HomeMy WebLinkAboutAgenda Report - January 18, 1995 (75)OF
CITY OF LODI
COUNCIL COMMUNICATION
AGENDA TITLE: Presentation c)f Westgate Park Design
MEETING DATE: January 18, 1995
PREPARED BY: Parks and Recreation Director
RECOMMENDED ACTION: That the City Council review the plan and design of Westgate Park and
approve a suitable design for this park facility.
BACKGROUND INFORMATION: A very interesting project that took staff (Parks and Recreation
as well as Public Works) on a path of many hours of meetings
and plan design development.
You might recall that about eight to ten months ago, we came to the Council to ask to hire a landscape
architect (not approved), a hundred plus hours later, public meetings behind us, and additional exposure
to the Parks and Recreation Commission, we bring before you tonight the Commission's suggestion
for the Westgate Park design.
Mr. Ron Williamson (Parks and Recreation), Mr. Rich Prima and Mr. Wes Fujitani (Public Works staff),
and Mr. Steve Virrey (Parks Project Coordinator) will present the plan design proposed. The
Commission's suggested design in not necessarily the design that was proposed and supported by the
development staff or the public who were present at our various meetings.
Very quickly, this design had its start in 1986 when Rich Bigler, Landscape Architect, was asked to
do a conceptual plan (with public input) to address a drainage basin park in the west area. In 1993,
when doing the Park, Recreation and Open Space Master Plan, Mr. Jerry Draggoo took the park again
under general advisement and suggested facility needs (need assessment analysis) of the area and
where these might be located. In September of this year (1994), when the staff was directed by City
Council to do an in house design of the Westgate Park facility, in addition to spending a couple of days
in Roseville and other Sacramento area cities to review recently developed parks and how to proceed
with the needed public meetings and build consensus, we set aside a plan for public meeting and input.
That plan called for a site meeting at Westgate Park itself as well as a west side meeting at Reese
School. We hand carried fliers to each home in the Westgate Park development area and made the
same available at Reese School, City Hall, the library, and the Parks and Recreation office.
We conducted two meetings that addressed the Bigler Plan and the Park, Recreation and Open Space
Master Plan suggestions and what staff saw as area and community needs. After explanation of all
plans and possible facilities for the park, the people in attendance voted on their wants and wishes.
These wants and wishes, in addition to staff recommendation went to the Commission for presentation
in November 1994 (as a regular agenda item) to introduce the project and design. It went again to
Commission for approval or recommendation in December 1994 as a public hearing.
APPROVED: /
THOMAS A. PETERSON recycled paper
City Manager
cc -1
Presentation of Westgate Park Design
January 18, 1995
Page 2
We have included our documentation to include plan "A" and "B". "A" is the staff and citizen plan.
"B" is the Parks and Recreation Commission recommended plan. Cost estimates are included and
attached for each plan. Please find included Exhibit A Plan "A" and Exhibit B Plan "B". We will make
our presentation and try to answer any questions you might have.
The Commission also asked that this message be included: If we're going to build parks, we need staff
(park maintenance) to maintain these facilities. So with the approval of this 20 acre sight, please also
consider suitable maintenance staff to support it.
FUNDING: Development Impact Fees
Plan "A" - $621,925.00
Plan "B" - $718,875.00
Ron Williamson, Director, Parks and Recreation
RW:svr
01 1895.CC
0MEMORANDUM, City of Lodi, Public Works Department
To:Parks and Recreation Director+
From: City Engineer
Date: December 1, 1994
Subject: Westgate Paris Funding and Schedule
At the last Parks and Recreation Commission meeting, the question was raised about available funding
and the Park's development schedule. These questions cannot be completely answered at this time
because the Parks and Recreation portion of the Capital Improvement Program (CIP) has not been
updated since the adoption of the Park, Recreation and Open Space Master Plan. While the Master
Plan contained the various project budget estimates, the CIP is where the City's capital priorities are set
and the projects are shown in their expected year of construction. The last long-range CIP (to the
General Plan horizon year of 2007) was done in November 1993. in that program, the Westgate Park
improvements were shown for construction in 1996197 at a cost of $353,000. Since then, the budget
format has been changed to include capital projects; however, the long-range CIP was not included in
the annual budget. We still need this type of long-range planning document. The Finance Director and I
are still discussing this issue and hope to resolve it for the next budget cycle.
Presently, funds to complete the turf and irrigation system are appropriated from the Storm Drain and
Parks and Recreation Development Impact Mitigation Fee (iMF) funds. The latest cost and funding
breakdown is shown on the attached sheet.
The part you are mostly interested in is the remaining $479,000 for park improvements. This will come
solely from the Parks and Recreation IMF Fund. The Fund presently has approximately $780,000
available, plus there is an additional $330,000 guaranteed to be paid from subdivisions in progress.
While it appears we could complete Westgate Park in 1995, there are other IMF projects to consider in
the next few years:
• Master plan and improvements for DeBenedetti Park
• Acquisition and improvements for the Southeast Area Park south of Johnson Ranch
subdivision
• Master plan and adjacent property acquisition at Roget Park
. Lodi Lake expansion - west 13 acres
Any one of these projects could use all available funds; however, our Westgate Park sales agreement
does call for the City to '...diligently pursue the completion of the basin/park, including turfing and
Irrigation, on a schedule compatible with the Seller's development plans, taking into account the
availability of funds for such projects.' Given that the Lodi West development will take a few more
years, it is reasonable to assume the City will work toward completing the Park over a similar time frame.
