HomeMy WebLinkAboutAgenda Report - April 4, 2001 E-23CITY OF LODI COUNCIL COMMUNICATION
AGENDA TITLE: Adopt resolution authorizing the City Manager to provide a Public Benefits Program Grant in
the amount of $25,000 to fund the Demand-side Management Project for Holz Rubber
MEETING DATE: April 4, 2001
PREPARED BY: Electric Utility Director
RECOMMENDED ACTION: That the City Council adopt a resolution authorizing the City Manager to
provide a Public Benefits Program Grant in the amount of $25,000 to Holz
Rubber Company as part of a demand-side management project.
BACKGROUND INFORMATION: In an effort to reduce annual energy costs, Holz Rubber Company, located at
1129 South Sacramento Street, has embarked upon a series of demand-side
management projects. The first phase of their effort consists of insulating the
entire steam pipe delivery and return system within the facility. Prior to insulating the delivery and return system, the
piping will be checked for leaks (any and all leaks will be repaired/sealed before insulation is added). This element will
save nearly $40,000 a year in energy costs.
The second phase in the energy conservation plan is to test, and where needed, clean or replace all existing steam
traps inside the facility. It is estimated that this will save in excess of $7,000 annually. The third and final phase of the
demand-side management plan is to install a curtain enclosure system around the facilities press and molding
machines. The enclosure system reduces heat loss, and will have a projected energy savings of $2,500 per year.
Future proposed demand-side management or energy conservation measures include: a facility -wide lighting retrofit,
installing new skylights, and insulating the facilities autoclaves, caustic tanks and boiler(s).
Assisting the City of Lodi Electric Utility in the identification of the various energy conservation measures were
Planergy International, the city's chosen energy services company, and the engineering and maintenance team at
Holz Rubber Company. The aforementioned energy efficiency improvements are recommended, and do qualify as
approved demand-side management components of the City of Lodi Public Benefits Program.
FUNDING: 164605 — Public
Benefits Program (Category: Demand-side Management)
Funding Approval:
Vicky WAthie, Finance Director
Alan N. Vallow
Electric Utility Director
PREPARED BY: Rob Lechner, Manager of Customer Programs
ANV/RUlst
APPROVED:
H. Dixon F nn - City Manager
April 4, 2001: Addendum to Consent Calendar Items E-21 and E-23
E-21, Public Benefits Program Grant- Quashnick Tools Company Demand-side
Management Project ($15,562)
The grant amount of $15,562 to Quashnick Tools demand-side management project reflects a
10% contribution from the City of Lodi Public Benefits Program fund. To date, all other demand-
side management rebates to commercial & industrial customers have been 25% of the total
project cost.
Rationale: In reviewing the scope of work, and the particular equipment to be purchased, it was
determined that a 10% Public Benefits Program grant was most appropriate. Quashnick Tools
has approximately fourteen (14) milling machines, or similar pieces of equipment, that are utilized
in like fashion to the BostoMatic 12 recently purchased (and is the eligible piece of equipment for
an energy efficiency rebate). The BostoMatic 12, which is a high efficiency/energy efficient unit,
will replace a 15 year old milling machine. However, Quashnick Tools total energy reduction- as
a result of replacing one inefficient/aging milling machine- was assessed as nominal. It has been
determined that the new BostoMatic 12 consumes 20% less electricity than the existing piece of
equipment. After carefully assessing these various factors, it is recommended that a Public
Benefits Program grant of less than the traditional 25% is most appropriate for this project (a 10%
grant is the requested grant amount).
--� E-23, Public Benefits Program Grant- Holz Rubber Company Demand-side Management
Project ($25,000)
The grant amount of $25,000 to Holz Rubber Company's demand-side management project
reflects a 25% contribution from the City of Lodi Public Benefits Program fund. This 25%
contribution figure was not listed on the original City Council Communication.
In March of this year, Holz Rubber Company approached the Electric Utility Department staff
seeking assistance in reducing their overall energy costs. The City of Lodi Electric Utility enlisted
the services of Planergy International (formerly Energy Masters International), the city's chosen
energy services partner, to provide an immediate solution to Holz Rubber Company's request.
Following a day -long visit and assessment of the Holz facility, Planergy International
recommended the most advantageous (and simplest to implement) energy efficiency
improvement: insulating the hundreds of feet of steam pipe within the plant. The estimated total
project cost to Holz Rubber Company, as projected by the aforementioned assessment, is
$100,000.
