Deneb J. Callahan, Building and E*dpmad MWnbnanoa Superintendent
cc: Purchasing Officer
Police Chief
Poke Captain Schick
Building and Equipment Maintenance Superintendent
01/2"4
. V W
MEMORANDUM, City of Lodi, Public Works oeparht�nt
To: City Manager
City Council
From: Pubic Worcs Director
Date: February 10, 1994
Subject: Lodi Jail Painting and Plumbing Retrofit Project
At the last Council Meeting, February 2. 1994, the City Council accepted the
improvements under this project: however, questioned the change order for an
additional lavatory faucet in the amount of $644.32. Let me add that a $600.00 faucet
should be questioned.
Other Council Members, off the recL-d, questioned the number of change orders on
this project. Not knowing what the bit' was going to come in at, we were trying to keep
the initial contract to a minimum. However, this contract turned out very similar to a
kitchen remodel project where once you get into the project it was dear, in order to do
it right, additional items should be added. The final contract price was within $200.00
of the appropriated budgeted amount.
A breakdown of costs for the additional lavatory faucet is as follows:
Hot and cold vandal -resistant, push-button,
sell -dosing lavatory faucet (materials) S 339.00
Installation labor $ 150.00
Plumber's profit S 63.00
General contractors profit and insurance S 92.32
S 644.32
Attached is a copy of the catalogue showing the actual piece of equipment and retail
cost.
If you have any further questions concerning this item, please contact me or
Dennis Callahan at 3-8706.
4Li7o4n
ko
Director
JLRAM
•
Fowl Q
�fOpSOUTM �'tEAIMYt1El10MVE
CHICA10
FAUCETS m " w&"
Ja NAME
IIEMl� s - i
St>rMT1EDAS91A1Mi (�,�� � s** A .:.G l
ATMM FOR
t
V
1�nsM
DIA,
NOTE: TRANSFER
»ns~
VALVE Oft INTEGRAL
DIA.
SPOUT BY OTHERS
VALVE C -C
(AS REQUIRED)
I
I 1/2' NPT
SUPPLY (BY
OTHERS)
NOTE:
MIN. TO 5 ire" MIN. TO PET
REMOVE
BACK OF WALL
UNITS
LAVATORY AND
WALL THICKNESS
(AS REQUIRED)
Tmmm" DnU
!1"lW lm "MIK
fto
HOT AND COLD VANDAL RESISTANT PUSH BUTTON
SELF CLOSING LAVATORY FITTING FOR THROUGH THE WALL MOUNTING.
FOR LAVATORIES WITH INTEGRAL SPOUTS
137
EXPOSED PARTS CHROME PLATED FINISH
+ j