AGENDA TITLE: City Council Goals
MEETING DATE: May 3, 1995
PREPARED BY: Finance Director
RECOMMENDATION: Accept the list of attached goals and goal summaries for information and
provide staff with final direction before budget hearings to be held in
June.
BACKGROUND
On February 21 the City Council met with Department Heads to identify possible City goals for the
1995-97 Financial Plan and Budget. These goals were listed, staff summaries were prepared and the
goals were reviewed and ranked by staff and Council between February 21 and May 3. From an initial
list of 34 goals, a final list of ten goals and goal summaries has been prepared and is presented tonight
for City Council comment and direction to staff.
The City Council goals have been developed to involve the City Council as early as possible in the
budget process by identifying the goals and priorities which the City Council believes will produce the
greatest benefit to the City. As such, these goals will become the focus of staff efforts and resources.
In addition, by identifying the most significant City goals, the City Council is assured that the most
important, highest priority goals are accomplished and that adequate resources are appropriated to
ensure their accomplishment.
The identification of major City goals and the early involvement of the City Council in budget
development is a new experience for the City Council and staff. However, government and business has
been successfully using this management technique for several years at all levels of their organizations.
By setting long term goals and objectives, the City Council can proactively set the direction of the City,
can reinforce their responsibility for establishing City policy and can measure their accomplishments.
Staff Summaries
Each goal identified by the City Council has been summarized by staff using the following format:
Objective
Background and Workscope
Action Steps
Responsible Department and Activity
Financial and Staff Resources Allocated
Outcome and Final Product
APPROVED:
THOMAS A. PETERSON recycled paper
City Manager
cc -1
The goal summaries were prepared to ensure that the staff and Council had a clear understanding of
what is to be accomplished, what resources are required, who is responsible, how the objective is to be
measured and when the objectives are to be accomplished. As a summary, the goals are a broad
statement to give direction. Over time, they will be refined and adjusted based on further study and
analysis.
Review Process
From the initial list of 34 goals arranged in a random order (Exhibit A), the goals were reviewed by staff
and ranked. A second list was published in the order based of the staff's ranking (Exhibit B). This list
was again reviewed along with the goal summaries and was reduced to 16 goals. The other 18 goals
were eliminated for the following reasons:
• Will be included as a Department objective in the 1995-97 Financial Plan and Budget
Multi -Model Station
Completion of Lodi Lake Master Plan
Update of the General Plan
Needs Assessment for Parks and Recreation
Information Bulletin Board
Financing Library Services
Enhanced Library Services
Charter City
• Additional information required
Fire Department Response Plan
Fleet Vehicle Replacement
Enhanced Park Facilities
• Completed in the 1994-95 Budget Year
Funding of the Boys & Girls Club
City/School - Joint Use Agreement
• To be considered at a later date
Financial Planning and Budget
Purchase of the City Hall Annex
• Included in other objectives
Hotel Lodi
Financial Condition of the Electric Utility
Deferred Maintenance - Street Trees
Final Review
The list of 16 goals and staff summaries were distributed to the City Council for ranking and returned
on or before April 14. A new list was prepared in the order of the City Council's ranking (Exhibit C)
and further reviewed by staff for presentation to the City Council on May 3. These goals were either
left in their original form or consolidated with other goals to arrive at a final list of 10 goals and goal
summaries (Exhibit D) as listed below:
Consolidated Goals .
The consolidation of the 16 goals and summaries as listed above reflect the City Council's priorities and
where they have been consolidated appear to be a rational and logical consolidation. Unless directed
otherwise by the City Council, these goals will be listed as the Major City Goals in the 1995-97
Financial Plan and Budget. The Goal Summaries will also be included. Accordingly, the funding for
these goals will be included in the appropriate activity or capital budget.
Dixon Flynn
Finance Director
Attachment
Initial List of City Council Goals (Exhibit A)
City Council Goals as Ranked By Staff (Exhibit B)
City Council Worksheet (16 Goals) (Exhibit C)
Final List of Goals and Summaries (Exhibit D)
Goals
Cost
1.
Economic Revitalization
$200,000 per Year O&M
Central City Revitalization
$5.5 million CIP
Cherokee Lane Beautification
Business Growth
2.
Street Crimes Unit
$320,000 per Year O&M
3.
