AGENDA TITLE: Contract Award for Wastewater Pipe Improvements, Alley South of Locust Street,
Washington Street to Cherokee Lane ($152,350)
MEETING DATE: April 19, 1995
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council adopt the attached resolution awarding the contract
for the above project to Crutchfield Construction Company in the amount
of $152,350.00.
BACKGROUND INFORMATION: This project will relieve sewage backup problems in the area by
replacing 2,000 feet of 6 -inch diameter wastewater pipe with
10 -inch diameter pipe. All the wastewater services in the alley will
be replaced and new cleanouts will be installed.
Plans and specifications for this project were approved on March 15, 1995. The City received the
following nine bids for this project:
Bidder
Location
Bid
Engineer's Estimate
$213,650
Crutchfield Construction
Stockton
$152,350
Teichert Construction
Stockton
$181,616
Environmental Construction
Sacramento
$189,740
Jardin Pipeline, Inc.
Hayward
$202,550
Wayne Fregien Engineering
Stockton
$223,760
Arcadian Enterprises
Shasta Lake
$274,100
DSS Company
Stockton
$285,400
Delta Excavating, Inc.
Brentwood
$299,400
Pfister Excavating, Inc.
Vallejo
$452,500
FUNDING: Originally Budgeted: 1992
Budgeted Fund: Wastewater Capital Reserve F nd
Current Appropriation $170,000
Total Project Estimate:$170,000
Bid Opening Date: April 5, 1995
Jack L Ronsko
Public orks Director
Prepared by Lyman Chang, Associate Civil Engineer
Attachment
cc: City Attorney
Purchasing Officer
Water/Wastewater Superintendent
APPROVED: i49%�
THOMAS A. PETERSON recycled paper
City Manager
CAWARD.DOC 04H2l&C_1
RESOLUTION NO. 95-51
A RESOLUTION OF THE LODI CITY COUNCIL
AWARDING THE CONTRACT FOR WASTEWATER PIPE
IMPROVEMENTS, ALLEY SOUTH OF LOCUST STREET,
WASHINGTON STREET TO CHEROKEE LANE
WHEREAS, in answer to notice duly published in accordance with law and the order of this City
Council sealed bids were received and publicly opened on April 5, 1995 at 11:00 a.m. for the bid for
Wastewater Pipe Improvements, Alley South of Locust Street, Washington Street to Cherokee Lane described
in the specifications therefore approved by the City Council on March 15, 1995; and
WHEREAS, said bids have been compared, checked, and tabulated and a report thereof filed with
the City Manager as follows:
Bidder
Location
Amount
Engineer's Estimate
$213,650
Crutchfield Construction
Stockton
$152,350
Teichert Construction
Stockton
$181,616
Environmental Construction
Sacramento
$189,740
Jardin Pipeline, Inc.
Hayward
$202,550
Wayne Fregien Engineering
Stockton
$223,760
Arcadian Enterprises
Shasta Lake
$274,100
DSS Company
Stockton
$285,400
Delta Excavating, Inc.
Brentwood
$299,400
Pfister Excavating, Inc.
Vallejo
$452,500
WHEREAS, the City Manager recommends award of the bid for Wastewater Pipe Improvements,
Alley South of Locust Street, Washington Street to Cherokee Lane to the lowest bidder, Crutchfield
Construction of Stockton, CA; and
NOW, THEREFORE, BE IT RESOLVED by the Lodi City Council that the award of the bid for
Wastewater Pipe Improvements, Alley South of Locust Street, Washington Street to Cherokee Lane be and
the same is hereby awarded to Crutchfield Construction of Stockton, CA, the lowest bidder, in the amount of
$152,350.00.
Dated: April 19, 1995
I hereby certify that Resolution No. 95-51 was passed and adopted by the City Council of the City of
Lodi in a regular meeting held April 19, 1995, by the following vote:
AYES: COUNCIL MEMBERS - Davenport, Pennino, Sieglock, Warner and
Mann (Mayor)
NOES: COUNCIL MEMBERS - None
ABSENT: COUNCIL MEMBERS - None
ABSTAIN: COUNCIL MEMBERS -
None
JA Q&LINEL. R
Act g