AGENDA ITEM C 0 (P
COUNCIL COMMUNICATION
AGENDA TITLE: Adopt Resolution Ratifying Expenses and Authorizing City Manager to Execute Change
Orders to Alley Improvement Project — Phase 9 ($1,004.54) and Accept Improvements
Under Contract for Alley Improvement Project — Phase 9
MEETING DATE: May 17, 2023
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt Resolution Ratifying Expenses and Authorizing City Manager to
Execute Change Orders to Alley Improvement Project — Phase 9
($1,004.54) and Accept improvements under contract for Alley Improvement
Project — Phase 9
BACKGROUND INFORMATION: The City has reconstructed various alleys over the past 10 years. The
projects have typically included between one and two alleys per year,
depending on funding levels. Specific projects are selected based on a
citywide alley condition assessment list and are rated based on pavement condition and drainage improvement
needs.
This project reconstructed the alley north of Walnut Street, between Washington Street and Central Avenue, as
shown on Exhibit A. The project included approximately 15,000 square feet of pavement removal and
replacement, two new concrete alley approaches, installation of 550 lineal feet of concrete valley gutter,
installation of storm drain system improvements, and other incidental and related work, all
as shown on the plans and specifications for the above project.
The final cost of the contract was $440,913.54 and was completed in substantial conformance with the
specifications approved by City Council. There were two change orders totaling $41,004.54. Since the Council
action to award the contract limited City Manager change order authority to $40,000, staff is requesting Council
ratify the additional $1,004.54 expenditure that exceeded the $40,000 limit.
Change Order 1 ($21,716.79) included costs due to expended time and materials work required to address an
existing water line, which was installed more shallow than shown on the as built plans. This condition required
several final paving modifications. The original contract was 40 days; 27 calendar days were added to make
the necessary adjustments.
Change Order 2 ($19,287.75) was an internal change order in unit item quantities to account for additional
paving and gutter length to accommodate the adjusted grades. The contract was completed prior to the
adjusted contract completion date. Photos of completed work are shown in Exhibit B.
APPROVED.sr,•,, r. E M,, s.an7.:1i,3:rn, "
Stephen Schwabauer, City Manager
\\cvcfi lv02\pu bwks$\WP\PROJ ECTS\STR EETS\Al ley Improvements Phase 9 (2021)\CRatC0Accept1.docx
5/4/2023
Adopt Resolution Ratifying Expenses and Authorizing City Manager to Execute Change Orders to Alley Improvement Project — Phase 9 ($1,004.54) and Accept
Improvements Under Contract for Alley Improvement Project— Phase 9
February 15, 2023
Page 2
Following acceptance by the City Council, as required by law, the City Engineer will file a Notice of Completion
with the County Recorder's office. The notice serves to notify vendors and subcontractors that the project is
complete and begins their 30 -day period to file a stop notice requiring the City to withhold payments from the
prime contractor in the event of a payment dispute.
FISCAL IMPACT: The project will reduce maintenance costs in the reconstructed alleys.
FUNDING AVAILABLE: This project was funded by 2020/21 Community Development Block Grant funds
($538,147)
CE�22
Charles E. Swimley, Jr.
Public Works Director
Prepared by Jim! Billigmeier, Associate Civil Engineer
CES/AB/CD
Attachments
cc: CDBG Program Specialist
\\cvcfilv02\pubwks$\wP\PROJECTS\STREETS\Alley Improvements Phase 9 (2021)\CRatCOAcceptl.docx 5/4/2023
2021/22 Alley Improvement Project - Phase 9
Exhibit A
9
Oak St.
'a
Walnut St. Walnut St.
Legend
Project Location Boundary
/" h-Rho,
0 50 100
Feet
200
Alley Improvement Contract — Phase 9
EXHIBIT B
Before After
RESOLUTION NO. 2023-90
A RESOLUTION OF THE LODI CITY COUNCIL RATIFYING EXPENSES AND
AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDERS TO
ALLEY IMPROVEMENT PROJECT — PHASE 9
WHEREAS, this project reconstructed the alley north of Walnut Street, between
Washington Street and Central Avenue, and included approximately 15,000 square feet of
pavement removal and replacement, two new concrete alley approaches, installation of
550 lineal feet of concrete valley gutter, installation of storm drain system improvements, and
other incidental and related work; and
WHEREAS, the final cost of the contract was $440,913.54 and was completed in
substantial conformance with the specifications approved by City Council; and
WHEREAS, there were two change orders totaling $41,004.54; and
WHEREAS, Council action to award the contract limited the City Manager's change
order authority to $40,000, and staff is requesting Council ratify the additional $1,004.54
expenditure that exceeded the $40,000 limit; and
WHEREAS, staff recommends ratifying expenses and authorizing the City Manager to
execute change orders to Alley Improvement Project — Phase 9 in the amount of $1,004.54.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby ratify
expenses and authorize the City Manager to execute change orders to Alley Improvement
Project — Phase 9 in the amount of $1,004.54; and
BE IT FURTHER RESOLVED, pursuant to Section 6.3q of the City Council Protocol
Manual (adopted 11/6/19, Resolution No. 2019-223), the City Attorney is hereby authorized to
make minor revisions to the above -referenced document(s) that do not alter the compensation
or term, and to make clerical corrections as necessary.
Dated: May 17, 2023
I hereby certify that Resolution No. 2023-90 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held May 17, 2023 by the following votes:
AYES: COUNCIL MEMBERS — Bregman, Craig, Nakanishi, Yepez, and
Mayor Hothi
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
PAMELA M. FARRIS
Assistant City Clerk
2023-90