HomeMy WebLinkAboutAgenda Report - December 20, 1995 (73)y 0,
� � pQ
U /COUNCIL COMMUNICATIO
AGENDA TITLE: Acceptance of Improvements Under Refinish and Reline Two Portable
Basketball Floors Contract
MEETING DATE: December 20, 1995
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the 'Refinish
and Reline Two Portable Basketball Floors" contract, and direct the
City Engineer to file a Notice of Completion with the County Recorder's
office.
BACKGROUND INFORMATION: The contract was awarded to Boberg Hardwood Floors, of
Sacramento, on October 4, 1995, in the amount of $21,950. The
contract has been completed in substantial conformance with the
plans and specifications approved by the City Council.
There were minor problems with the finish coat but these were no fault of the contractor. These problems
are being corrected.
The contract completion date was December 1, 1995, and the actual completion date was
November 15, 1995. The final contract price was $21,950.
FUNDING: Originally Budgeted: 1994/95
Budgeted Fund: Capital Outlay Reserve Fund
Current Appropriation: $25,000
Total Project Estimate: $25,000
Bid Opening Date: September 20, 1995
4�dP,—
�
Jack L. Ronsko
Public Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLR/WKF/Im
cc: Purchasing Officer
Parks Supervisor McGeorge
APPROVED:
H. Dixoh Flynn --
CACCPT.DCC 12/13/95
AGENDA TITLE: Acceptance of Improvements Under Refinish and Reline Two Portable
Basketball Floors Contract
MEETING DATE: December 6, 1995
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the 'Refinish
and Reline Two Portable Basketball Floors" contract, and direct the
City Engineer to file a Notice of Completion with the County Recorder's
office.
BACKGROUND INFORMATION: The contract was awarded to Boberg Hardwood Floors, of
Sacramento, on October 4, 1995, in the amount of $21,950. The
contract has been completed in substantial conformance with the
plans and specifications approved by the City Council.
The contract completion date was December 1, 1995, and the actual completion date was
November 15, 1995. The final contract price was $21,950.
FUNDING: Originally Budgeted:
Budgeted Fund:
Current Appropriation:
Total Project Estimate:
Bid Opening Date:
1994/95
Capital Outlay Reserve Fund
$25,000
$25,000
September 20, 1995
�✓ r
(Jac L. Ronsko
ubli Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer
JLR/WKF/Im
cc: Purchasing Officer
Parks Supervisor McGeorge
APPROVED: - »'
H. Dixon Flynn -- City Mb ager
CACCPT.DOC 11/16/95
0 MEMORANDUM, City of Lodi, Public Works Department
To: City Manager
From: Public Works Director
Date: December 13, 1995
Subject: Refinishing and Relining of Two Portable Basketball Floors
In response to Council Member Davenport's December 6, 1995 memorandum (copy
attached), it is true that the City experienced peeling of the final finish coat on the two
portable basketball floors. However, the peeling was not the fault of the contractor and,
therefore, it is appropriate to recommend the filing of a Notice of Completion with the
County Recorder's office.
Attached is a memorandum dated December 12, 1995 from Senior Civil Engineer
Wes Fujitani explaining the problem we experienced with the finish coat. Under the
specifications, the contractor was to disassemble the floor panels after the finish coat
was cured. However, because of the Parks and Recreation Department's experience
and knowledge of disassembly, they offered to dismantle the portable floor. As part of
the disassembly, peeling of the final finish coat did take place. The contractor offered
to make the required repairs at no cost to the City, but due to the scheduled use of the
floors in the afternoons and evenings, the Parks and Recreation Department felt it
would be in the City's best interest for them to do the work and coordinate it with their
recreation schedule.
The Notice of Completion only certifies that the contractor has completed his work and that
the City accepts the work performed by the contractor. A sample Notice of Completion is
attached. It is appropriate for the Council to accept this project.
ri� - t
skos Director
JLRArn
attachments
cc: City Council
City Attorney
City Engineer
Parks and Recreation Director
BSKTBFLR.DOC
,` t
CITY COUNCIL H. DIXON FLYNN
STEPHEN). MANN, Mayor CITY O F I, O D I City Manager
DAVID P. WARNER JENNIFER M. PERRIN
Mayor Pro Tempore City Clerk
RAY G. DAVENPORT CITY HALL, 221 WEST PINE STREET
P.O. BOX 3006 JOHN W. STOVALL
PHILLIP A. PENNING Interim City Attorney
JACK A. SIEGLOCK LODI, CALIFORNIA 952A1-1910
(209) 333-6702
FAX (209) 333-6807 _
MEMORANDUM
TO: DIXON FLYNN, CITY MANAGER
FROM: RAY DAVENPORT, COUNCILMEMBER
DATE: DECEMBER 6, 1995
SUBJECT: REFINISHING OF TWO PORTABLE BASKETBALL FLOORS
This memo formalizes my complaint and concern in regard to the Public Works
Director's council communication on the above subject as presented in the December 6,
1995 council communication packet.
