HomeMy WebLinkAboutResolutions - No. 2023-216RESOLUTION NO. 2023-216 A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 4 WITH SCHWEITZER ENGINEERING LABORATORIES (SEL) ENGINEERING SERVICES, INC., OF VACAVILLE, FOR SUBSTATION RELAY MODERNIZATION PROJECT WHEREAS, Lodi Electric Utility (LEU) is continuing efforts to upgrade all remaining solid- state and electromechanical relays to microprocessor relays, and this effort includes the standardization of equipment to Schweitzer Engineering Laboratories (SEL) Engineering Services, Inc., which both provides equipment and engineering services; and WHEREAS, on April 20, 2022, the City authorized an Agreement with SEL in the amount of $1,024,073 to upgrade the existing incoming 60 kV relays at Industrial Substation to improve protection coordination between LEU and PG&E, as well as asset monitoring and protection of the incoming 60 kV power supply and equipment at Industrial Substation; and WHEREAS, on February 1, 2023, Change Order No. 1 to the SEL Agreement was authorized to add $421,578 in funding for additional commissioning and support, as well as the addition of one new relay protection panel; and WHEREAS, on July 6, 2023, the City approved Change Order No. 2 to extend the completion date of work from March 2023 to December 2023 to minimize system impacts during the warmer months of the year; and WHEREAS, on July 13, 2023, the City approved Change Order No. 3 (CCO 3) in the amount of $250,733 for work associated with the State of California Natural Gas Power Plant with the actual cost of the work under CCO 3 to be reimbursed in full by the State as part of its contractual obligations to the City; and WHEREAS, with equipment near or at end -of -life, LEU proposes to continue to use SEL to upgrade and replace the 12 kV relaying at Industrial Substation, and these efforts will also include replacing two 60kV substation breakers at Industrial Substation, which will require complex coordination efforts between LEU, PG&E, SEL, and others; and WHEREAS, SEL provides full substation upgrade services required for the Industrial Substation, including the best combination of expertise and qualifications to install and setup SEL devices, as well providing a means of third -party Factory Acceptance Testing to perform detailed auditing of all installation and wiring work prior to full commissioning; and WHEREAS, utilizing SEL will provide for the standardization of equipment and substation commissioning throughout the existing LEU substations and LEU's previous and current collaborative efforts with SEL have proven successful and incredibly efficient and thorough to maintain a safe and reliable electrical system; and WHEREAS, including this proposed change order, the amount of SEL's Agreement for this project totals $2,597,853 and is included in the City's 5 -Year Capital Improvement Program. NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby authorize the City Manager to execute Change Order No. 4 with Schweitzer Engineering Laboratories (SEL) Engineering Services, Inc., of Vacaville for the Substation Relay Modernization Project in the amount of $901,469; and BE IT FURTHER RESOLVED, pursuant to Section 6.3q of the City Council Protocol Manual (adopted 11/6/19, Resolution No. 2019-223), the City Attorney is hereby authorized to make minor revisions to the above -referenced document(s) that do not alter the compensation or term, and to make clerical corrections as necessary. Dated: October 18, 2023 I hereby certify that Resolution No. 2023-216 was passed and adopted by the City Council of the City of Lodi in a regular meeting held October 18, 2023 by the following votes: AYES: COUNCIL MEMBERS — Bregman, Craig, Nakanishi, Yepez, and Mayor Hothi NOES. COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS — None ABSTAIN: COUNCIL MEMBERS — None OLIVIA NASHED City Clerk 2023-216