CITY OF LODI
COUNCIL COMMUNICATION
lN4 -Al
AGENDA TITLE: Plans and Specifications and Advertisement for Bids for Blakely Park Pool
Resurfacing, 1050 South Stockton Street
MEETING DATE: March 1, 1995
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council approve the plans and specifications for the above
project and authorize advertising for bids.
BACKGROUND INFORMATION: This project will place a new fiberglass surface on the south pool at
Blakely Park. The existing pool is heavily pitted and needs to be
refinished. Since the pool was built in 1953, only minor plaster
repairs have been made to the surfacing. These repairs were
done two years ago. The timing of this project is scheduled so it will be completed before the start of
the swimming season.
Money for this project was appropriated in the 1994/95 budget.
FUNDING: Originally Budgeted:
Budgeted Fund:
Current Appropriation:
Total Project Estimate:
Planned Bid Opening Date:
Prepared by Wesley K Fujitani, Senior Civil Engineer
JLR/WKFAm
cc: Purchasing Officer
Parks Superintendent
1994/95
Capital Outlay Reserve
$43,000
$30,000
March 22, 1995
0
,Kav-,'L
Ja L. Ronsko
Publi Works Director
APPROVED:
THOMAS A. PETERSON recycled paper
City Manager