AGENDA TITLE: Adopt Resolution Awarding Contract for Hale Park Parking Lot Reconstruction to Tosted
Asphalt, Inc., of Fresno ($81,520) and Authorizing City Manager to Execute Change
Orders ($30,000)
MEETING DATE: February 15, 2023
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt resolution awarding contract for Hale Park Parking Lot Reconstruction
to Tosted Asphalt, Inc., in the amount of $81,520 and authorizing City
Manager to execute change orders in an amount not -to -exceed $30,000.
BACKGROUND INFORMATION: This project consists of reconstructing the parking lot at Hale Park. The
work includes replacing approximately 8,000 square feet of parking lot
pavement, reconstructing a driveway approach, installing two
handicap -accessible parking stalls, replacing miscellaneous concrete, and other incidental and related work.
The existing parking lot pavement is severely cracked, settled and potholed due to the age of the pavement.
The cracks have allowed water to seep into the pavement subgrade, causing the pavement to fail.
The specifications for this project were approved on July 20, 2022. The City received the following bids for this
project on December 28, 2022:
The lowest bid came in much lower than the engineer's estimate and what was budgeted. With the available
funding, Staff proposes to expand the scope of work to make the curb ramp at the corner ADA compliant,
Stephen Schwabauer, City Manager
\\cvcfilv02\pubwks$\WP\PROJECTS\PARKS\Hale Park\2022 Parking Lot Reconstruction\CAward docx 2/1/2023
Above/(Below)
Bidder
Location
Bid
Engineer's Estimate
Engineer's Estimate
$230,762.00
Tosted Asphalt, Inc.
Fresno
$81,519.60
($ 48,155.40)
A.M. Stephens Construction
Lodi
$110,747.80
($ 18,927.20)
Hensley's Paving & General
Waterford
$113,314.00
($ 16,361.00)
Sierra Asphalt, Inc.
Rancho Cordova
$116,121.00
($ 13,554.00)
Consolidated Engineering
Valley Spring
$116,950.00
($ 12,725.00)
Garcia Paving Inc.
Fresno
$124,785.69
($ 4,889.31)
Robert Burns Construction
Stockton
$131,183.01
$ 1,508.01
Arrow Construction
Sacramento
$136,326.00
$ 6,651.00
United Pavement Maintenance
Hughson
$149,878.00
$ 20,203.00
E.E. Gilbert Construction
Martinez
$158,858.90
$ 29,183.90
FBD Vanguard Construction
Livermore
$161,558.00
$ 31,883.00
B & M Builders, Inc.
Rancho Cordova
$172,230.00
$ 42,555.00
The lowest bid came in much lower than the engineer's estimate and what was budgeted. With the available
funding, Staff proposes to expand the scope of work to make the curb ramp at the corner ADA compliant,
Stephen Schwabauer, City Manager
\\cvcfilv02\pubwks$\WP\PROJECTS\PARKS\Hale Park\2022 Parking Lot Reconstruction\CAward docx 2/1/2023
Adopt Resolution Awarding Contract for Hale Park Parking Lot Reconstruction to Tosted Asphalt, Inc, of Fresno ($81,520), Authorizing City Manager to Execute Change
Orders ($30,000)
February 15, 2022
Page 2
installing thermoplastic parking striping instead of paint, and fixing the drainage issues in the gutter.
Consistent with all projects, contingency is required to address any unforeseen issues.
Staff received a bid advisory against the contractor from the Foundation of Fair Contracting and from Norcal
Industry Compliance. In general, the claims are centered around failure to comply with the bid specifications
resulting in an unfair competitive advantage. Both staff and the City's labor compliance consultant have
reviewed their complaints and have found that none of them have any basis.
Staff recommends adopting resolution awarding Contract for Hale Park Parking Lot Reconstruction to Tosted
Asphalt, Inc., of Fresno, in the amount of $81,520 and authorizing City Manager to execute change orders in
an amount not -to -exceed $30,000.
FISCAL IMPACT: This project does not impact the General Fund.
FUNDING AVAILABLE: This project is funded by 2022/23 CDBG funds:
CDBG-23001.Contracts: $170,000
CDBG-23001.lntLabor:3$ 6,000
TOTAL: $206,000
Andrew Keys
Andrew Keys
Deputy City Manager/Internal Services Director
0Q� ("). n
Charles E. Swim€ey, Jr.