California Youth Soccer Association
Revenue/Cost Neutral
4.
Electric Utility Service Improvements
Cost Containment
Deregulation of the Electric Utility
Utility User's Tax
5.
Residential Neighborhood Improvements
$75,000 per year O&M
Eastside Neighborhood Revitalization
Code Enforcement
6.
Conferencing/Performing Arts Center
$9.5 million CIP
7.
Water Utility Service Improvements
Revenue/Cost Neutral
8.
Indoor Sports Facility
$4.0 to $6.0 million CIP
9.
Compensation Policy Development
Cost Containment
Employee Benefits/Cafeteria Plan
Performance Pay
10.
Contracting Services
Cost Containment
Street Tree Services
Transit Services
Consolidated Goals .
The consolidation of the 16 goals and summaries as listed above reflect the City Council's priorities and
where they have been consolidated appear to be a rational and logical consolidation. Unless directed
otherwise by the City Council, these goals will be listed as the Major City Goals in the 1995-97
Financial Plan and Budget. The Goal Summaries will also be included. Accordingly, the funding for
these goals will be included in the appropriate activity or capital budget.
Dixon Flynn
Finance Director
Attachment
Initial List of City Council Goals (Exhibit A)
City Council Goals as Ranked By Staff (Exhibit B)
City Council Worksheet (16 Goals) (Exhibit C)
Final List of Goals and Summaries (Exhibit D)
City of Lodi Exhibit A
INITIAL LIST OF CITY COUNCIL GOALS
** Department Recommended
Goal
Department
1
Code Enforcement
Administration
2
City/School Facilities - Joint Use Agreement
Administration
3
Contracting Transit Services
Administration
4
Multi -Model Station- CIP Project
Administration
5
Purchase of City Hall Annex - CIP
City Attorney
6
California Youth Soccer Association Agreement
City Attorney
7
Charter City
City Attorney
8
Performing Art Center - CIP Project
Community Center
9
Boys & Girls Club - CIP Project
Community Development
10
Update General Plan
Community Development
11
Hotel Lodi
Community Development
12
Central City Revitalization
Economic Development
13
Cherokee Lane Beautification -CIP
Economic Development
14
East Side Neighborhood Revitalization
Economic Development
15
Business Growth
Economic Development
16
Electric Utility- Financial Condition
Electric Department
17
Deregulation of Electric Utility
Electric Department
18
Utility Users Tax - Revenue Neutral
Finance
19
Fire Department Response Plan
Fire Department
20
Information Bulleting Board
Information Systems
21
Enhanced Library Services
Library Department
22
Financing Library Services
Library Department
23
Indoor Sports Facility - CIP
Parks & Recreation
24
Enhanced Park Facilities -CIP
Parks & Recreation
25
Performance Pay
Personnel Department
26
Employee Benefits/Cafeteria Plan
Personnel Department
27
Street Crimes Unit
Police Department
28
Water Supply Plan
Public Works
29
Deferred Maintenance - Streets/Trees - CIP
Public Works
30
Contracting for Street Tree Services
Public Works
31
Financial Planning and Budget * *
Finance
32
Completion of Lodi Lake Master Plan **
Parks and Recreation
33
Maintenance & Operation Needs Assessment Study **
Parks and Recreation
34
Fleet Vehicle Replacement **
Fire
** Department Recommended
City of Lodi Exhibit B
CITY COUNCIL GOALS AS RANKED BY STAFF
Goal
Department
Points
1 Central City Revitalization
Economic Development
22
2 Business Growth
Economic Development
22
3 Street Crimes Unit
Police Department
21
4 Cherokee Lane Beautification -CIP
Economic Development
21
5 Utility Users Tax - Revenue Neutral
Finance
20
6 Multi -Model Station- CIP Project
Administration
20
7 East Side Neighborhood Revitalization
Economic Development
20
8 Code Enforcement
Administration
20
9 Deregulation of Electric Utility
Electric Department
18
10 Completion of Lodi Lake Master Plan **
Parks and Recreation
18
11 California Youth Soccer Association Agreement
City Attorney
18
12 Boys & Girls Club - CIP Project
Community Development
18
