HomeMy WebLinkAboutAgenda Report - May 17, 1995 (43),� OF
CITY OF LODI
COUNCIL COMMUNICATION
AGENDA TITLE: Acceptance of Improvements Under Municipal Service Center Electric Utility
Building Modification/Expansion Contract
MEETING DATE: May 17, 1995
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council accept the improvements under the
"Municipal Service Center Electric Utility Building
Modification/Expansion" contract and direct the City Engineer to file
a Notice of Completion with the County Recorder's office.
BACKGROUND INFORMATION: The contract was awarded to Wall Construction of Modesto on
September 15, 1994, in the amount of $221,000. The contract has
been completed in substantial conformance with the plans and
specifications approved by the City Council.
The contract completion date was April 4, 1995, and the actual completion dated was April 7, 1995.
The final contract price was $248,165. The difference between the contract amount and the final
contract price is mainly due to seventeen change orders totaling $27,165. A list of these change orders
is attached.
FUNDING: Originally Budgeted:
Budgeted Fund:
Current Appropriation:
Total Project Estimate:
Bid Opening Date:
1993/94
Electric Utility Capital Fund
$232,000
$232,000
September 7, 1994
JackL Ronsko
blic orks Director
Prepared by Dennis J. Callahan, Building and Equipment Maintenance Superintendent
91Ri:71N11N1Gi1
Attachment
cc: Purchasing Officer
Acting Electric Utility Director
Building and Equipment Maintenance Superintendent
Wenell Mattheis Bowe
APPROVED:
1 THOMAS A. PETERSON recycled paper
City Manager
CACCEPT.DOC 135/10/95C 1
MSC ELECTRIC UTILITY
MODIFICATION/EXPANSION
WALL CONSTRUCTION
CHANGE ORDER RECAP
April 25, 1995
CO #
DESCRIPTION
AMOUNT
TOTAL
CONTRACT
$ 221,000
1
New concrete slab @ driveway.
$
220
$
221,220
2
Misc. door, frame, hardware, switch, dispenser, VCT
tile, vinyl wall covering,
$
570
$
221,790
3
First course of CMT from (E) grade.
$
550
$
222,340
4
Restroom: electric outlet; replace tile; new mirror.
$
550
$
222,890
5
New concrete landing on south side of building.
$
150
$
223,040
6
Install 2 1" underground plastic gas lines.
$
2,250
$
225,290
7
Remove existing roofing.
$
7,500
$
232,790
8
Add window in south wall, Room #105
$
1,200
$
233,990
9
Eliminate door & frame #8; add sink @ storage room
N/C
$
233,990
10
Install electric sub -panel.
$
1,500
$
235,490
11
Provide 2 new instant water heaters.
$
1,200
$
236,690
12
Provide lockers.
$
310
$
237,000
13
Epoxy paint shop hallway floor.
void
$
237,000
14
Supply & install correct locksets.
$
2,500
$
239,500
15
Misc: light fixtures, suspended ceiling; HVAC registers;
trim at window; paint masonry walls
$
5,000
$
244,500
16
Misc Engineering Office changes, painting, concrete
demo, downspout drain, roof sheathing, trim
$
2,285
$
246,785
17 Misc. Infill, Paint, Insulation, Repair
TOTAL CHANGE ORDERS TO DATE
$
$
1,380
27,165
$
248,165