HomeMy WebLinkAboutAgenda Report - December 21, 2022 C-04CITY OF
100 10 zt�
mss+
C A L I FORN IA
AGENDA ITEM
C•4
COUNCIL COMMUNICATION
AGENDA TITLE: Approve Plans and Specifications and Authorize Advertisement for Bids for Lodi Station
Parking Garage Repair Project
MEETING DATE: December 21, 2022
PREPARED BY: Public Works Director
RECOMMENDED ACTION Approve plans and specifications and authorize advertisement for bids for
Lodi Station Parking Garage Repair Project.
BACKGROUND INFORMATION: The Lodi Station Parking Garage, located at 50 North Sacramento Street,
was constructed in 2002, using post -tensioned concrete. In June of 2022,
a vehicle hit the concrete wall barrier on the third floor of the parking
structure and cause extensive damage to the barrier and the concrete floor. Staff hired Walker Consultants, of
San Francisco to conduct a structural assessment of the extent of the damage. Walker Consultants is the
original structural designer of the parking structure and has extensive post -tension structure experience. The
assessment report indicated the damage does not cause any structural issues to the parking structure but
recommended the area remain fenced off until repairs are complete (Exhibit A).
This project includes the replacement of the damaged concrete barrier, reset the post -tension steel cable; and
other incidental and related work as shown on the plans and specifications of the project.
The plans and specifications are on file in the Public Works Department. The planned bid opening date is
February 1, 2021. The project estimate is $125,000.
Staff recommends Council approve plans and specifications and authorize advertisement for bids for Lodi
Station Parking Garage Repair Project.
FISCAL IMPACT: The repair is necessary to repair the vehicle damage to the existing structure and
to avoid additional, future damage if the repairs are not addressed. This project
does not impact the General Fund.
FUNDING AVAILABLE: To be identified with the project award
a -Jac
Charles E. Swimley, Jr
Public Works Director
Prepared by Lyman Chang, City Engineer/Deputy Public Works Director
CES/LC/cd
Attachment
cc: Public Works Management Analyst
Facilities Superintendent
Transportation Manager
APPROVED: IJV XWqbJ
Stephen Schwabauer, City Manager
\\cvcfilv02\pubwks$MP\PROJECTS\TRANSIT\Lodi Station Parking Structure\2022 Structural Repair\CPSA doc 12/5/2022
WALKER
CONSULTANTS
October 11, 2022
Mr. Lyman Chang
City Engineer/Deputy Public Works Director
City of Lodi
221 W. Pine Street
Lodi, CA 95240
Re: Structural Investigation and Repair for Lodi Station Parking Structure
50 N. Sacramento Street, Lodi, CA
Dear Mr. Chang,
135 Main Street, Suite 1030
San Francisco, CA 94105
Office: 415.644.0630
Fax: 415.644.0637
www.walkerparking.com
Walker Parking Consultants is pleased to submit for your review this letter report for the Structural
Investigation/Repair of damaged concrete barrier wall at the Lodi Station Parking Structure.
Background and Description
The Lodi Station Parking Structure is a 3 -level post -tensioned concrete parking structure. The lateral
system for the parking structure consists of special reinforced concrete shear walls. At the perimeter of
the building concrete crash barrier walls are provided to prevent cars from accidentally falling off the edge
of the garage. Metal screens were provided for aesthetics reason.
One of the concrete barrier walls on the north side was hit by a car causing severe damage to the wall.
The City of Lodi desires to restore the concrete barrier wall.
DISCUSSION
The following documents were provided to Walker Parking Consultants in order to assess the extent of
the damage and feasibility of repairing and restoring the concrete barrier.
Record drawings for Lodi Station Parking Structure prepared by Gordon H. Chong and Partners
June 29, 2000. Walker Consultants was the structural engineer for the project.
Based on the drawing date, the project was designed to the California Building Code 1998 Edition. CBC
1998 required the barrier walls to be designed for a load of 6000 lbs acting at a height of 18 inches above
the floor. The current edition of the California Building Code, CBC 2019, requires the wall to be designed
for 6000 lbs but acting at 18" or 27", non -currently, above the floor.
WALKER
CONSULTANTS
OBSERVATIONS and FINDINGS
Edward Y.C. Tan visited the site on August 24, 2022, to assess the damage on the barrier wall.
The following observations were made:
The damaged concrete barrier wall is on the third level, east side of the garage. The barrier wall suffered
extensive damage (see Photo 1). The barrier wall was hit with a force that caused the wall to shear off
from the edge of the slab (see Photo 2). The Code required barrier load is based on a car travelling at 5
MPH. The car that hit the wall was going at a speed far greater than the Code assumed speed.
The hooks for the wall vertical bars were pulled out. These caused spalling of the concrete cover on the
inside face of the wall (see Photo 3). In some areas, the concrete at the base of wall fell off.
The main slab post -tensioning cables were exposed due to spalling of the concrete cover but were not
damaged (see Photo 4). The anchors for the temperature cables running perpendicular to slab edge were
exposed in two areas, at the middle of the slab edge and close to the east edge (see Photo 5). The
concrete at the anchors spalled causing the anchors to move. These anchors will need to be re -seated.
The barrier wall has been displaced from its original location. There are a few of the vertical bars still
attached to the concrete slab. The wall is leaning out and has pushed the metal screen. The metal screen
is slightly bowed and pushed out (see Photo 6).
CODE REQUIREMENTS
The parking structure was designed and built in 2000. CBC 1998, the governing code at that time,
required the barrier walls to be designed for a load of 6000 lbs. The current Code, CBC 2022 requires
the same load but needs to be checked for two conditions. The load acting at 18" above the floor and at
27" above the floor. The replacement wall will be designed to these loading conditions.
In new construction, the barrier wall vertical bars will be anchored into the concrete slab. Since the slab
is existing, the vertical bars will be doweled into the concrete slab by drilling into the slab and anchoring
the vertical bars with epoxy. Since the slab edge has had damaged, and new holes need to be dilled for
the wall vertical bars, it would be prudent to provide a redundancy to the wall's structural strength. It is
recommended that the wall, also be designed to resist the barrier load, spanning horizontally between
columns. Added horizontal reinforcement be provided, to resist the load and the walls be provided with
clip angles at the ends.
WALKER
CONSULTANTS
Conclusion
Based on our observation the damage cause by the collision is limited to the barrier wall and the slab
edge supporting it. The structural integrity of the concrete deck and the remaining portion of the existing
parking structures has not been compromised. The repair work would be limited to the affected area only.
We hope that this has addressed your concern. If you have any questions or need further clarification,
please give us a call and we will gladly have a discussion with you.
Very truly yours,
WALKER CONSULTANTS
onu
Y �
4� 0A t'A
S 4666
* 06.30.23
\ OF CALl��
WALKER
CONSULTANTS
Photo 1 — Damage to wall
F;,no►"
By L
pRp. 1379 1 .FG91
r
Photo 2 — Wall sheared off from slab edge
WALKER
CONSULTANTS
F gyDIIJ
L
ORD.
1379 1' .EC 91
Photo 3 — Spalling of concrete cover
WALKER
CONSULTANTS
Photo 4 — Exposed main slab PT cables
Photo 5 — Temperature cable anchors
WALKER
CONSULTANTS
Photo 6 — Bowed metal screen