HomeMy WebLinkAboutAgenda Report - August 15, 2001 E-12COUNCILCITY OF LODI • •
IL 1
9<�FOR�
AGENDA TITLE: Accept Improvements Under Contract for Salas Park Playground Improvements,
2001 South Stockton Street, Hutchins Street Square, 600 West Oak Street,
Century Park Playground Improvements, Century Boulevard and Church Street
MEETING DATE: August 15, 2001
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the "Salas Park
Playground Improvements, 2001 South Stockton Street, Hutchins Street
Square, 600 West Oak Street, Century Park Playground Improvements,
Century Boulevard and Church Street" contract.
BACKGROUND INFORMATION: The project was awarded to A.M. Stephens Construction Company,
of Lodi, on March 21, 2001, in the amount of $150,889.00. The
contract has been completed in substantial conformance with the
plans and specifications approved by the City Council.
The contract completion date was August 9, 2001, and the actual completion date was June 1, 2001.
The final contract price was $162,746.60. The difference between the contract amount and the final
contract price is mainly due to the estimated quantities being less than the actual work done by the
contractor.
Following acceptance by the City Council, the City Engineer will file a Notice of Completion with the
County Recorder's office.
FUNDING: Budgeted Fund: 1998/99 Community Development Block Grant Funds $31,645.00
1999/00 Community Development Block Grant Funds $90,535.00
2000/01 Community Development Block Grant Funds $40,670.00
Contract Amount: $162,850.00
Richard C. Prima, Jr.
Public Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
RCPfWKF/Im
cc: Joel Harris, Purchasing Officer
Charlene Lange, Community Center Director
Steve Dutra, Parks Superintendent
Joseph Wood, Community Improvement Manager
Carrie Anderson, Community Development Block Grant Coordinator
APPROVED:
H. Dixon Flynn -- City Manager
C_accept 08/02/01