HomeMy WebLinkAboutAgenda Report - August 17, 2022 C-10CITY OF Zo .�t CALIFORNIA AGENDA ITEM + 10 COUNCIL COMMUNICATION AGENDA TITLE: Adopt Resolution Authorizing City Manager to Execute Amendment No. 1 to Cooperative Agreement with State of California for Proposed State Route 99/Turner Road Interchange Improvements MEETING DATE: August 17, 2022 PREPARED BY: Public Works Director RECOMMENDED ACTION: Adopt resolution authorizing City Manager to execute Amendment No. 1 to Cooperative Agreement with State of California for proposed State Route 99/Turner Road Interchange Improvements. BACKGROUND INFORMATION: Since 21018, San Joaquin Council of Governments (SJCOG), in partnership with California Department of Transportation (Caltrans), the City of Lodi, and the design consultant, Drake Haglan & Associates, Inc. have collaborated to prepare the necessary environmental clearance and design documents for constructing the State Route 99 (SR99)/Turner Road Interchange Improvements (Project). The contract between SJCOG and Drake Haglan and Associates has been expanded to provide the construction management services through project completion. The project improvements include the'const-uction of a round -a -bout located near the southerly end of the southbound Turner Road freeway off -ramp, widening Cherokee Lane (currently a one-way southbound roadway segment) into a two-way facility be -ween Pioneer Drive and Turner Road, including Class II bike lanes in both directions and sidewalk on the westerly side of the roadway. The project also includes lengthening the SR99/Turner Road Southbound on-ramp by 400 feet to provide longer acceleration distance to merge with mainline traffic. Project construction is anticipated to begin in late 2022. As a condition of project approval, Caltrans -equired the City of Lodi to enter into a Cooperative Agreement with the State of California. On October 20, 2021, Council authorized the Public Works Director to execute the initial Cooperative Agreement for the State Route 99/Turner Road Interchange Project. The Cooperative Agreement is specific to the Project and outlines the terms and conditions for constructing improvements within the State right of way. Amendment No. 1 to the initial Cooperative .agreement includes Caltrans requested changes to the funding table and language providing a mechanism -or the City to pay Caltrans for a portion of the project signal controller and cabinet that will be supplied bar Caltrans. FISCAL IMPACT: The Project ccnstruction and construction management services outlined in the Cooperati\.e Agreement will be funded through a combination of State and local funding sources managed through SJCOG. APPROVED: Steve Schwabauef Stephen Schwabauer, City Manager \\cvcfilv02\pubwks$\WP\PROJECTS\STREETS\TURNER\Turner_SR99 interchaige improvements\CC_SR99_Turner _08_17_2022 Amend No 1 coop_agreement doc 8/3/2022 Adopt Resolution Authorizing Public Works Director to Execute Amendment No. 1 to Cooperative Agreement with State of California for Proposed State Route g9/Turner Road Interchange Improvements August 17, 2022 Page 2 FUNDING AVAILABLE: Funding availability is dependent on California Transportation Commission (CTC) allocation. The allocation is expected to be considered at the September 2022 CTC meeting. To qualify for consideration, the Cooperative Agreement mt_st be executed prior to this date. Charles E. Swimley, Jr. Public Works Director CES/CES/cd Attachment \\cvcflv02\pubwks$\WP\PROJECTS\STREETS\TURNER\Turnef_SR99 interchange improvements\CC_SR99_Turner_08_17_2022 Amend No 1 coop_agreement doc 8/3/2022 Agreement 10-533 Al Project No. 1014000090 EA 10- 1 C260 10 -SJ -99- 31.1/31.6 COOPERATIVE AGREEMENT COVER SHEET Funding Summary Amendment — Funding Summary No. 02 Agreement Amendment No. 01 Work Description CITY OF LODI TO CONSTRUCT IMPROVEMENTS TO THE SOUTHBOUND STATE ROUTE -99/ TURNER ROAD INTERCHANGE Contact Information CALTRANS Allen Lao, Project Manager 1976 E. Dr. Martin Luther King Jr. Blvd. Stockton, CA 95205 Office Phone: (209) 986-5570 Email: allen.lao@ae dot.ca.gov CITY OF LODI Charles E. Swimley Jr., Public works Director 221 West Pine Street Lodi, CA 95240 Office Phone: (209) 333-6707 Email: cswimle todi. og_v Project Development Agreement 2017-02-17 (Created May 25, 2022) i Cover Sheet Table of Contents AMENDMENT No. 01 FUNDING SUMMARY No. 02 ............................. FUNDING TABLE ............................................ EXPENDITURE TABLE .................................. SPENDING SUMMARY .................................. Funding.............................................................. Invoicing and Payment ...................................... CONSTRUCTION Support .......................... CONSTRUCTION Capital ........................... Department Furnished Materials (DFM) ...... Signatures........................................................... AGREEMENT 10-533 Al Project No. 1014000090 ...........................................................................1 ...........................................................................1 ...........................................................................1 ...........................................................................2 ...........................................................................3 ...........................................................................4 ........................................................................... 5 ..........................................................................6 ...........................................................................6 ........................................................................... 6 ........................................................................... 7 Project Development Agreement 2017-02-17 (Created May 25, 2022) ii AGREEMENT 10 — 533 Al Project No. 1014000090 EA 1 C260 10 -SJ -99-31.0/31.7 AMENDMENT NO. 01 FUNDING SUMMARY NO. 02 1. PARTIES, in accordance with the provisions of this AGREEMENT, hereby amend this AGREEMENT by replacing Funding Summary No. Olin its entirety with Funding Summary No. 02. 2. Funding summary No. 2 adds RSTP funds of $641,347 and increases the SBI LPP funding from $1,629,000 to $4,729,000. Also decreasing HIP funding from $1,720,000 to $1,150,270 and decreasing the Measure K funding from $4,130,000 to $3,380,000 and removing the Local funds of $645,756. FUNDING TABLE IMPLEMENTING AGENCY CITY Source Party Fund Type CONST. SUPPORT CONST. CAPITAL Totals STA'T'E SJCOG SB 1 LPP 0 4,729,000 4,729,000 LOCAL- FEDERAL CITY Fed HIP 0 1,150,270 1,150,270 LOCAL- FEDERAL CITY RSTP 0 641.347 641,347 LOCAL CITY Measure K 1,660,617 1,487,260 3,147,877 LOCAL CITY Measure KM 0 232,123 232,123 Totals 1,660,617 8,240,000 9,900,617 mNon-federal match Project Development Agreement 2017-02-17 (Created May 25, 2022) 1 of 7 FUNDING SUMMARY No. 02 EXPENDITURE TABLE IMPLEMENTING AGENCY4 CITY Source Party Fund Type CONST. CAPITAL Eligible Ineligible STATE CALTRANS SB 1 LPP X low W-7 LOCAL- FEDERAL CITY Fed HIP X -- LOCAL- FEDERAL CITY RSTP X -- LOCAL CITY Measure K X X LOCAL CITY Measure KM X -- Note: An "X" denotes the funding type is available for payment. MNon-federal match AGREEMENT 10 — 533 A 1 Project No. 1014000090 Project Development Agreement 2017-02-17 (Created May 25, 2022) 2 of 7 FUNDING SUMMARY No. 02 AGREEMENT 10 — 533 Al Project No. 1014000090 Project Development Agreement 2017-02-17 (Created May 25, 2022) 3 of 7 SPENDING SUMMARY CONST. SUPPORT CONST. CAPITAL DFM Fund Type CALTRANS CITY CITY CALTRANS Totals SB l LPP 0 Q 4,729,000, - 0 4.729.000 Fed HIP 0 0 1,150,270 641,347 0 0 1,150,270 641,347 RSTP 0 0 Measure K 0 1,660,617 1,475,660 11,600 3,147,877 Measure K 0 0 232,123 0 232,123 Totals Q 1,660,617 8,228,400 11,600 9,900,617 AGREEMENT 10 — 533 Al Project No. 1014000090 Project Development Agreement 2017-02-17 (Created May 25, 2022) 3 of 7 FUNDING SUMMARY No. 02 Funding AGREEMENT 10 — 533 Al Project No. 1014000090 3. If there are insufficient funds available in this AGREEMENT to place the PROJECT right-of-way in a safe and operable condition, the appropriate IMPLEMENTING AGENCY will fund these activities until such time as PARTIES amend this AGREEMENT. That IMPLEMENTING AGENCY may request reimbursement for these costs during the amendment process. 