HomeMy WebLinkAboutMinutes - April 4, 2023 SSFUTURE LODI SHOOTING RANGE
& TRAINING FACILITY
Project location
Current status:
The Lodi Police Department currently utilizes a gun range located in the basement of the old Police
Department building that is under repair.
Officer practice and Quarterly handgun qualifications
Monthly SWAT qualifications
Classes and Demonstrations (Citizen’s Academy / Leadership Lodi)
Need:
We are unable to meet our rifle qualifications due to size of current range.
Current Cost Reduced by Outdoor Range:
Rental costs to utilize a range meeting qualification requirements
(cost $300 –500 per session)
Staff overtime and peripheral costs to travel to other facilities if they are available
Galt (50 mins round trip)
Linden (1 hour round trip)
Stockton PD (1 hour round trip)
Fairfield (1.5 hours round trip)
An outdoor range could potentially generate revenue for rental to other agencies, schools, or public groups.
Additionally, it will be a tool for not only recruitment, but also employee retention.
Current status:
The Lodi Police Department currently utilizes a variety of facilities and locations in order to accomplish
required training and conduct operations.
Rick Cromwell Community Room
Hutchins Street Square / Grape Festival Grounds
Bond Manufacturing / Tokay and Lodi High
Need:
Location to permanently house our Virtual Reality training simulator
Location to safely detonate explosive devices
A state of the art training facility can attract new employees and help retain our current employees.
Current Cost Reduced by Outdoor Range:
Liability of detonating explosive devices in areas not designed
Staff overtime and peripheral costs to locate training facilities, transporting equipment to facilities, and set
up/ take down time such as range equipment, VR simulator, defensive tactics mats and pads.
Training facility rooms could potentially generate revenue for rental to other agencies, schools, or public
groups.
Current status:
We currently utilize an EVOC (Emergency Vehicle Operation Course) in Alameda County at the Sheriff’s
Department training center.
Officers are required to complete this training every two years
Need:
There are no EVOC training centers in our immediate area.
Current Cost Reduced by EVOC:
Qualification course requirements (cost $1,000 –1,500 per officer per session)
Staff overtime and peripheral costs to travel to other facilities if they are available
Alameda County Sheriff’s Dept. EVOC (2.5 hours round trip)
Mather AF Base (1.5 hours round trip)
Crows Landing (2 hours round trip)
EVOC could potentially generate revenue for rental or leasing to other agencies, schools, or public groups.
A partnership with San Joaquin Delta College for this project would be beneficial to continue to attract new
employees. Many of our officers have graduated from their academy. A partnership would also help us to stay
up to date on current best practices, training techniques, and technological advances to provide the best law
enforcement services possible. There are numerous agencies in our area that have shown interest in specifically
utilizing our EVOC and this could generate revenue for our City and San Joaquin Delta College.
Training Facility divided into three (3) phases:
Phase 1:
EVOC area: Paving and grading & EVOC Fencing
1 -300 yard range (10 Positions)
Access Road Improvements
Site Clearing and Grading
Site Fencing
Phase 2:
2 -100 yard ranges
30 position range
10 position range
3 -25 yard ranges (10 positions each)
open interior to also use as 30 positions
EOD Storage and Detonation Area
270 degree range
Training Buildings, bathrooms, and Storage
Phase 3:
Parking
Large Training Building, bathrooms, and shade areas
ENTRANCE
90’ x 60’
Gym / DTac
room
30’ x 30’
Armory
100’ x 60’
Classroom
30’ x 30’
VR room
30’ x 30’
Breakroom or
Classroom
30’ x 30’
Classroom
