HomeMy WebLinkAboutAgenda Report - May 17, 2023 C-06CITY OF tgo Z10 Z CALIFORNIA AGENDA ITEM C 0 (P COUNCIL COMMUNICATION AGENDA TITLE: Adopt Resolution Ratifying Expenses and Authorizing City Manager to Execute Change Orders to Alley Improvement Project — Phase 9 ($1,004.54) and Accept Improvements Under Contract for Alley Improvement Project — Phase 9 MEETING DATE: May 17, 2023 PREPARED BY: Public Works Director RECOMMENDED ACTION: Adopt Resolution Ratifying Expenses and Authorizing City Manager to Execute Change Orders to Alley Improvement Project — Phase 9 ($1,004.54) and Accept improvements under contract for Alley Improvement Project — Phase 9 BACKGROUND INFORMATION: The City has reconstructed various alleys over the past 10 years. The projects have typically included between one and two alleys per year, depending on funding levels. Specific projects are selected based on a citywide alley condition assessment list and are rated based on pavement condition and drainage improvement needs. This project reconstructed the alley north of Walnut Street, between Washington Street and Central Avenue, as shown on Exhibit A. The project included approximately 15,000 square feet of pavement removal and replacement, two new concrete alley approaches, installation of 550 lineal feet of concrete valley gutter, installation of storm drain system improvements, and other incidental and related work, all as shown on the plans and specifications for the above project. The final cost of the contract was $440,913.54 and was completed in substantial conformance with the specifications approved by City Council. There were two change orders totaling $41,004.54. Since the Council action to award the contract limited City Manager change order authority to $40,000, staff is requesting Council ratify the additional $1,004.54 expenditure that exceeded the $40,000 limit. Change Order 1 ($21,716.79) included costs due to expended time and materials work required to address an existing water line, which was installed more shallow than shown on the as built plans. This condition required several final paving modifications. The original contract was 40 days; 27 calendar days were added to make the necessary adjustments. Change Order 2 ($19,287.75) was an internal change order in unit item quantities to account for additional paving and gutter length to accommodate the adjusted grades. The contract was completed prior to the adjusted contract completion date. Photos of completed work are shown in Exhibit B. APPROVED.sr,•,, r. E M,, s.an7.:1i,3:rn, " Stephen Schwabauer, City Manager \\cvcfi lv02\pu bwks$\WP\PROJ ECTS\STR EETS\Al ley Improvements Phase 9 (2021)\CRatC0Accept1.docx 5/4/2023 Adopt Resolution Ratifying Expenses and Authorizing City Manager to Execute Change Orders to Alley Improvement Project — Phase 9 ($1,004.54) and Accept Improvements Under Contract for Alley Improvement Project— Phase 9 February 15, 2023 Page 2 Following acceptance by the City Council, as required by law, the City Engineer will file a Notice of Completion with the County Recorder's office. The notice serves to notify vendors and subcontractors that the project is complete and begins their 30 -day period to file a stop notice requiring the City to withhold payments from the prime contractor in the event of a payment dispute. FISCAL IMPACT: The project will reduce maintenance costs in the reconstructed alleys. FUNDING AVAILABLE: This project was funded by 2020/21 Community Development Block Grant funds ($538,147) CE�22 Charles E. Swimley, Jr. Public Works Director Prepared by Jim! Billigmeier, Associate Civil Engineer CES/AB/CD Attachments cc: CDBG Program Specialist \\cvcfilv02\pubwks$\wP\PROJECTS\STREETS\Alley Improvements Phase 9 (2021)\CRatCOAcceptl.docx 5/4/2023 2021/22 Alley Improvement Project - Phase 9 Exhibit A 9 Oak St. 'a Walnut St. Walnut St. Legend Project Location Boundary /" h-Rho, 0 50 100 Feet 200 Alley Improvement Contract — Phase 9 EXHIBIT B Before After RESOLUTION NO. 2023-90 A RESOLUTION OF THE LODI CITY COUNCIL RATIFYING EXPENSES AND AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDERS TO ALLEY IMPROVEMENT PROJECT — PHASE 9 WHEREAS, this project reconstructed the alley north of Walnut Street, between Washington Street and Central Avenue, and included approximately 15,000 square feet of pavement removal and replacement, two new concrete alley approaches, installation of 550 lineal feet of concrete valley gutter, installation of storm drain system improvements, and other incidental and related work; and WHEREAS, the final cost of the contract was $440,913.54 and was completed in substantial conformance with the specifications approved by City Council; and WHEREAS, there were two change orders totaling $41,004.54; and WHEREAS, Council action to award the contract limited the City Manager's change order authority to $40,000, and staff is requesting Council ratify the additional $1,004.54 expenditure that exceeded the $40,000 limit; and WHEREAS, staff recommends ratifying expenses and authorizing the City Manager to execute change orders to Alley Improvement Project — Phase 9 in the amount of $1,004.54. NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby ratify expenses and authorize the City Manager to execute change orders to Alley Improvement Project — Phase 9 in the amount of $1,004.54; and BE IT FURTHER RESOLVED, pursuant to Section 6.3q of the City Council Protocol Manual (adopted 11/6/19, Resolution No. 2019-223), the City Attorney is hereby authorized to make minor revisions to the above -referenced document(s) that do not alter the compensation or term, and to make clerical corrections as necessary. Dated: May 17, 2023 I hereby certify that Resolution No. 2023-90 was passed and adopted by the City Council of the City of Lodi in a regular meeting held May 17, 2023 by the following votes: AYES: COUNCIL MEMBERS — Bregman, Craig, Nakanishi, Yepez, and Mayor Hothi NOES: COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS — None ABSTAIN: COUNCIL MEMBERS — None PAMELA M. FARRIS Assistant City Clerk 2023-90