4. If there are insufficient funds in this AGREEMENT to implement the obligations and responsibilities of this AGREEMENT, including the applicable commitments and conditions included in the PROJECT environmental documentation, permits, agreements, and/or approvals that are in effect at a time that WORK stops, each PARTY accepts responsibility to fund their respective WORK until such time as PARTIES amend this AGREEMENT. Each PARTY may request reimbursement for these costs during the amendment process. 5. The cost of any engineering support performed by CALTRANS includes all direct and applicable indirect costs. CALTRANS calculates indirect costs based solely on the type of funds used to pay support costs. State and federal funds administered by CALTRANS are subject to the current Program Functional Rate. All other funds are subject to the current Program Functional Rate and the current Administration Rate. The Program Functional Rate and Administration Rate are adjusted periodically. In accordance with California Senate Bill 848, the Administration Rate is capped at 10 percent until January 1, 2023, for Self -Help Counties with a countywide sales tax measure dedicated to transportation improvements. 6. If the WORK is funded with state or federal funds, any PARTY seeking CALTRANS reimbursement of indirect costs must submit an indirect cost rate proposal and central service cost allocation plan (if any) in accordance with Local Assistance Procedures Manual, 2 CFR, Part 200 and Chapter 5. These documents are to be submitted annually to CALTRANS' Audits and Investigations for review and acceptance prior to CALTRANS' reimbursement of indirect costs. 7. Travel, per diem, and third -party contract reimbursements for WORK are to be paid from the funds in this AGREEMENT only after the contractor performs the work and incurs said costs. Project Development Agreement 2017-02-17 (Created May 25, 2022) 4 of 7 AGREEMENT 10 — 533 Al Project No. 1014000090 Payments for travel and per diem will not exceed the rates paid rank and file state employees under current California Department of Human Resources (Ca1HR) rules current at the effective date of this AGREEMENT. If CITY invoices for rates in excess of CalHR rates, CITY will fund the cost difference and reimburse CALTRANS for any overpayment. 8. In accordance with the CALTRANS Federal -Aid Project Funding Guidelines, PARTIES must obtain approval from the Federal Highway Administration prior to any PROJECT funding changes that that will change the federal share of funds. 9. Notwithstanding the terms of this AGREEMENT, PARTIES agree to abide by the funding guidelines for all contributed funds that are programmed and allocated by the CTC. Invoicing and Payment 10. PARTIES will invoice for funds where the SPENDING SUMMARY shows that one PARTY provides funds for use by another PARTY. PARTIES will pay invoices within forty-five (45) calendar days of receipt of invoice when not paying with Electronic Funds Transfer (EFT). When paying with EFT, CITY will pay invoices within five (5) calendar days of receipt of invoice. 11. If CITY has received EFT certification from CALTRANS then CITY will use the EFT mechanism and follow all EFT procedures to pay all invoices issued from CALTRANS. 