13 Water Supply Plan
Public Works
17
14 Update General Plan
Community Development
16
15 Performing Art Center - CIP Project
Community Center
16
16 Enhanced Park Facilities -CIP
Parks & Recreation
15
17 Electric Utility- Financial Condition
Electric Department
15
18 Contracting Transit Services
Administration
15
19 Maintenance & Operation Needs Assessment Study **
Parks and Recreation
14
20 Fire Department Response Plan
Fire Department
14
21 Employee Benefits/Cafeteria Plan
Personnel Department
14
22 Charter City
City Attorney
14
23 Purchase of City Hall Annex - CIP
City Attorney
13
24 Performance Pay
Personnel Department
13
25 Indoor Sports Facility - CIP
Parks & Recreation
13
26 Hotel Lodi
Community Development
13
27 Financial Planning and Budget **
Finance
13
28 Contracting for Street Tree Services
Public Works
13
29 City/School Facilities - Joint Use Agreement
Administration
13
30 Information Bulleting Board
Information Systems
12
31 Fleet Vehicle Replacement **
Fire
12
32 Financing Library Services
Library Department
12
33 Deferred Maintenance - Streets/Trees - CIP
Public Works
11
34 Enhanced Library Services
Library Department
10
City of Lodi Exhibit C
CITY COUNCIL WORKSHEET
Goal
Staff
Council
No
Goal
Department
Rank
Mayor
Points
12
1 Central City Revitalization
Economic Development
1
* *
15
27
2 Street Crimes Unit
Police Department
4
* *
13
13
3 Cherokee Lane Beautification -CIP
Economic Development
2
* *
12
15
4 Business Growth
Economic Development
3
**
11
6
5 California Youth Soccer Association Agreement
City Attorney
9
* *
11
17
6 Deregulation of Electric Utility
Electric Department
10
11
1
7 Code Enforcement
Administration
5
**
10
14
8 East Side Neighborhood Revitalization
Economic Development
6
**
10
8
9 Performing Art Center - CIP Project
Community Center
15
10
28
10 Water Supply Plan
Public Works
11
10
23
11 Indoor Sports Facility - CIP
Parks & Recreation
29
9
18
12 Utility Users Tax - Revenue Neutral
Finance
7
8
26
13 Employee Benefits/Cafeteria Plan
Personnel Department
26
7
25
14 Performance Pay
Personnel Department
28
7
30
15 Contracting for Street Tree Services
Public Works
27
6
3
16 Contracting Transit Services
Administration
19
5
City of Lodi Exhibit D
FINAL LIST OF CITY COUNCIL GOALS
Goal
Estimated
No
Goal
Department
Cost
1
Economic Revitalization
Administration/Public Works/
$200,000 per year O&M
Central City Revitalization
Community Development
$5.0 million CIP
Cherokee Lane Beautification
Business Growth
2
Street Crimes Unit
Police Department
$320,000 per year O&M
3
California Youth Soccer Association
Administration/City Attorney/
Revenue/Cost Neutral
Public Works
4
Electric Utility Service Improvements
Electric Department
Cost containment
Deregulation of the Electric Utility
Utility User's Tax
5
Residential Neighborhood Improvements
Community Development/
$75,000 per year O&M
Code Enforcement
Administration
Eastside Neighborhood Improvements
6
Conferencing/Performing Arts Center
Administration/Public Works
$9.5 million CIP
7
Water Utility Service Improvements
Public Works
Revenue/Cost Neutral
8
Indoor Sports Facility
Parks and Recreation/
$4.0 to $6.0 million CIP
Public Works
9
Compensation Policy Development
Administration/
Cost containment
Employee Benefits/Cafeteria Plan
Personnel Department
Performance Pay
10
Contracting Services
Administration/Other
Cost containment
Contracting Street Tree Services
Contracting Transit Services
of Lodi
MAJOR CITY GOAL - Economic Revitalization
OBJECTIVE
Implement the economic revitalization plan approved by the City Council in December 1994 to
accomplish the following objectives:
• Preserve, enhance and promote the financial stability of the downtown.
• Provide an attractive entryway on Cherokee Lane and build a base for further improvements.
• Promote and preserve economic stability to attract and retain business.
• Improve residential conditions overall and focus improvements in the Eastside
Neighborhoods.