or Office
252’
60’
EVOC COURSE
Security Cameras
Lighting
City of Lodi Police Training Facility
Engineer's Opinion of Probable Cost February 2023
Engineer's Estimate (60% Design)
Project Features:
Site Clearing and Grading
1 EA -300 Yard Range (10 Total Shooting Positions)
2 EA -100 Yard Ranges (40 Total Shooting Positions)
3 EA -25 Yard Ranges (10 Total Shooting Positions)
Safety Berms and Protective Shielding Walls at Ranges
Defensive Driving Training Course
EOD Detonation Area
Site Drainage
Access Roads
Parking Areas with ADA Stalls
Areas for Training Buildings/Restrooms and Storage
Site Fencing with with Gate Access (Site, EVOC, EOD)
Engineer's Estimate
(60% Design)
$2,000,000
Recommended
Escalation/Contingenc
y/ Support Services
$970,000
Not In Design
Contract Items**
$14,000
Estimated Cost to
Construct (60%
Design)*
$2,984,000
PHASE 1 (2024)PHASE 2 (2025)PHASE 3 (2026)
Engineer's Estimate
(60% Design)
$2,000,000
Recommended
Escalation/Contingenc
y/ Support Services
$1,105,000
Not In Design
Contract Items**
$321,588
Estimated Cost to
Construct (60%
Design)*
$3,426,588
Engineer's Estimate
(60% Design)
$500,000
Recommended
Escalation/Contingenc
y/ Support Services
$310,000
Not In Design
Contract Items**
$1,411,500
Estimated Cost to
Construct (60%
Design)*
$2,221,500
Engineer's Estimate (60% Design) (Phase 1)
Item Description Unit Quantity Unit Cost Cost
1.0 Clearing and Grubbing AC 23 $ 6,000.00 $ 136,170.80
2.0 Aggregate Base (Roads/Concrete/Asphalt)CY 4564 $ 48.00 $ 219,092.09
3.0 Asphalt Concrete TON 4815 $ 125.00 $ 601,851.85
4.0 Concrete (ADA, Firing Range)CY 38 $ 800.00 $ 30,444.44
5.0 Striping SF 0 $ 3.00 -
6.0 Signage EA 0 $ 300.00 -
7.0 Berms (Import and Placement)CY 2100 $ 30.00 $ 63,000.00
8.0 Site Grading (Rough Grading)AC 22 $ 5,000.00 $ 110,000.00
9.0 CMU Walls SF 128 $ 25.00 $ 3,202.50
10.0 Fencing (8' tall w/ 3 barbed wire)LF 5650 $ 60.00 $ 339,000.00
11.0 Access Gates EA 2 $ 10,000.00 $ 20,000.00
12.0 HESCO Barriers (Protective Shielding Walls)LF 0 $ 160.00 -
13.0 Ballistic Sand (Import and Placement)CY 250 $ 40.00 $ 10,000.00
14.0 K-Rails LF 1910 $ 50.00 $ 95,500.00
15.0 Drainage -Swales (Excavation/Backfill)LF 4400 $ 25.00 $ 110,000.00
16.0 Drainage -Trench Drain LF 0 $ 120.00 -
17.0 Drainage -Culvert (24")LF 65 $ 250.00 $ 16,250.00
18.0 Drainage -Abandon Culvert LF 40 $ 100.00 $ 4,000.00
19.0 Erosion Control Seeding AC 4 $ 5,700.00 $ 22,800.00
20.0 Electrical LS 1 $ 250,000.00 $ 250,000.00
SUBTOTAL $ 2,031,311.68
Estimate $2,000,000
Recommended Construction
Escalation to 2024
10% $200,000
Escalated Estimate 2024 $2,200,000
Recommended Construction
Contingency
15% $330,000
Engineering Services During
Construction
5% $110,000
Construction Management 10% $220,000
Environmental Support 5% $110,000
Total Estimated Cost to Construct Phase 1 $2,970,000
Description Unit Quantity Unit Cost Cost
Not In Contract
a Storage Containers EA 2 $ 7,000.00 $ 14,000.00
b Mobile Restrooms EA 0 $ 100,000.00 -
c Shaded Area -50'x20' (EVOC)SF 0 $ 25.00 -
d Shaded Area -100'x35' (Large
Classroom)
Item No.0 $ 25.00 --
e Overhand Awning -12'x10' (EOD)SF 0 $ 25.00 -
f Classrooms -40'x24' (2 EA) SF 0 $ 75.00 -
f.1 ADA Sidewalk (Asphalt)TON 0 $ 125.00 -
g Classrooms-252'x60' SF 0 $ 75.00 -
h Elevated Shooting Platform EA 0 $ 600.00 -
i Training Poles EA 0 $ 600.00 -
SUBTOTAL $ 14,000.00
Engineer's Estimate (60% Design) (Phase 1)
Engineer's Estimate (60% Design) (Phase 2)
Item Description Unit Quantity Unit Cost Cost
1.0 Clearing and Grubbing AC 23 $ 6,000.00 -
2.0 Aggregate Base (Roads/Concrete/Asphalt)CY 4564 $ 48.00 $ 25,341.01
3.0 Asphalt Concrete TON 4815 $ 125.00 -
4.0 Concrete (ADA, Firing Range)CY 38 $ 800.00 $ 199,288.89
5.0 Striping SF 0 $ 3.00 $ 4,185.00
6.0 Signage EA 0 $ 300.00 $ 2,700.00
7.0 Berms (Import and Placement)CY 2100 $ 30.00 $ 1,173,000.00