12. When a PARTY is reimbursed for actual cost, invoices will be submitted each month for the prior month's expenditures. After all PROJECT COMPONENT WORK is complete, PARTIES will submit a final accounting of all PROJECT COMPONENT costs. Based on the final accounting, PARTIES will invoice or refund as necessary to satisfy the financial commitments of this AGREEMENT. 13. If an executed Program Supplement Agreement (PSA) or STIP Planning, Programming, and Monitoring Program Fund Transfer Agreement (PPM) exists for this PROJECT then CITY will abide by the billing and payment conditions detailed for the fund types identified in the PSA or PPM. 14. If CALTRANS reimburses CITY for any costs later determined to be unallowable, CITY will reimburse those funds. Project Development Agreement 2017-02-17 (Created May 25, 2022) 5 of 7 AGREEMENT 10 — 533 Al Project No. 1014000090 CONSTR UCTION Support 15. No invoicing or reimbursement will occur for the CONSTRUCTION SUPPORT PROJECT COMPONENT. CONSTRUCTION Capital 16. CITY will invoice and CALTRANS will reimburse for actual costs incurred and paid. Department Furnished Materials (DFM) 17. CALTRANS will invoice CITY for $11,600 after execution of this AGREEMENT and forty-five (45) working days prior to the commencement of Department Furnished Materials expenditures. This represents the entire Department Furnished Materials estimated costs. Thereafter, CALTRANS will invoice and CITY will reimburse for actual costs incurred and paid upon execution of the amendment. Project Development Agreement 2017-02-17 (Created May 25, 2022) 6 of 7 FUNDING SUMMARY No. 02 Signatures AGREEMENT 10 — 533 Al Project No. 1014000090 PARTIES are authorized to enter into this AGREEMENT and have delegated to the undersigned the authority to execute this AGREEMENT on behalf of the respective agencies and hereby covenants to have followed all the necessary legal requirements to validly execute this AGREEMENT. By signing below, the PARTIES each expressly agree to execute this AGREEMENT electronically. The PARTIES acknowledge that executed copies of this AGREEMENT may be exchanged by facsimile or email, and that such copies shall be deemed to be effective as originals. STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION Dennis T. Agar District Director Date: Michelle Ishaya District Budget Manager Gina Schumacher HQ Accounting Supervisor CITY OF LODI Stephen Schwabauer City Manager Date: 011 V i a, rA ash d City Clerk Janice D. Magdich City Attorney Project Development Agreement 2017-02-17 (Created May 25, 2022) 7 of 7 RESOLUTION NO. 2022-204 A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING THE CITY MANAGER TO EXECUTE AMENDMENT NO. 1 TO THE COOPERATIVE AGREEMENT WITH THE STATE OF CALIFORNIA FOR THE PROPOSED STATE ROUTE 99 / TURNER ROAD INTERCHANGE IMPROVEMENTS WHEREAS, since 2018, San Joaquin Council of Governments (SJCOG), the California Department of Transportation (Caltrans), the City of Lodi, and the design consultant, Drake Haglan & Associates, Inc., have collaborated to prepare the necessary environmental clearance and design documents for constructing the State Route 99 (SR99)/Turner Road Interchange Improvements; and WHEREAS, as a condition of project approval, Caltrans required the City of Lodi to enter into a Cooperative Agreement with the State of California; and WHEREAS, on October 20, 2021, Council authorized the Public Works Director to execute the initial Cooperative Agreement for the State Route 99/Turner Road Interchange Project; and WHEREAS, Amendment No. 1 to the initial Cooperative Agreement includes Caltrans -requested changes to the funding table and language providing a mechanism for the City to pay Caltrans for a portion of the project signal controller and cabinet that will be supplied by Caltrans; and WHEREAS, SJCOG requires the City to execute an addendum to the Cooperative Agreement; and WHEREAS, staff recommends authorizing the City Manager to execute Amendment