HomeMy WebLinkAboutAgenda Report - December 6, 1995 (38)AGENDA TITLE: Plans and Specifications and Advertisement for Bids for White Slough Water
Pollution Control Facility Chain Link Fence
MEETING DATE: December 6, 1995
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council approve the plans and specifications for the above
project and authorize advertising for bids.
BACKGROUND INFORMATION: This project will provide a fence around the treatment plant facilities
and ponds as a means of security for the City's operation. No
security fencing currently exists around the treatment plant. The
treatment plant administration building has experienced vandalism
and burglaries in the past and this fence will completely enclose the City operation. The fence will not
enclose either the NCPA project or the County mosquito abatement ponds and it will not interfere with the
farming of the City's leased lands.
After the fence is installed, the Public Works Department plans to install an infrared alarm system to
provide additional security and give the County Sheriff's Department more response time before intruders
can break into any buildings. The infrared alarm system is not included as part of this project and will be
brought back to Council at a later date.
The money for this project will be coming from the Wastewater Capital Outlay Reserve Fund. A request
for appropriation of funds will be made at contract award. Construction is anticipated to begin in the spring
of 1996.
FUNDING: Originally Budgeted: 1994/95
Budgeted Fund: Wastewater Capital Outlay Reserve Fund
Total Project Estimate: $68,000
Planned Bid Opening Date: January 17, 1996
Jac L. Ronsko
Publi Works Director
Prepared by Wesley K. Fujitani, Senior Civil Engineer