BACKGROUND AND WORKSCOPE
Central City Revitalization Element
This element of the Revitalization Program was approved by the City Council to focus additional City
effort and resources on improving the local economy by enhancing community pride in the downtown
and promoting the downtown as the historic, pedestrian and socializing center of the City. To
accomplish this goal the City Council adopted 6 objectives:
1. Promote downtown specialty retail, restaurant, entertainment and cultural uses.
2. Enhance the visual character and identity of the downtown.
3. Focus public investment to create an attractive pedestrian environment.
4. Tap the potential of the transit station and adjacent Southern Pacific lands to stimulate
private investment.
5. Establish incentives to encourage reinvestment in existing buildings and businesses.
6. Initiate a downtown directional and entrance sign program.
The precise work scope is currently being developed on an objective by objective basis. Examples of
projects and programs which could eventually be funded through this program include, streetscape
improvements on downtown streets, a gateway on School Street at the Lodi Avenue intersection,
directional signs to the downtown, added police patrol services in the downtown, relocation of the
homeless shelter, financial assistance for relocating business to the downtown, building improvements
and activities to attract pedestrian traffic.
City of Lodi
MAJOR CITY GOAL - Economic Revitalization
Cherokee Lane Beautification Element
Cherokee Lane parallels Highway 99 and is the preferred route for north -south intercity travel in the
Central Valley. Before the Highway 99 bypass was built, Cherokee Lane was Highway 99 with a mix of
businesses which catered to highway traffic. Over time however, Kettleman Lane became the preferred
location for commercial development and disinvestment along Cherokee Lane became a problem. To
improve Cherokee Lane the City Council adopted three objectives:
I. Improve streetscape and lighting conditions.
2. Establish development standards and guidelines that improve the appearance of buildings
and businesses.
Encourage and accommodate lodging, auto and support businesses.
Business Growth
The City Council adopted a list of goals to promote economic development in both the targeted
business districts and for city-wide development to promote business and job growth. This goal
provides the long term direction to staff and a commitment by the City Council to promote business
growth and retention. To ensure that adequate resources are focused on this goal, the City established a
position for an economic development coordinator to lead the effort. The economic development goals
approved by the City Council in April 1994 include:
1. Recruit new business which will be compatible with and complimentary to the
community.
2. Retain existing businesses.
3. Expand existing business.
4. Create an atmosphere beneficial to conducting business.
5. Provide and maintain a tax environment favorable to business development and
expansion.
6. Provide financial assistance to business ventures which will make a significant
contribution to the City by increasing or retaining jobs and/or by adding capital
investment.
7. Coordinate the downtown revitalization project.
8. Coordinate the Cherokee Lane Improvement project.
9. Market Lodi as a tourist and business location.
Some objective to be developed to support of these goals include land use policy revisions, formation of
a redevelopment agency to finance reconstruction of buildings in blighted areas, the formation of a Lodi
Conference and Visitors Bureau and revitalization of downtown and Cherokee Lane.
City of Lodi
MAJOR CITY GOAL - Economic Revitalization
ACTION STEPS
Specific action steps will be established as projects and programs are defined.
RESPONSIBLE DEPARTMENT
Administration
Others (depending on the project and/or program)
FINANCIAL AND STAFF RESOURCES ALLOCATED
The City has allocated $176,000 per year in 1995-96 and 1996-97 for economic development plus
$200,000 per year for specific projects and programs in the capital improvement budget. The need for
additional staff is not anticipated; however, consultant services will be required to complete projects
currently identified. Additional resources could be needed if the Council develops a more aggressive
program.
OUTCOMEXINAL PRODUCT
To be determined on a project by project, program by program basis.
7
City of Lodi
MAJOR CITY GOAL - Street Crimes Unit
OBJECTIVE
Field a Street Crimes Unit to focus Police resources on high crime neighborhoods and deter criminal
activities.
BACKGROUND AND WORKSCOPE
Overall crime in Lodi has declined in the last year. However, criminal activity in certain neighborhoods
and areas of the City exist at unacceptable levels. The continued efforts by the City to remove criminals
from the streets and neighborhoods is and will remain a top priority. Recognizing the fiscal constraints
which the City faces, the Police Department believes a Street Crimes Unit concept provides the Police
Department with the necessary resources to concentrate police personnel in specific problem areas to
free patrol officers to respond to general service calls.