No.1 to the Cooperative Agreement with State of California for proposed State Route 99/Turner Road Interchange Improvements. NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby authorize City Manager to execute Amendment No. 1 to the Cooperative Agreement with State of California for the proposed State Route 99/Turner Road Interchange Improvements; and BE IT FURTHER RESOLVED, pursuant to Section 6.3q of the City Council Protocol Manual (adopted 11/6/19, Resolution No. 2019-223), the City Attorney is hereby authorized to make minor revisions to the above-refe enced document(s) that do not alter the compensation or term, and to make clerical correctioZas necessary. Dated: August 17, 2022 I hereby certify that Resolution No. 2022-204 was passed and adopted by the City Council of the City of Lodi in a regular meeting held August 17, 2022 by the following votes: AYES: COUNCIL MEMBERS — Hothi, Kuehne, Nakanishi, and Mayor Chandler NOES: COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS — Khan ABSTAIN: COUNCIL MEMBERS — None OLIVIA NASHED City Clerk 2022-204 10 -SJ -99-31.1/31.6 AMENDMENT NO. 1 TO AGREEMENT 10-533 6!.-10 Agreement 10-533 Al EA 10-1C260 Project ID 1014000090 This Amendment No. 1 (AMENDMENT) to Agreement 10-533 (AGREEMENT), executed on and effective from 10/19/2021, is between the State of California, acting through its Department of Transportation, referred to as CALTRANS, and: City of Lodi, a body politic and municipal corporation or chartered city of the State of California, refe-red to hereinafter as CITY. RECITALS CALTRANS and CITY, collec-ively referred to as PARTIES, entered into AGREEMENT No. 10-533, on 10/19/2021,:defining the terms and conditions for City of Lodi to construct improvement3 to the southbound state route-99/Turner Road interchange at PM 31.0/31.7, referred to as PROJECT. 2. The AGREEMENT establishes post mile limits were stated as 31.0/31.7 and the LPP Funds were cap at $1,629,000_ PARTIES now seek to add $3,100;0.00 of SB 1 LPP funds to Construction Capital for a total of $4,468,00.0. Remove $197,284 of Fed HIP from Construction Support and decrease $372,446 of Fed HIP =rom Construction Capital for a total of $1,150,270. Remove the $637,156 of Local from Construction Support and remove $8,600 of Local from Construction Capital. Remove $222,844 of Measure 0 from Construction Support add $232,.123 of Measure KM to Construction Capital. Add $641,347 of RSTP funds to Construction Capital. Add $1,399,617 of Measure K to Construction Support and decrease $2,381,740 of Measur~ K for Construction Capital to $1,748,260. Increase DFM from $8,600 to $11,600 and using Measure K for DFM and to change the postmiles to 31.1/34.6. IT IS THEREFORE MUTUALLY AGREED: 1. Article The Header in the AGREEMENT is replaced in its entirety to read as follows: Cooperative Agreement # 10-5.3 EA 10-1C260 Project ID 1014000090 District 10, Route 99, San Joaquin County, PM 31.1/31.6 1 of 3 Agreement 10-533 Al EA 10-1C260 Project ID 1014000090 10 -SJ -99-31.1/31.6 2. A revised Funding Summary is attached and made part of the AGREEMENT. Any reference to the Funding Summary in the AGREEMENT is deemed to refer to the revised Funding Summary attached herein. 3. All other terms and conditions of the AGREEMENT shall remain in full force and effect. 4. This AMENDMENT is deemed to be included and made a part of the AGREEMENT. CONTACT INFORMATION The information provided below indicates the primary contact information for each PARTY to this AGREEMENT. PARTIES will notify each other in writing of any personnel or location changes. Contact information changes do not require an amendment to this AGREEMENT. CITY OF LODI Public Works Director: Charles E. Swimley Jr. Phone Number: (209) 333-6707 E-mail: cswirnle c01odi.g,0v Billing Address: 221 West Pine Street Lodi,_CA 95240 CALTRANS Project Manager: Allen Lao Phone Number: 209 986-5570 2 of 3 10 -SJ -99-31.1/31.6 E-mail: tillc:n.lilCY(LL?