HomeMy WebLinkAboutAgenda Report - October 19, 2022 C-2104 Ccry OF A%1e?10*Z!100 Z CALL FORNIA AGENDA ITEM C ~ 21 COUNCIL COMMUNICATION AGENDA TITLE: Adopt Resolution Authorizing Additional Appropriation of Funds to Substation Intrusive Maintenance Capital Improvement Project for Fiscal Year 2023 ($322,000) MEETING DATE: October 19, 2022 PREPARED BY: Electric Utility Director RECOMMENDED ACTION. Adopt a resolution authorizing the additional appropriation of funds to the Substation Intrusive Maintenance Capital Improvement Project for Fiscal Year 2023 in the amount of $322,000. BACKGROUND INFORMATION: Lodi Electric Utility's (LEU) Industrial Substation Is undergoing a relay modernization for all 60kV relay devices and components. Industrial Substation's 60kV incoming and outgoing sub -transmission lines provide power to all of Lodi. In April 2022, City Council approved an agreement with Schweitzer Engineering Laboratories, Inc. (SEL) to complete full relay replacement at Industrial Substation (60kV) due to protection and coordination deficiencies between PG&E and LEU, end -of -life relays, device standardization and modernization, and power transmission reliability. LEU is proposing to use Substation Technicians to simultaneously replace wiring between the 60kV circuit breakers and the relay control house. Existing wiring is nearing end -of -life at 30 years or older, with Issues arising during both wet and dry seasons. Upgrading the wiring will provide additional reliability, in addition to replacement of all relays. Coordination between SEL and LEU staff will result in synchronized replacement of all 60kV relays and circuit breaker wiring, with commission testing to be performed once to prove out all replaced components. Delay of wiring replacement will cause rellablllty Issues for Lodi's sub -transmission system. While this work will be completed in coordination with the Substation Relay Modernization Project, wire replacement work to be performed by LEU staff falls under the Substation Intrusive Maintenance Project. The current budget for this project totals $20,000. With the additional $322,000 needed for the proposed wire replacement, the revised project budget for the Substation Intrusive Maintenance Project will total $342,000 for Fiscal Year 2023. FISCAL IMPACT: This portion of the project is estimated to cost $322,000. FUNDING AVAILABLE: Staff are requesting an appropriation of funds in the amount of $322,000 from Fund 501 to 501990000.77020 (EUCP-23001). lJ1_ Andrew Keys Deputy City Manager/Internal Services Director o Jeff Berkheimer Electric Utility Director APPROVED: a/r_ Stephen Schwabauer, City Manager Capital Improvement Program - Maintenance FY 2022-2023 Maintenance Project Title: Substation Intrusive Maintenance Work Munis Project Code: EUCP-23001 #245 Section I:Description District Nos: Citywide Project Length Ongoing Priority Normal Substation maintenance including but not limited to: substation power transformer testing; DGA oil testing for power transformers and load tap changers (LTCs) and materials/equipment not covered or tracked as part of a specific project. Also provides for LTC testing in year five (5) of the cycle. Justification/factor driving project Provides funding for a five (5) year cycle on substation power transformer testing from an outside vendor. Provides more accurate tracking and record keeping for annual reports and maintenance records. Will provide critical information on transformer condition and lifespan for furure replacement planning. Provides for a five (5) year cycle of LTC inspections. Additional Information Provides a schedule for complete testing of two (2) substation power transformers per year for four (4) years and a year of reprieve. (With the exception of Killelea Bank #2, which can be tested or run to failure if desired.) Year five (5) of the cycle can be utilized for LTC inspections. FY 23 includes an additional $322K appropriated by Council to replace the wiring between between the 60kV Section II Estimated Project Costs Expenditure Internal Staff Miscellaneous Total Capital Costs Prior Years $ $ FY 21122 FY 22123 FY 23124 FY 24125 FY 25126 FY 26127 Future Yrs Estimate Budget $ 210,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000 $ 132,000 $ 10,000 $ 10,000 $ 10,000 $ 10,000 4 $ - $ 342,000 $ 20,000 $ 20,000 $ 20,000 $ 20,000 $ - Total $ 250,000 $ 172,000 Is - $ 422,000 Is $ - Section III Funding Sources/Methods of Financing Funding Source(s) Prior Years 501 - EU Outlay Capital Reserve Fund $ $ FY 21122 FY 22123 FY 23124 FY 24125 FY 25126 FY 26127 Future Yrs Estimate Budget $ 342,000 $ 20,000 $ 20,000 $ 20,000 $ 20,000 Total $ 422,000 $ - $ - $ - Total Project Financing $ - $ - $L342,000 $ 20,000 $ 20,000 $ 20,000 1 $ 20,000 $ - $ 422,000 RESOLUTION NO. 2022-258 A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING APPROPRIATION OF FUNDS TO SUBSTATION INTRUSIVE MAINTENANCE CAPITAL IMPROVEMENT PROJECT FOR FISCAL YEAR 2023 WHEREAS, Lodi Electric Utility's (LEU) Industrial Substation is undergoing a relay modernization for all 60kV relay devices and components; and Industrial Substation's 60kV incoming and outgoing sub -transmission lines provide power to all of Lodi; and WHEREAS, in April 2022, City Council approved an agreement with Schweitzer Engineering Laboratories, Inc. (SEL) to complete full relay replacement at Industrial Substation (60kV) due to protection and coordination deficiencies between PG&E and LEU, end -of -life relays, device standardization and modernization, and power transmission reliability; and WHEREAS, LEU is proposing to use Substation Technicians to simultaneously replace wiring between the 60kV circuit breakers and the relay control house as existing wiring is nearing end -of -life at 30 years or older, with issues arising during both wet and dry seasons; and WHEREAS, upgrading the wiring will provide additional reliability, in addition to replacement of all relays; and WHEREAS, coordination between SEL and LEU staff will result in synchronized replacement of all 60kV relays and circuit breaker wiring, with commission testing to be performed once to prove out all replaced components; and WHEREAS, delay of wiring replacement will cause reliability issues for Lodi's sub - transmission system; and WHEREAS, while this work will be completed in coordination with the Substation Relay Modernization Project, wire replacement work to be performed by LEU staff falls under the Substation Intrusive Maintenance Project; and WHEREAS, staff is recommending to appropriate funds in the amount of $322,000 from Fund 501 to Account No. 50199000.77020 for said project (EUCP-23001). NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby authorize the appropriation of funds to the Substation Intrusive Maintenance Capital Improvement Project (EUCP-23001) for Fiscal Year 2023 in the amount of $322,000 as noted above for a total approved budget of $342,000. Dated: October 19, 2022 I hereby certify that Resolution No. 2022-258 was passed and adopted by the City Council of the City of Lodi in a regular meeting held on October 19, 2022 by the following vote: AYES: COUNCIL MEMBERS — Hothi, Khan, Kuehne, Nakanishi, and Mayor Chandler NOES: COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS — None ABSTAIN: COUNCIL MEMBERS — None �u��ID" OLIVIA NASHED City Clerk 2022-258