Mr. Ronsko suggests we accept the improvements and file a Notice of Completion
with the County Recorder's office in regard to the aforementioned contract.
I have been informed by extrinsic sources that in fact some areas of the floors
finish is peeling.
Upon inspection of the floors, the peeling may be related to the procedure and
method of moving the portable panels.
I do not support the filing of false statements by department heads. Additionally it
is unacceptable for a department head to attempt to cover up the true condition of a
project and fail to report conditions as they presently exist.
I trust this problem will not occur in the future.
cc: City Councilmembers
City Attorney
0 MEMORANDUM, City of Lodi, Public Works Department
To: Public Works Director
From: Senior Civil Engineer
Date: December 12, 1995
Subject: Resurfacing and Relining of Two Portable Basketball Floors
I spoke to Tim McGeorge, Parks Supervisor, and Steve Virrey, Parks Project Coordinator, about
the peeling of the finish coat on the basketball floors that were recently relined and refinished by
Boberg Hardwood Floors. Both Tim and Steve felt that the peeling is a minor problem and that
the repair work can be done by the Parks Department crew with minimal time and effort.
The Parks Department had assembled both basketball floors and the City awarded Boberg
Hardwood Floors a contract to sand the floors down to bare wood, seal and stripe the floors and
apply a finish coat. After the finish coat was applied, the floors were to be disassembled so that
the panels would not stick together. The peeling is occurring on the edges of the panels. Tim
and Steve felt that the peeling is the result of the finish coat curing before the Parks crew
disassembled the floor panels. The Parks crew did the disassembly of the floors because they
were more familiar with the process and because they had more manpower so they could do the
work quicker. During the application of the finish coat, Mike Boberg, the contractor, estimated
that the coat would cure in about three hours. Tim and his crew checked the finish and began to
break the panels as soon as the coat was not tacky (after approximately two hours). The finish
coat just set up faster than anticipated. This same process was used on the second floor and
there is some peeling but not as much as on the first floor.
As soon as the peeling was discovered, Mike Boberg was called so that he_ could inspect the
peeling. He offered to do all the repairs but the Parks Department felt it would be easier to have
it done with the Parks crew. The repairs must be done in the morning because Tokay High is
using the floors in the afternoon and the adult basketball program is using the floors in the
evenings. Coordinating the repair work with Boberg Hardwood Floors would have been more
difficult for the Parks crew than doing the work themselves. Mr. Boberg gave the City all the
repair material and showed the Parks crew how to do the repair work. There is some bubbling in
the first patch but the patch work has been blending with the finish coat much better as the crew
has gained experience. According to Tim McGeorge, each patch is done in two to three minutes.
Tim also said that as they are making the repairs, they are finding fewer and fewer edges that
are peeling.
\4
Wes Fujitani
Senior Civil Engineer
mi
ca Parks Superintendent
PWD MEMOAOC
When recorded, mail to:
Public Works Director
City of Lodi
P. O. Box 3006
Lodi, CA 95241-1910
QJTN e..#
rN k M�
NOTICE OF COMPLETION
NOTICE IS HEREBY GIVEN THAT:
On Wednesday, December 6, 1995, the City Council of the City of Lodi accepted
completion of the work of improvements known as "Sacramento Street - Street
Reconstruction, Park Street to Vine Street".
The work of improvement consisted of reconstructing approximately 41,800 square feet
of asphalt concrete pavement with 1,500 tons of asphalt concrete, installing 4,640
square yards of engineering fabric, installing 2 wheelchair ramps, and other incidental
and related work as shown on the plans and specifications for this project.
The contractor is A. M. Stephens Construction Co., Inc., P. O. Box 1867, Lodi,
California, 95241.
The surety is American Casualty Company of Reading, Pennsylvania, G. Scott Gaddy,
Attomey-in-Fact, 2180 Harvard Street, Suite 240, Sacramento, California, 95815.
CITY OF LODI
By:
Richard C. ?Prima,
City Engineer
That I am the City Engineer of the City of Lodi, the municipal corporation that executed
the foregoing notice as owner of the aforesaid interest or estate in the property therein
described; that I make this verification on behalf of said municipal corporation; that I
have read this notice and know the contents thereof, and that the facts therein stated
are true.
I declare under penalty of perjury that the foregoing is true and correct.
Dated at Lodi, California, this 7th day of December, 1995.
L
Richard C. Prim .
City Engineer