[�[)l.�ci.�l]V SIGNATURES Agreement 10-533 Al EA 10-1 C260 Project ID 1014000090 PARTIES are authorized to enter into this AMENDMENT and have delegated to the undersigned the authority to execute t_ais AMENDMENT on behalf of the respective agencies and hereby covenants to have followed all the necessary legal requirements to validly execute this AMENDMENT. By signing belcw, the PARTIES each expressly agree to execute this AMENDMENT electronically. The PARTIES acknowledge that executed copies of this AMENDMENT may be exchanged by facsimile or email, and that such copies shall be deemed to be effective as originals. STATE OF CALIFORNIA DEPARTMENT OF TRANSPORTATION By: Denise T. Agar District Director VERIFIED OF FUNDS & AUTHORITY: By: Michelle Ishaya District Budget Manager CERTIFIED AS TO FINANCIAL TERMS & POLICIES: By: Nadine Karavan HQ Accounting Supervisor CITY OF LODI By: Stephen Schwabauer City Manager Attest: Jennifer Cusmir City Clerk APROVED AS TO FORM & PROCEDURE: By: Janice D. Magdich City Attorney 3 of 3 10 -SJ -99-31.1/31.6 Agreement 10-533 Al EA 10-1C260 Project ID 1014000090 4of3 AGREEMENT 10 - 533 EA 1C260 Project No. 1014000090 10 -SJ -99-31.1/31.6 FUNDING SUMMARY NO. 02 'Non-federal match Project Development Agreement 2017-02-17 (Created August 11, 2022) 1 of 6 FUNDING TABLE IMPLEMENTING AGENCY4 CITY CONST. CONST. Source Party Fund Type SUPPORT 261.,000 CAPITAL 4,468,000 Totals 4,729,000 STATE CALTRANS SB 1 LPP LOCAL- CITY Fed HIP 0 1,150,270 1,150,270 FEDERAL LOCAL - CITY RSTP 0 641,347 641,347 FEDERAL LOCAL CITY Measure K 1,399,617 1,748,260 3,147,877 LOCAL CITY Measure Km 0: 232,123 232,123 Totals 1,660,617 8,240,000 9,900,6171 'Non-federal match Project Development Agreement 2017-02-17 (Created August 11, 2022) 1 of 6 FUNDING SUMMARY No. 02 l;`�7DL'1�TilTTTTDT. T A DT Z, lIL1 1' \L11 ll it�.:1 1ALL11 II IMPLEMENTING AGENCY4 CITY Ii _ I CONST. CAPITAL Eligible Ineligible Source Party Fund Type STATE CALTRANS SB 1 LPP x x LOCAL - FEDERAL CITY Fed HIP X -- LOCAL - FEDERAL CITY RSTP X -- LOCAL CITY Measure K X x LOCAL CITY Measure KM X - Note: An "X" denotes the funding type is available for payment. 'Non-federal match AGREEMENT 10 - 533 Project No. 1014000090 Project Development Agreement 2017-02-17 (Created August 11, 2022) 2 of6 FUNDING SUMMARY No. 02 SPENDING SUMMARY CONST. SUPPORT CONST. CAPITAL Fund Type CALTRANS 0 DFM CALTRANS Totals CITY 261,000 CITY 56 1 LPP 4,468,000 0 4,729,000 'I-ecl HIP 0 0 1,150,270 0 1,150,270 RSTP 0 0 641,347 0 641,347 Measure K 0 1,399,617 1,736,660 11,600 3,147,877 Measure Km 0 232,123 0 232.,123 Totals 0 1,660,617 8,228,400 11,600 9,900,617 AGREEMENT 10 - 533 Project No. 1014000090 Project Development Agreement 2017-02-17 (Created August 11, 2022) 3 of6 FUNDING SUMMARY No. 02 Funding AGREEMENT 10 - 533 Project No. 1014000090 1. If there are insufficient funds available in this AGREEMENT to place the PROJECT right-of-way in a safe and ope-able condition, the appropriate IMPLEMENTING AGENCY will fund these activities until such time as PARTIES amend this AGREEMENT. That IMPLEMENTING AGENCY may request reimbursement for these costs during the amendment process. 2. If there are insufficient funds in this AGREEMENT to implement the obligations and responsibilities of this AGREEMENT, including the applicable commitments and conditions included in the PROJECT environmental documentation, permits, agreements, and/or approvals that are in effect at a time that WORK stops, each PARTY accepts responsibility to fund their respective WORK until such time as PARTIES amend this AGREEMENT. Each PARTY may request reimbursement for these costs during the amendment process. The cost of any engineering support performed by CALTRANS includes all direct and applicable indirect costs. CALTRANS calculates indirect costs based solely on the type of funds used to pay support costs. State and federal funds administered by CALTRANS are subject to the current Program Functional Rate. All other funds are subject to the current Program Functional REte and the current Administration Rate. The Program Functional Rate and Administration Rate are adjusted periodically. In accordance with California Senate Bill 848, the Administration Rate is capped at 10 percent until January 1, 2023, fo- Self -Help Counties with a countywide sales tax measure dedicated to transportation improvements. 