ACTION STEPS
• Recruit and hire 3 new police officers
08/95
• Train new officers
10/95
• Select members for the Street Crimes Unity and promote a Sergeant
10/95
• Street Crimes Unit becomes operational
11/95
• Recruit and hire 2 new police officers
08/96
• Train new officers
10/96
RESPONSIBLE DEPARTMENT
Police
FINANCIAL AND STAFF RESOURCES ALLOCATED
The operating budget of the Police Department will be increased $200,000 in 1995-96 and $120,000 in
1996-97. An additional $35,000 will be provided in the Capital Budget for the purchase of two patrol
vehicles. Three additional officers and one sergeant will be added to the authorized staffing level in
1995-96 and two additional officers will be added to the authorized staffing level in 1996-97.
OUTCOMEXINAL PRODUCT
Cost effective police services focused on specifically identified problem/crime areas.
of Lodi
MAJOR CITY GOAL - California Youth Soccer Association
OBJECTIVE
Execute a long term lease with the California Youth Soccer Association (CYSA) for 275 acres at the
White Slough Water Pollution Control Facility for use as a regional soccer complex.
BACKGROUND AND WORKSCOPE
The City is presently negotiating with CYSA for the lease of 275 acres at the White Slough Water
Pollution Control Facility. The Association proposes to build a fifty field regional soccer complex
which will attract soccer tournaments from around Northern California and the Western States. It is
likely that the rents received and the secondary economic impact on the City from such tournaments
would greatly exceed the City's present income from leasing the property for agricultural uses.
A draft lease has been prepared and forwarded to the Association. The firm hired to prepare the
required environmental impact report is already on site, and is moving forward. The Association has
also retained an engineering firm to help design the tertiary water treatment facilities which will be
required to use treated wastewater for irrigating the soccer fields.
ACTION STEPS
• Final draft of lease 5/95
• Environmental impact report completion/circulation/certification 7/95
• Final design of facilities (odor control/tertiary treatment) 8/95
• Construction of improvement begins 9/95
RESPONSIBLE DEPARTMENT AND ACTIVITY
Public Works, City Attorney
FINANCIAL AND STAFF RESOURCES ALLOCATED TO ACHIEVE THE GOAL
Staff hours of responsible departments until completion of the project.
OUTCOME/FINAL PRODUCT
Long term lease between the City and CYSA for property at White Slough, with both rental income and
secondary economic impacts on the City from tourism and retail sales.
of Lodi
MAJOR CITY GOAL - Electric Utility Service Improvements
OBJECTIVE
To develop a short and long term strategic plan to improve the competitive position of the City's
electric utility service in order to provide competitive rates and to maintain the financial health of the
City's electric utility fund.
BACKGROUND AND WORKSCOPE
The electric utility industry is moving toward a competitive open market due to recent legislative and
regulatory agency initiatives. Under the initial guidelines from the Public Utilities Commission, large
industrial customers will be allowed to purchase power on the open market beginning January 1, 1996.
For Lodi, this could result in the loss of customers such as General Mills, Pacific Coast Producers, RM
Holz, etc. which as a group purchase more than 12% of the City available power. If this is allowed to
occur, the cost of providing electric services to residential customers would have to be significantly
increased to pay for the power the City is obligated to purchase.
To prevent this, the City will have to develop a marketing plan to retain major power customers and to
cut the cost of electric services to ensure competitive residential rates.
In addition to the market pressure from deregulation, the City has a significant investment in several
ventures with Northern California Power Agency cities (NCPA) for power generation facilities and to
purchase power. These investments have been made over several years with the objective of making
NCPA cities and Lodi independent of PG&E and other power suppliers. The City's share of debt under
these agreements is approximately $141 million and must be paid for in either power purchases from
NCPA or debt service payments.
In developing its independence, the City of Lodi has invested in a number of power plants and purchase
power agreements. This includes a geothermal plant, a hydroelectric plant, a cogeneration plant, a
steam turbine injection generator, open market purchases and power swapping agreements. With the
addition of the steam turbine injection generator in June 1995, the cost of power will increase
approximately $6.0 million per year which must be passed on to the rate payer or sold to other users.