Holz Rubber: Scope of Work
Steam System Improvements
Steam Pipe
Insulation work will be performed during regular business hours
Piping modifications must be performed on weekends when boiler is down
Reuse existing 4" header to presses
Install new branch lines and fittings to presses
Install new valves in branch lines (approx. 60) to presses
Replace flex pipe to presses as needed (approx. 100 of the approx. 300 hoses)
Owner to provide in-house custom made flex pipe to presses; Planergy to install
Replace existing Y- 6" supply line valves (appox. 3)
Insulate approx. 100' of 5"- 6" steam pipe and all fittings
Insulate approx. 80' of 4" steam pipe and all fittings
Insulate approx. 935' of 2" steam pipe and all fittings
Insulate approx. 30' of 1-1l2" steam pipe and all fittings
Removable insulation will be installed for areas of high maintenance, i.e. supply valves
Condensate Return Pipe
Insulate approx. 100' of 6" condensate return pipe and all fittings
Insulate approx. 100' of 4" condensate return pipe and all fittings
Insulate approx. 100' of 2" condensate return pipe and all fittings
Steam Traps
Test all existing traps for operation
Replace steam traps as needed (approx. 35 of 70) with rugged inverted bucket traps
Potentially all traps could need replacement
Properly size all steam traps to be installed
Install new steam traps as necessary where traps currently do not exist
Autoclaves
Install insulation on six (6) autoclaves.
Caustic Tanks
Install insu Four (4) tanks currently operate without covers
Note: It is strongly recommended that covers are fabricated for these tanks
Generally, these tanks are kept at 180 degrees exposed to atmosphere
VV/il/iVvt SLY aary •a•aa vaVvry vvaa ••+••••"�•"�
Holz Rubber. Draft Project Summary
Steam System Improvements
Utilization Factor = 50%
Annual Consumption (Therms) =
Energy
Total
52,417
Average Esti hated Gas Cost =
Savings
Savings
Total
Installed Cost =
MMStu/Yr
(Therms) Savings ($)
Steam Piping Insulation
4,599
45,994 $
36,795
Condensate Return Piping Insulation
398
3,982 $
3,185
Autoclaves Insulation
172
1,672 S
1,338
Caustic Tank insulation
589
5,721 $
4,576
"Jacuzzr Covers
0
0 $
-
Steam Leaks
948
9,203 S
7,362
Steam Traps
1,179
11,450 $
9,160
2,127
78,021 S
62,417
Annual Consumption (Therms) =
360,000
Projected Savkvs =
52,417
Average Esti hated Gas Cost =
$ 0.80
Percent Savings =
22%
Installed Cost =
183,067
Simple Payback =
2.9
(Could be as high as $100,000)
(Recent Costs have been as high as $2.29/therm)
(Could be as low as $133,000)
RESOLUTION NO. 2001-80
A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING
THE CITY MANAGER TO PROVIDE A PUBLIC BENEFITS
PROGRAM GRANT — DEMAND-SIDE MANAGEMENT PROJECT
TO HOLZ RUBBER COMPANY
WHEREAS, the State has mandated that beginning January 1, 1998, the City of
Lodi is obligated to fund various programs through a Public Benefits Charge (PBC)
based on a historical electric revenue requirement; and
WHEREAS, the requirement amounts to approximately $1 Million per year that
must be dedicated to qualifying programs such as energy efficiency. A further stipulation
is that these efforts must be done on the customer's side of the meter in order to qualify;
and
WHEREAS, the Electric Utility Department recommends that the City provide a
Public Benefits grant in the amount of $25,000.00 to fund the following projects:
1) The first phase of their effort consists of insulating the entire steam pipe
delivery and return system within the facility. Prior to insulating the
delivery and return system, the piping will be checked for leaks (any and
all leaks will be repaired/sealed before insulation is added). This element
will save nearly $40,000 a year in energy costs.
2) The second phase in the energy conservation plan is to test, and where
needed, clean or replace all existing steam traps inside the facility. It is
estimated that this will save in excess of $7,000 annually.
3) The third and final phase of the demand-side management plan is to
install a curtain enclosure system around the facilities press and molding
machines. The enclosure system reduces heat loss, and will have
projected energy savings of $2,500 per year.
WHEREAS, assisting the City of Lodi Electric Utility in the identification of the
various energy conservation measures were Planergy International, the City's chosen
energy services company, and the engineering and maintenance team at Holz Rubber
Company. The aforementioned energy efficiency improvements are recommended, and
do qualify as approved demand-side management components of the City of Lodi Public
Benefits Program.
NOW, THEREFORE, BE IT RESOLVED, that the Lodi City Council hereby
authorizes the City Manager to provide a Public Benefits Program Grant in the amount of
$25,000.00 to Holz Rubber Company to fund a demand-side management project as set
out above.
Dated: April 4, 2001
I hereby certify that Resolution No. 2001-80 was passed and adopted by the Lodi
City Council in a regular meeting held April 4, 2001 by the following vote:
AYES: COUNCIL MEMBERS — Hitchcock, Land and Mayor Nakanishi
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — Howard and Pennino
ABSTAIN: COUNCIL MEMBERS — None
SUSAN J. BLACKSTON
City Clerk
2001-80