AGENDA TITLE: Adopt a Resolution Awarding the Contract for the Lodi Station Parking Structure,
50 North Sacramento Street, to F & H Construction ($6,724,000); and Appropriate
$7,017,000 for the Project
MEETING DATE: March 21, 2001
PREPARED BY: Public Works Director
RECOMMENDED ACTION: That the City Council adopt a resolution awarding the contract for the above project to
F & H Construction, of Stockton, in the amount of $6,724,000 (base bid plus
Alternates #1 and #2); and appropriate funds in accordance with the recommendation
shown below.
BACKGROUND INFORMATION: The Final Environmental Assessment for the Lodi Station Parking Structure
and amendment to the Federal Transportation Improvement Program
(FTIP) are the last requirements that must be met prior to contract award.
The 30 day review period of the Final Environmental Assessment and the
FTIP amendment ends on March 21, 2001. FTA is scheduled to issue a Finding of No Significant Impact (FONSI)
on March 21, 2001. We anticipate those actions will be completed by that time. If they are delayed, staff will update
Council at the meeting.
This project consists of a three (3) level parking structure (120,000± square feet, 329 cars): one (1) at ground level
and two (2) levels above ground; ground level retail/office space (15,000± square feet); associated electrical,
mechanical, utility, site preparation and landscape work; curb gutter and sidewalks; and demolition and replacement
Of Sacramento Street from Pine to Elm.
Plans and specifications for this project were approved on July 19, 2000. The bid included two alternates: Alternate 1
was for the decorative metalwork on the east side of the structure; and Alternate 2 was for removal of the abandoned 8 -
inch water line along Sacramento Street. Staff is recommending we accept the base bid plus both alternates at this time.
The City received the following five bids for this project:
Bidder
Location
Base Bid
Alternate 1
Alternate 2
Engineer's Estimate
$5,000,000
F & H Construction
Stockton
$6,651,000
$ 63,000
$10,000
Allen L. Bender, Inc.
West Sacramento
$6,715,972
$109,212
$10,295
C. T. Brayton & Sons, Inc.
Escalon
$6,912,750
$ 65,000
$ 2,000
McCarthy Building Co., Inc.
Roseville
$6,944,390
$ 75,000
$12,000
John F. Otto, Inc.
Sacramento
$7,561,652
$ 65,000
$11,000
REQUESTED APPROPRIATION:
Construction Contract $6,724,000
Contingency $ 293,000
Total Appropriation Requested $7,017,000
APPROVED: 50- IF -41 LV
H. Dixon Flynn -- City Manager
CAWARD
03/15/01
Adopt a Resolution Awarding the Contract for the Lodi Station Parking Structure,
50 North Sacramento Street, to F & H Construction ($6,724,000); and Appropriate $7,017,000 for the Project
March 21, 2001
Page 2
FUNDING: FTA Funds
$2,806,681
SJVAPCD REMOVE Funds
$ 317,000
Measure K Grant Funds
$2,926,600
Measure K Streets Fund
$ 167,845
Electric Utility
$ 115,500
Public Works/Water Funds
$ 165,750
TDA Funds
$ 517,624
TOTAL
$7,017,000
Bid Opening Date: December 14, 2000
Funding Available:
Vicky McAthie, F' a Direct r
Richard C. Prima, Jr.
Public Works Director
Prepared by Gary Wiman, Project Manager
RCP/GW/pkh
cc: Randy Hays, City Attorney
Joel Harris, Purchasing Officer
Carlos Tobar, Transportation Manager
Rad Bartlam, Community Development Director
CAWARD
RESOLUTION NO. 2001-73
A RESOLUTION OF THE LODI CITY COUNCIL AWARDING
THE CONTRACT FOR THE LODI STATION PARKING
STRUCTURE, AND FURTHER APPROPRIATING
FUNDS TO COVER THE PROJECT
WHEREAS, in answer to notice duly published in accordance with law and the
order of this City Council, sealed bids were received and publicly opened on December
14, 2000 at 2:00 p.m. for Lodi Station Parking Structure, 50 North Sacramento Street,
and further described in the specifications therefore approved by the City Council on July
19, 2000; and
WHEREAS, said bids have been compared, checked, and tabulated and a report
thereof filed with the City Manager as follows:
The City received the following five bids for this project:
Bidder
Location
Base Bid
Alternate 1
Alternate 2
Engineer's Estimate
Measure K Street Funds
$5,000,000
Electric Utility
$ 115,500
Public Works/Water Funds
$ 165,750
F & H Construction
Stockton
$6,651,000
$
63,000
$
10,000
Allen L. Bender, Inc.
West Sacramento
$6,715,972
$ 109,212
$
10,295
C. T. Brayton & Sons
Escalon
$6,912,750
$
65,000
$
2,000
McCarthy Building Co.
Roseville
$6,944,390
$
75,000
$
12,000
John F. Otto, Inc.
Sacramento
$7,561,652
$
65,000
$
11,000
WHEREAS, staff recommends awarding the contract (base bid plus Alternates
#1 and #2) for Lodi Station Parking Structure, 50 North Sacramento Street to the low
bidder, F & H Construction, of Stockton, CA.
NOW, THEREFORE, BE IT RESOLVED, that the Lodi City Council does hereby
award the contract, consisting of the base bid plus Alternates #1 and #2, for the Lodi
Station Parking Structure, 50 North Sacramento Street, as of March 23, 2001 to F & H
Construction, of Stockton, CA, the low bidder, in the amount of $6,724,000; and
BE IT FURTHER RESOLVED that funds be appropriated as follows:
FTA
$2,806,681
SJVAPCD REMOVE Funds
$ 317,000
Measure K Grant Funds
$2,926,600
Measure K Street Funds
$ 167,845
Electric Utility
$ 115,500
Public Works/Water Funds
$ 165,750
TDA Funds
$ 517,624
TOTAL
$7,017,000
Dated: - March 21, 2001
-------------------------------------------------------------------
--------------------------------------------------------------------
I hereby certify that Resolution No. 2001-73 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held March 21, 2001, by the following
vote:
AYES: COUNCIL MEMBERS — Hitchcock, Howard, Land, Pennino and
Mayor Nakanishi
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
SUSAN J. BLACKSTON
City Clerk
2001-73