Without deregulation, the City is faced with the need to cut costs, raise rates or find buyers for its
excess power. With deregulation, the City must cut operating costs and protect itself from having
stranded investments. To ensure that the residents of Lodi are provided safe, reliable and cost effective
electric utility services, the City must develop a strategic plan to address these issues in the near future.
/"r,
City of Lodi
MAJOR CITY GOAL - Electric Utility Service Improvements
Possible actions include:
• Refinancing outstanding debt with NCPA
• Reducing operating and personnel costs
• Implementing a utility user's tax
• Contracting electric utility services in part or whole
• Reducing the transfer to the General Fund whether as an In -Lieu Franchise Tax or Utility
User's Tax
• Sell in part or whole the City's ownership in power generation facilities
• Sell in part or whole the City's electric utility service
ACTION STEPS
The action steps to be followed in developing a long term strategic plan for the electric utility include:
• Conduct a preliminary fact finding review of the current financial
status and internal controls of the electric utility fund.
05/95
• Adopt a preliminary electric utility budget during budget hearings
in June 1995
06/95
• Contract with the City's audit firm to conduct an in-depth financial
and operations audit of the electric utility fund and internal controls.
06/95
• Adopt final 1995-97 Financial Plan and Budget for the Electric Fund
10/95
• Complete a ten year financial plan based on the goal to provide
City customers with competitive electric rates and reliable service.
02/96
• Complete a marketing strategy to sell surplus electric power
02/96
RESPONSIBLE DEPARTMENT AND ACTIVITY
Electric Department, Finance Department, Administration and NCPA
FINANCIAL AND STAFF RESOURCES ALLOCATED TO ACHIEVE GOAL
Staff hours and $50,000 of contract services for audit and consultant services
OUTCOME AND FINAL PRODUCT
Reliable and cost effective electric utility services provided to residential, commercial and industrial
customers at competitive rates.
City of Lodi
MAJOR CITY GOAL - Residential Neighborhood Improvements
OBJECTIVE
Develop and implement a residential neighborhood improvement program to eliminate blight and to
ensure that all neighborhoods are maintained at standards consistent with community values.
BACKGROUND AND WORKSCOPE
The City of Lodi is committed to maintaining neighborhood residential standards at a level in which
every resident can be proud of their neighborhood and which reflects the high standards of the
community. To this end the City Council has developed an action plan to revitalize the Eastside
residential area which will be used to achieve the City's economic development objectives and which
can be used to protect all neighborhoods within the City from blight.
Over time, the City has witnessed the deterioration of the Eastside Neighborhood which is bounded on
the west by Church Street and on the east by Cherokee Lane. The cause for this deterioration has been
identified to the following trends:
• A decrease in the number of residents who own the housing in which they reside.
• An increase in the number of transient, low income residents who have no stake in the
quality of their neighborhoods.
• An increase in the number of high density, multi -unit residential buildings with inadequate
neighborhood services and infrastructure.
• A crime rate higher than the rate found in other residential neighborhoods.
The City of Lodi has traditionally focused on providing high quality services and infrastructure for its
residents. It has also avoided interfering in the affairs of private property owners. However, the
residents of Lodi expect all property owners to maintain their property at a level consistent with the
values of their neighbors and to ensure their neighborhoods remain safe and clean.
ACTION STEPS
The following action steps have been identified:
• Expand code enforcement efforts to eliminate blight and unsafe
neighborhood conditions.
• Develop programs to encourage home ownership and property renovation.
• Reconfigure commercial and multi -unit residential zoning designations.
• Upgrade multi -unit residential development standards.
• Work with neighborhood and community organizations to promote
neighborhood services and programs.
RESPONSIBLE DEPARTMENT
Administration and Community Development
07/95
06/96
06/96
06/96
On-going
City of Lodi
MAJOR CITY GOAL - Residential Neighborhood Improvements
FINANCIAL AND STAFF RESOURCES ALLOCATED
Current staff hours and add part-time hours ($16,000 per year) and an additional code enforcement
officer ($45,000 per year). Add contract services to develop zoning regulations ($20,000),
OUTCOME/FINAL PRODUCT
Safe, clean neighborhoods which reflect the standards of the community and pride in ownership.
City of Lodi
MAJOR CITY GOAL - Conferencing/Performing Art Center
OBJECTIVE
To construct an 800 seat conferencing/performing arts center in Lodi to:
• Promote local and regional interest in the performing arts through the production of plays,
recitals and concerts.