4. If the WORK is funded with state or federal funds, any PARTY seeking CALTRANS reimbursement of indirect costs must submit an indirect cost rate proposal and central service cost allocation plan (if any) in accordance with Local Assistance Procedures Manual, 2 CFR, Part 200 and Chapter 5. These documents are to be submitted annually to CALTRANS' Audits and Irrvestigations for review and acceptance prior to CALTRANS' reimbursement of indirect costs. Project Development Agreement 2017-02-17 (Created August 11, 2022) 4 of6 FUNDING SUMMARY No. 02 AGREEMENT 10 - 533 Project No. 1014000090 5. Travel, per diem, and third-pa-ty contract reimbursements for WORK are to be paid from the funds in this AGREEMENT only after the contractor performs the work and incurs said costs. Payments for travel and per died will not exceed the rates paid rank and file state employees under current California Department of Human Resources (Ca1HR) rules current at the effective date of this AGREEMENT. If CITY invoices for rates in excess of CaIHR rates, CITY will fund the cost difference and reimburse CALTRANS for any overpayment. 6. In accordance with the CALTRANS Federal -Aid Project Funding Guidelines, PARTIES must obtain approval from the Federal Highway Administration prior to any PROJECT funding changes that that will change the federal share of funds. 7. Notwithstanding the terms of this AGREEMENT, PARTIES agree to abide by the funding guidelines for all contributed funds that are programmed and allocated by the CTC. Invoicing and Payment PARTIES will invoice for funds where the SPENDING SUMMARY shows that one PARTY provides funds for use by another PARTY. PARTIES will pay invoices within forty-five (45) calendar days of receipt of invoice when not paying with Electronic Funds Transfer (EFT). When paying with EFT, CITY will pay invoices within five (5) calendar days of receipt of invoice. 9. If CITY has received EFT certification from CALTRANS then CITY will use the EFT mechanism and follow all EFT procedures to pay all invoices issued from CALTRANS. 10. When a PARTY is reimburses for actual cost, invoices will be submitted each month for the prior month's expenditures After all PROJECT COMPONENT WORK is complete, PARTIES will submit a final Eccounting of all PROJECT COMPONENT costs. Based on the final accounting, PARTIES will invoice or refund as necessary to satisfy the financial commitments of this AGREEMENT. Project Development Agreement 2017-02-17 (Created August 11, 2022) 5 of6 FUNDING SUMMARY No. 02 AGREEMENT 10 - 533 Project No. 1014000090 11. If an executed Program Suppl-.ment Agreement (PSA) or STIP Planning, Programming, and Monitoring Program Func Transfer Agreement (PPM) exists for this PROJECT then CITY will abide by the billing and payment conditions detailed for the fund types identified in the PSA or PPM. 12. If CALTRANS reimburses CITY for any costs later determined to be unallowable, CITY will reimburse those funds. CONSTRUCTION SuMor 13. CITY will invoice and CALTRANS will reimburse for actual costs incurred and paid. CONSTRUCTION Capita 14. CITY will invoice and CALTRANS will reimburse for actual costs incurred and paid. Department Furnished Materials (DFM) 15. CALTRANS will invoice and CITY will reimburse for actual costs incurred and paid. Project Development Agreement 2017-02-17 (Created c ugust 11, 2022) 6 of6