AGENDA ITEM C ~ 21
COUNCIL COMMUNICATION
AGENDA TITLE: Adopt Resolution Authorizing Additional Appropriation of Funds to Substation Intrusive
Maintenance Capital Improvement Project for Fiscal Year 2023 ($322,000)
MEETING DATE: October 19, 2022
PREPARED BY: Electric Utility Director
RECOMMENDED ACTION. Adopt a resolution authorizing the additional appropriation of funds to the
Substation Intrusive Maintenance Capital Improvement Project for Fiscal Year
2023 in the amount of $322,000.
BACKGROUND INFORMATION: Lodi Electric Utility's (LEU) Industrial Substation Is undergoing a relay
modernization for all 60kV relay devices and components. Industrial Substation's
60kV incoming and outgoing sub -transmission lines provide power to all of Lodi.
In April 2022, City Council approved an agreement with Schweitzer Engineering Laboratories, Inc. (SEL) to complete full
relay replacement at Industrial Substation (60kV) due to protection and coordination deficiencies between PG&E and
LEU, end -of -life relays, device standardization and modernization, and power transmission reliability.
LEU is proposing to use Substation Technicians to simultaneously replace wiring between the 60kV circuit breakers and
the relay control house. Existing wiring is nearing end -of -life at 30 years or older, with Issues arising during both wet and
dry seasons. Upgrading the wiring will provide additional reliability, in addition to replacement of all relays.
Coordination between SEL and LEU staff will result in synchronized replacement of all 60kV relays and circuit breaker
wiring, with commission testing to be performed once to prove out all replaced components. Delay of wiring replacement
will cause rellablllty Issues for Lodi's sub -transmission system.
While this work will be completed in coordination with the Substation Relay Modernization Project, wire replacement work
to be performed by LEU staff falls under the Substation Intrusive Maintenance Project. The current budget for this project
totals $20,000. With the additional $322,000 needed for the proposed wire replacement, the revised project budget for
the Substation Intrusive Maintenance Project will total $342,000 for Fiscal Year 2023.
FISCAL IMPACT: This portion of the project is estimated to cost $322,000.
FUNDING AVAILABLE: Staff are requesting an appropriation of funds in the amount of $322,000 from Fund 501
to 501990000.77020 (EUCP-23001).
lJ1_
Andrew Keys
Deputy City Manager/Internal Services Director
o
Jeff Berkheimer
Electric Utility Director
APPROVED: a/r_
Stephen Schwabauer, City Manager
Capital Improvement Program - Maintenance
FY 2022-2023
Maintenance Project Title: Substation Intrusive Maintenance Work Munis Project Code: EUCP-23001
#245
Section I:Description District Nos: Citywide Project Length Ongoing Priority
Normal
Substation maintenance including but not limited to: substation power transformer testing; DGA oil testing for power transformers and load tap changers (LTCs) and materials/equipment not covered
or tracked as part of a specific project. Also provides for LTC testing in year five (5) of the cycle.
Justification/factor driving project
Provides funding for a five (5) year cycle on substation power transformer testing from an outside vendor. Provides more accurate tracking and record keeping for annual reports and maintenance
records. Will provide critical information on transformer condition and lifespan for furure replacement planning. Provides for a five (5) year cycle of LTC inspections.
Additional Information
Provides a schedule for complete testing of two (2) substation power transformers per year for four (4) years and a year of reprieve. (With the exception of Killelea Bank #2, which can be tested or
run to failure if desired.) Year five (5) of the cycle can be utilized for LTC inspections. FY 23 includes an additional $322K appropriated by Council to replace the wiring between between the 60kV
Section II Estimated Project Costs
Expenditure
Internal Staff
Miscellaneous
Total Capital Costs
Prior Years
$
$
FY 21122 FY 22123 FY 23124 FY 24125 FY 25126 FY 26127 Future Yrs
Estimate Budget
$ 210,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000
$ 132,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000
4
$ - $ 342,000 $ 20,000 $ 20,000 $ 20,000 $ 20,000 $ -
Total
$ 250,000
$ 172,000
Is -
$ 422,000
Is
$ -
Section III
Funding Sources/Methods of Financing
Funding Source(s) Prior Years
501 - EU Outlay Capital Reserve Fund $
$
FY 21122 FY 22123 FY 23124 FY 24125 FY 25126 FY 26127 Future Yrs
Estimate Budget
$ 342,000 $ 20,000 $ 20,000 $ 20,000 $ 20,000
Total
$ 422,000
$ -
$ -
$ -
Total Project Financing $ -
$ - $L342,000 $ 20,000 $ 20,000 $ 20,000 1 $ 20,000 $ -
$ 422,000
RESOLUTION NO. 2022-258
A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING
APPROPRIATION OF FUNDS TO SUBSTATION INTRUSIVE MAINTENANCE
CAPITAL IMPROVEMENT PROJECT FOR FISCAL YEAR 2023
WHEREAS, Lodi Electric Utility's (LEU) Industrial Substation is undergoing a relay
modernization for all 60kV relay devices and components; and Industrial Substation's 60kV
incoming and outgoing sub -transmission lines provide power to all of Lodi; and
WHEREAS, in April 2022, City Council approved an agreement with Schweitzer
Engineering Laboratories, Inc. (SEL) to complete full relay replacement at Industrial Substation
(60kV) due to protection and coordination deficiencies between PG&E and LEU, end -of -life relays,
device standardization and modernization, and power transmission reliability; and
WHEREAS, LEU is proposing to use Substation Technicians to simultaneously replace
wiring between the 60kV circuit breakers and the relay control house as existing wiring is nearing
end -of -life at 30 years or older, with issues arising during both wet and dry seasons; and
WHEREAS, upgrading the wiring will provide additional reliability, in addition to
replacement of all relays; and
WHEREAS, coordination between SEL and LEU staff will result in synchronized
replacement of all 60kV relays and circuit breaker wiring, with commission testing to be performed
once to prove out all replaced components; and
WHEREAS, delay of wiring replacement will cause reliability issues for Lodi's sub -
transmission system; and
WHEREAS, while this work will be completed in coordination with the Substation Relay
Modernization Project, wire replacement work to be performed by LEU staff falls under the
Substation Intrusive Maintenance Project; and
WHEREAS, staff is recommending to appropriate funds in the amount of $322,000 from
Fund 501 to Account No. 50199000.77020 for said project (EUCP-23001).
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby authorize
the appropriation of funds to the Substation Intrusive Maintenance Capital Improvement Project
(EUCP-23001) for Fiscal Year 2023 in the amount of $322,000 as noted above for a total
approved budget of $342,000.
Dated: October 19, 2022
I hereby certify that Resolution No. 2022-258 was passed and adopted by the City Council
of the City of Lodi in a regular meeting held on October 19, 2022 by the following vote:
AYES: COUNCIL MEMBERS — Hothi, Khan, Kuehne, Nakanishi, and Mayor Chandler
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
�u��ID"
OLIVIA NASHED
City Clerk
2022-258