Senior Civil Engineer Wes Fujitani will be attending the Parks and Recreation Commission meeting on
December 6 on behalf of the Public Works Department. If you have any questions or need additional
information, please contact Wes or myself at your convenience.
Richard C. Prima, Jr
City Engineer
RCPAm
attachment
cc: Public Works Director
Finance Director
Senior Civil Engineer
MP&R9Q1.D0C
Westgate Basin/Park Expansion Cost Estimate
Basin expansion area: 15.99 acres (gross)
Net expansion area: 15.5 acres
Note: all costs below rounded to nearest $1,000.
It
Total Cost: $2,911,000
by developer per purchase agreement, developer gets to sell dirt
per 1994 City Master Plan less park share of site costs above and including $5,000 of other funds for improvements attributable to non-resident use.
Previous development costs of existing site not included.
12/1/94 E BAWESTALS
Storm Drain Fee Program
Parks & Recreation Fee
Improvements
Cost
Cost
Program Cost
Basin/Park Acquisition
$115,000/ac.
14.09 ac.
$1,621,000
1.90 ac.
$218,000
street R/W prorated by on-site area
Excavation/Grading•
$0.00/CY
118,830 CY
$0
0%
$0
Topsoil removelrepl'
$0.00/CY
18,500 CY
$0
0%
$0
Rip & roll bottom'
$0.000/SF
365,500 SF
$0
0%
$0
Dirt sale'
$0.00/CY
118,830 CY
$0
0%
$0
Fence w/mowstrip around basin
$47,000
100%
$47,000
0%
$0
basin security fence
Fence w/mowstrip @ property line
$36,000
0%
$0
100%
$36,000
park security fence
Frontage Impr. Unit #1'
$62,000
88%
$55,000
12%
$7,000
Evergreen Dr.
Frontage Impr. Unit 92
$28,000
88%
$25,000
12%
$3,000
Applewood Dr.
Interior Drainage
$27,000
100%
$27,000
0%
$0
Irrigation System expansion
$233,000
88%
$205,000
12%
$28,000
prorated by area of basin/high ground
Turf
$160,000
88%
$141,000
12%
$19,000
Park Improvements—
$479,000
0%
$0
100°x6
$479,000
_
Total Cost:
$2,121,000
$790,000
-
Total Cost: $2,911,000
by developer per purchase agreement, developer gets to sell dirt
per 1994 City Master Plan less park share of site costs above and including $5,000 of other funds for improvements attributable to non-resident use.
Previous development costs of existing site not included.
12/1/94 E BAWESTALS
PROP06ED WE5TGATE PARK 1MPROVEMENT5: PLAN "A"
POTENTIAL UNIT TOTAL
IMPROVEMENTS QUANTITY UNIT PRICE COOT
ELECTRICAL SERVICE
01
ALLOWANCE
40 000.00
40 000.00
INTERIOR PARK LIGHTING
20
EACH POLE
3,500.00
70 000.00
DRINKING FOUNTAIN
02
EACH
1200.00
2,400.00
PLAYGROUND EQUIPMENT SYSTEM
01
ALLOWANCE
40000.00
40000.00
ADA PLAYGROUND COVER
01
ALLOWANCE
7000.00
7000.00
PICNIC SHELTER
01
EACH
30 000.00
30 000.00
TREES
150
EACH
220.00
33 000.00
10 FT PICNIC TABLES
06
EACH
600.00
3,000.00
8 FT PICNIC TABLES
05
EACH
525.00
2 625.00
HEAVY DUTY 13AR-13-OUE
01
EACH
600.00
800.00
PARK SIGN
01
EACH
3,500.00
3,500.00
RESTROOM/STORAGE BUILDING
01
EACH
100 000.00
100 000.00
6 FT BIKEIWALK PATH SYSTEM
4,500
LINEAL FEET
22.00
99 000.00
MISC. LANDSCAPE
01
ALLOWANCE
40 000.00
40 000.00
PAVED BASKETBALL COURT
01
EACH
26 000.00
26 000.00
IN-LINE HOCKEY COURT
01
EACH
28,000.00
26,000.00_
51NGLE PICNIC AREA 5LA135
05
EACH
3 000.00
15 000.00
PARK FURNITURE
01
ALLOWANCE
20 000.00
20 000.00
13ACKOTOPO - PRACTICE FIELDS
03
EACH
8.000.00
24,000.00
SHADE STRUCTURE PLAYGROUND AREA
01
EACH
35.000.00
35,000.00_
TOTAL COOT ESTIMATE: $621,925.00
PARKING 50 EACH SPACE 900.00 45,000.00
TOTAL BUDGET AVAILABLE: $479,000.00 TOTAL C05T ESTIMATE WITH PARKING AREA: $638,925.00
POTENTIAL GRANT FUNDS: $183,000.00 EXCLUDING IN-LINE HOCKEY COURT COST.
S.VIRREY 12/06/94