Public Works Director
Prepared by Alice Bernardino, Associate Civil Engineer
CES/AB/cd
Attachments
cc: Parks Project Coordinator
PRCS Director, Jaromay
\\cvcfilv02\pubwks$\WP\PROJECTS\PARKS\Hale Park\2022 Parking Lot Reconstruction\CAward.docx 2/1/2023
2022 HALE PARK PARKING LOT RECONSTRUCTION
209 E LOCUST ST CONTRACT
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein referred
to as the "City," TOSTED ASPHALT, INC., a California corporation, herein referred to as the
"Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by this
reference, to -wit:
Notice Inviting Bids
Information to Bidders
Certifications and Forms
General Provisions
Federal Requirements
Special Provisions
Bid Proposal
Contract
Contract Bonds
Federal Minimum Wage Rates
Plans
Addenda
The 2018 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
City of Lodi Construction Specifications
All of the above documents, sometimes hereinafter referred to as the "Contract Documents," are
intended to cooperate so that any work called for in one and not mentioned in the other is to be
executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees with
the City, at Contractor's cost and expense, to do all the work and furnish all the materials except
such as are mentioned in the specifications to be furnished by the City, necessary to construct
and complete in a good workmanlike and substantial manner and to the satisfaction of the City
the proposed improvements as shown and described in the Contract Documents which are
hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractor to provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts to
pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division 2
of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing wage
rate and other employer payments for health and welfare, pension, vacation, travel time, and
CONTRACT 4.1 01/12/23
subsistence pay, apprenticeship or other training programs. The responsibility for compliance
with these Labor Code requirements is on the prime contractor.
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for all
risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
This project consists of reconstructing the parking lot at Hale Park. The work includes replacing
approximately 8,000 square feet of parking lot pavement, constructing a driveway approach,
installing two handicap -accessible parking stalls, replacing miscellaneous concrete, and other
incidental and related work.
For additional bid item descriptions refer to Section 6-07 "Description of Bid Items
CONTRACT ITEMS
Item
Description
Mobilization and Temporary
Qty
Unit
Unit Price
Total
$ 2,500.00
1
1
LS
$ 2,500.00
Facilities, and Demobilization
$ 7,500.00
2
Demolition, Clearing, Grubbing,
1
LS
$ 7,500.00
and Gradin
3
Pavement Reconstruction
8,000
SF
$ 3.95
$ 30,000.00
4
Driveway Reconstruction
165
SF
$ 63.63
$ 10,500.00
5
Concrete ADA Parking Stall
380
SF
$ 25.00
$ 9,500.00
6
Miscellaneous Concrete
705
SF
$ 9.93
$ 7,000.00
7
Swing Gate Fabrication and
1
LS
$10,000.00 $ 10,000.00
Installation
8
Striping and Signage
1LS
$ 4,500.00 $ 4,500.00
TOTAL $ 81,500.00
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the provisions
of Section 3700 of the Labor Code, which requires every employer to be insured against liability
for workers' compensation or to undertake self-insurance in accordance with the provisions of
that code, and I will comply with such provisions before commencing the performance of the work
of this contract.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should there
be any conflict between the terms of this instrument and the Bid Proposal of the Contractor, then
this instrument shall control and nothing herein shall be considered as an acceptance of the said
terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to establish
lines and grades for the work as specified under the Special Provisions. All labor or materials not
mentioned specifically as being done by the City will be supplied by the Contractor to accomplish
the work as outlined in the specifications.
CONTRACT 4.2 01/12/23
ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract within 15
calendar days after the City Manager has executed the contract and to diligently prosecute to
completion within 30 CALENDAR DAYS.
ARTICLE IX - State of California Senate Bill 854 requires the following:
No contractor or subcontractor may be listed on a bid proposal for a public works project
unless registered with the Department of Industrial Relations pursuant to Labor Code
section 1725.5 [with limited exceptions from this requirement for bid purposes only under
Labor Code section 1771.1(a)].
No contractor or subcontractor may be awarded a contract for public work on a public
works project unless registered with the Department of Industrial Relations pursuant to
Labor Code section 1725.5.
This project is subject to compliance monitoring and enforcement by the Department of
Industrial Relations.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE DEDUCTED
FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR:
0
Title
(CORPORATE SEAL)
CITY OF LODI, a municipal corporation
By:
STEPHEN SCHWABAUER
City Manager
Date:
Attest:
OLIVIA NASHED
City Clerk
Approved As To Form
JANICE D. MAGDICH
City Attorney
CONTRACT 4.3 01/12/23
RESOLUTION NO. 2023-29
A RESOLUTION OF THE LODI CITY COUNCIL AWARDING THE CONTRACT
FOR HALE PARK PARKING LOT RECONSTRUCTION TO
TOSTED ASPHALT, INC., OF FRESNO; AND FURTHER AUTHORIZING
THE CITY MANAGER TO EXECUTE CHANGE ORDERS
WHEREAS, this project consists of reconstructing the parking lot at Hale Park which
includes replacing approximately 8,000 square feet of parking lot pavement, reconstructing a
driveway approach, installing two handicap -accessible parking stalls, replacing miscellaneous
concrete, and other incidental and related work; and
WHEREAS, specifications for this project were approved on July 20,
2022. The City
received the following bids for this project on December 28, 2022:
Above/(Below)
Bidder
Location
Bid
Estimate
Tosted Asphalt, Inc.