8.0 Site Grading (Rough Grading)AC 22 $ 5,000.00 -
9.0 CMU Walls SF 128 $ 25.00 $ 311,980.00
10.0 Fencing (8' tall w/ 3 barbed wire)LF 5650 $ 60.00 $ 40,200.00
11.0 Access Gates EA 2 $ 10,000.00 $ 10,000.00
12.0 HESCO Barriers (Protective Shielding Walls)LF 0 $ 160.00 -
13.0 Ballistic Sand (Import and Placement)CY 250 $ 40.00 $ 23,022.22
14.0 K-Rails LF 1910 $ 50.00 -
15.0 Drainage -Swales (Excavation/Backfill)LF 4400 $ 25.00 -
16.0 Drainage -Trench Drain LF 0 $ 120.00 -
17.0 Drainage -Culvert (24")LF 65 $ 250.00 -
18.0 Drainage -Abandon Culvert LF 40 $ 100.00 -
19.0 Erosion Control Seeding AC 4 $ 5,700.00 -
20.0 Electrical LS 1 $ 250,000.00 $ 170,000.00
SUBTOTAL $ 1,959,717.12
Estimate $2,000,000
Recommended Construction
Escalation to 2025
15% $300,000
Escalated Estimate 2025 $2,300,000
Recommended Construction
Contingency
15% $345,000
Engineering Services During
Construction
5% $115,000
Construction Management 10% $230,000
Environmental Support 5% $115,000
Total Estimated Cost to Construct Phase 1 $3,105,000
Description Unit Quantity Unit Cost Cost
Not In Contract
a Storage Containers EA 2 $ 7,000.00 $ 21,000.00
b Mobile Restrooms EA 0 $ 100,000.00 $ 100,000.00
c Shaded Area -50'x20' (EVOC)SF 0 $ 25.00 $ 25,000.00
d Shaded Area -100'x35' (Large
Classroom)
Item No.0 $ 25.00 --
e Overhand Awning -12'x10' (EOD)SF 0 $ 25.00 $ 25,000.00
f Classrooms -40'x24' (2 EA) SF 0 $ 75.00 $ 144,000.00
f.1 ADA Sidewalk (Asphalt)TON 0 $ 125.00 $ 28,587.96
g Classrooms-252'x60' SF 0 $ 75.00 -
h Elevated Shooting Platform EA 0 $ 600.00 -
i Training Poles EA 0 $ 600.00 -
SUBTOTAL $ 321,587.96
Engineer's Estimate (60% Design) (Phase 2)
Engineer's Estimate (60% Design) (Phase 3)
Item Description Unit Quantity Unit Cost Cost
1.0 Clearing and Grubbing AC 23 $ 6,000.00 -
2.0 Aggregate Base (Roads/Concrete/Asphalt)CY 4564 $ 48.00 $ 18,333.33
3.0 Asphalt Concrete TON 4815 $ 125.00 -
4.0 Concrete (ADA, Firing Range)CY 38 $ 800.00 -
5.0 Striping SF 0 $ 3.00 -
6.0 Signage EA 0 $ 300.00 -
7.0 Berms (Import and Placement)CY 2100 $ 30.00 -
8.0 Site Grading (Rough Grading)AC 22 $ 5,000.00 -
9.0 CMU Walls SF 128 $ 25.00 -
10.0 Fencing (8' tall w/ 3 barbed wire)LF 5650 $ 60.00 -
11.0 Access Gates EA 2 $ 10,000.00 -
12.0 HESCO Barriers (Protective Shielding Walls)LF 0 $ 160.00 $ 294,400.00
13.0 Ballistic Sand (Import and Placement)CY 250 $ 40.00 -
14.0 K-Rails LF 1910 $ 50.00 -
15.0 Drainage -Swales (Excavation/Backfill)LF 4400 $ 25.00 -
16.0 Drainage -Trench Drain LF 0 $ 120.00 -
17.0 Drainage -Culvert (24")LF 65 $ 250.00 -
18.0 Drainage -Abandon Culvert LF 40 $ 100.00 -
19.0 Erosion Control Seeding AC 4 $ 5,700.00 -
20.0 Electrical LS 1 $ 250,000.00 $ 230,000.00
SUBTOTAL $ 542,733.33
Estimate $500,000
Recommended Construction
Escalation to 2026
20% $100,000
Escalated Estimate 2026 $600,000
Recommended Construction
Contingency
15% $90,000
Engineering Services During
Construction
5% $30,000
Construction Management 10% $60,000
Environmental Support 5% $30,000
Total Estimated Cost to Construct Phase 3 $810,000
Description Unit Quantity Unit Cost Cost
Not In Contract
a Storage Containers EA 0 $ 7,000.00 -
b Mobile Restrooms EA 1 $ 100,000.00 $ 100,000.00
c Shaded Area -50'x20' (EVOC)SF 0 $ 25.00 -
d Shaded Area -100'x35' (Large
Classroom)
SF 3500 $ 25.00 $87,500.00
e Overhand Awning -12'x10' (EOD)SF 0 $ 25.00 -
f Classrooms -40'x24' (2 EA) SF 0 $ 75.00 $72,000.00
f.1 ADA Sidewalk (Asphalt)TON 0 $ 125.00 -
g Classrooms-252'x60' SF 0 $ 75.00 $1,134,000.00
h Elevated Shooting Platform EA 0 $ 600.00 $12,000.00
i Training Poles EA 0 $ 600.00 $6,000.00
SUBTOTAL $ 1,411,500.00
Engineer's Estimate (60% Design) (Phase 3)
Amount expended already:
•Approx. 10 years of City Employee Labor costs working on project in excess of 1,000 hours
•19 acres of land at $40k per acre = $760,000
QUESTIONS?
TOTAL ESTIMATED COSTS
TO COMPLETE BUILDING CURRENTLY:
$8,632,088