• Provide conference facilities for the greater Lodi area to benefit commercial activities such
as restaurants, hotels/motels, specialty stores and other services.
• Enhance the quality of life in Lodi to increase the desirability of the City as a community to
maintain and establish a business and to live and raise a family.
BACKGROUND AND WORKSCOPE
For nearly two decades, Lodi residents have promoted the idea that Lodi would benefit from a
conference/performing arts center. To achieve their goal, the Old Lodi Union High School Site
Foundation was formed to act as a catalyst to raise funds for the reconstruction of the downtown
abandoned high school. Over five million dollars has been raised to date to plan the site and finance the
capital improvements. The remaining work includes the renovation of the auditorium which can be
restored as an 800 seat capacity facility.
To complete this facility, a partnership between the City and the Foundation will continue to define the
scope of the project, evaluate the demand for a conference/performing arts center, develop use
agreements with the Lodi Arts Commission and the Lodi Unified School District, establish management
policies and develop a financing plan for construction and operating costs.
ACTION STEPS
The following action steps have been identified:
• Establish a steering committee with representatives from the
Foundation and Arts Commission.
06/95
• Sign contracts for working drawings
08/95
• Develop joint use agreement
10/95
• Prepare management plan for project development
12/95
• Prepare operating plan
12/95
• Approve working drawings
02/96
• Construction of facility
07/96
RESPONSIBLE DEPARTMENT
Administration, Community Center and Public Works
/-Y
City of Lodi
MAJOR CITY GOAL - Conferencing/Performing Art Center
FINANCIAL AND STAFF RESOURCES ALLOCATED
Approximately 400 staff hours and $9.5 million of capital funds
OUTCOME/FINAL PRODUCT
A conference/performing arts center for the residents of Lodi
City of Lodi
MAJOR CITY GOAL - Water Utility Service Improvements
OBJECTIVE
Ensure a safe, reliable and cost efficient water supply system
BACKGROUND AND WORKSCOPE
The City's water system currently has 25 developed wells. Due to DBCP and the TCE contamination
standards set by the State and the Environmental Protection Agency, together with bacteria, taste and
odor problems, 7 wells do not meet the current drinking water standards. Additionally, Well 9 has an
ongoing bacteria problem that causes a distribution system bacteria problem. To meet demand levels
anticipated for the summer of 1995, the City must install granular activated carbon (GAC) filters on at
least three wells and install a million gallon water tank located at the Fred Reid Substation. This will
increase the number of wells available to meet on-going and peak demands.
ACTION STEPS
The following action steps are necessary:
• Approval of a rate increase to service debt financing. 04/95
• Appropriate $75,000 for disinfection equipment at Well 9. 05/95
• Obtain bids for GAC at Wells 22 and 23 05/95
• Prepare plans and specifications for a water tank 05/95
RESPONSIBLE DEPARTMENT AND ACTIVITY
Public Works Department
FINANCIAL AND STAFF RESOURCES ALLOCATED TO ACHIEVE GOAL
Staff hours and $3.0 million in the Water Capital Budget.
OUTCOME/FINAL PRODUCT
Safe, reliable cost effective water services
14
City of Lodi
MAJOR CITY GOAL - Indoor Sports Facility
OBJECTIVE
Develop a plan to provide an indoor/sports facility for the residents of Lodi for indoor recreation
activities
BACKGROUND AND WORKSCOPE
The City has depended on the Lodi Unified School District, the Grape Festival and private property
owners to provide indoor space for indoor recreation activities. These facilities are limited and are
becoming more expensive to rent or lease.
The City has developed a Parks, Recreation and Open Space Master Plan which identified the need to
build an indoor sports facility to meet current demand. There are a number of alternative sites for this
facility and a number of existing facilities which the City could rent, lease or purchase. The estimated
cost for a facility of the size considered is between $4.0 million and $6.0 million. However, the final
cost is dependent on the site selected, the uses for the facility and whether existing facilities exist.