Fresno
$81,519.60
($ 48,155.40)
A.M. Stephens Construction
Lodi
$110,747.80
($ 18,927.20)
Hensley's Paving & General
Waterford
$113,314.00
($ 16,361.00)
Sierra Asphalt, Inc.
Rancho Cordova
$116,121.00
($ 13,554.00)
Consolidated Engineering
Valley Spring
$116,950.00
($ 12,725.00)
Garcia Paving, Inc.
Fresno
$124,785.69
($ 4,889.31)
Robert Burns Construction
Stockton
$131,183.01
$ 1,508.01
Arrow Construction
Sacramento
$136,326.00
$ 6,651.00
United Pavement Maintenance
Hughson
$149,878.00
$ 20,203.00
E.E. Gilbert Construction
Martinez
$158,858.90
$ 29,183.90
FBD Vanguard Construction
Livermore
$161,558.00
$ 31,883.00
B & M Builders, Inc.
Rancho Cordova
$172,230.00
$ 42,555.00
WHEREAS, staff recommends awarding the contract for Hale Park Parking Lot
Reconstruction to Tosted Asphalt, Inc., of Fresno, in the amount of $81,520 and authorizing the
City Manager to execute change orders in an amount not to exceed $30,000.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award
the contract for Hale Park Parking Lot Reconstruction to the low bidder, Tosted Asphalt, Inc., of
Fresno, California, in the amount of $81,520; and
BE IT FURTHER RESOLVED that the Lodi City Council does hereby authorize the
City Manager to execute the contract and change orders in an amount not to exceed $30,000;
and
BE IT FURTHER RESOLVED, pursuant to Section 6.3q of the City Council Protocol
Manual (adopted 11/6/19, Resolution No. 2019-223), the City Attorney is hereby authorized to
make minor revisions to the above -referenced document(s) that do not alter the compensation
or term, and to make clerical corrections as necessary.
Dated: February 15, 2023
I hereby certify that Resolution No. 2023-29 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held February 15, 2023 by the following votes:
AYES: COUNCIL MEMBERS — Bregman, Craig, Khan, Nakanishi, and
Mayor Hothi
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN. COUNCIL MEMBERS — None
OLIVIA NASHED
City Clerk
2023-29
Pamela Farris
From: Kristyn Pair
Sent: Friday, February 10, 2023 9:39 AM
To: City Council
Cc: Dina Morsi; Debbie Terry
Subject: Agenda Item - Hale Park Parking Lot Reconstruction
Good morning,
I have reviewed the posted City Council agenda regarding the upcoming meeting on February 15, 2023.
1 see that the award for the Hale Park Parking Lot Reconstruction project is still set to be awarded to Tosted
Asphalt, Inc.
I trust the City has done its due diligence in looking at the requirements of the project , which may include the
need for the use of heavy equipment (i.e. Skid steers, skip loaders, paving machines, and rollers), therefore
requiring the employ of operating engineers. I would, however, like to ask that City supply me with their
findings that show this contractor will, in fact, be able to perform this scope of work without the use of heavy
equipment. I request any communications to or from city staff or their labor compliance consultant regarding
this project in relation to the bid advisories received by the Foundation for Fair Contracting or NorCal
Construction Industry Compliance be sent to me for review.
I understand the City believes there is no issue with compliance regarding this bid, however, due to the scope
of work, comparisons of other projects of this size and type, as well as the findings outlined in our bid advisory
dated January 27, 2023, we ask that City of Lodi further assess and reconsider the award of the project.
Thank you for your time,
Xristyn Pair
Central Compliance Agent
NorCal Construction Industry Compliance (NCIC), LMCC
Cell: (559) 660-2961
P.O. Box 340596
Sacramento, CA 95834
r-2
NCIC
This message contains confidential information and is intended only for the individual named. If you are not the named addressee
you should not disseminate, distribute or copy this e-mail. Please notify the sender immediately by e-mail if you have received this
e-mail by mistake and delete this e-mail from your system. If you are not the intended recipient you are notified that disclosing,
copying, distributing or taking any action in reliance on the contents of this information is strictly prohibited.