Accordingly, the City will develop a concept plan to address the following elements:
• A needs and use assessment
• A site selection
• Concept drawings
• Alternative solutions
• Impact on operating costs
• Financing alternatives
ACTION STEPS
The following action steps have been identified:
• Contract with an urban/recreation planner to develop a plan to
address the elements listed above. 09/95
• Present recommendations to City Council. 03/96
RESPONSIBLE DEPARTMENT AND ACTIVITY
Parks and Recreation, Public Works and Administration
FINANCIAL AND STAFF RESOURCES ALLOCATED TO ACHIEVE THE GOAL
Staff hours and $25,000 for consultant services
OUTCOME/FINAL PRODUCT
An approved plan to build, lease or purchase an indoor sports facility.
f7
City of Lodi
MAJOR CITY GOAL - Compensation Policy Development
OBJECTIVE
Develop a compensation policy to guide the City Council and staff in providing fair and equitable
compensation to employees for their services which attracts and retains qualified and able employees
and which reflects the concerns of taxpayers for control of government compensation plans.
BACKGROUND AND WORKSCOPE
Compensation plays a key role in the employment of qualified staff needed to provide City services.
While the level of compensation is subject to negotiation, the need to develop policies to guide the City
Council and staff in setting compensation objectives is important. The tax paying public needs some
assurance that employees will be compensated in a manner that attracts and retains qualified staff while
at the same time reflects their ability and willingness to pay. The City's employees need assurance that
they will be paid a fair wage for their services consistent with their skills and demands from their jobs
and not be subjected to unfounded criticism and ridicule for the compensation they earn. This
undermines the morale of the employee and his family and does not promote high productivity.
The City needs to review a number of compensation strategies and policies which may be of use in
developing a policy for the City. There are a number of successful models which exist in other cities,
agencies and in the private sector which have been effective. These should be reviewed and those
elements which would fit successfully within a City policy should be presented to the City Council for
review. This policy should address total compensation. Elements to be considered in establishing a
compensation policy include:
• Performance pay tied to accomplishment and productivity
• Cafeteria plans
• Survey markets
• Cost of living adjustments
• Community values
ACTION STEPS
The following action steps have been identified:
Contract with a compensation consultant to assist staff and
Council develop a compensation policy
Conduct workshops
Review policies with City Council
RESPONSIBLE DEPARTMENT AND ACTIVITY
Personnel Department and Administration
FINANCIAL AND STAFF RESOURCES ALLOCATED TO ACHIEVE THE GOAL
Staff hours and contract services of $15,000
/9
08/95
09-12/95
02/96
City of Lodi
MAJOR CITY GOAL - Compensation Policy Development
OUTCOME/FINAL PRODUCT
A compensation policy for City employees acceptable to the City Council, the staff and general public.
City of Lodi
MAJOR CITY GOAL - Contracting Services
OBJECTIVE
To contract City services that can be performed more cost effectively by private enterprise and at
standards acceptable to the City Council.
BACKGROUND AND WORKSCOPE
The City Council adopted a budget policy in 1994 to contract City services when an opportunity to
contain the cost of government services and to enhance productivity existed. The City Council is
committed to using private sector resources in delivering municipal services as a key element in
providing cost effective services and to contain the increasing cost of government . As such, the
Council has identified two activities to be reviewed for possible contracting: (1) the maintenance of
street trees; and (2) transit services.
To conduct this review, City staff or a qualified consultant will develop a work statement which
identifies the level and quality of services to be provided, the level of management control to be
exercised in administering a contract service and the criteria to be used to evaluate cost and bids
between City staff and private contractors. Developing this criteria is demanding and important in
determining whether to contract services with private business or keep the service in-house. Every
player needs to know there is a level playing field and that the criteria used to evaluate the bids does not
favor one party or the other. Accordingly, the development of the criteria is best accomplished by an
independent consultant.
ACTION STEPS
The following action steps have been identified:
• Contract with a consultant to develop work statements, management
controls and evaluation criteria.
• Present plan to City Council for approval
• Solicit bids for street tree services
• Solicit bids for transit services
RESPONSIBLE DEPARTMENT AND ACTIVITY
Administration
FINANCIAL AND STAFF RESOURCES ALLOCATED TO ACHIEVE THE GOAL
Staff hours and $30,000 for consultant services
OUTCOME/FINAL PRODUCT
Cost effective street tree and transit services for the residents of Lodi
09/95
04/96
05/96
07/96