HomeMy WebLinkAboutAgenda Report - February 7, 2001 E-18CITY OF LODI COUNCIL COMMUNICATION AGENDA TITLE: Adopt Resolution Authorizing the City Manager to Execute a Work Order for Mark Thomas & Company, Inc., for Design of Kettleman Lane Widening Project from Woodbridge Irrigation District Canal to Tienda Drive and Stockton Street to Cherokee Lane; and Appropriate $152,650 MEETING DATE: February 7, 2001 PREPARED BY: Public Works Director RECOMMENDED ACTION: That City Council adopt a resolution authorizing the City Manager to execute a work order for design work for the Kettleman Lane Widening Project to Mark Thomas & Company, Inc., and appropriate $152,650 for the design work. BACKGROUND INFORMATION: At the November 1, 2000, City Council meeting, City Council authorized the City Manager to execute the professional service agreement with Mark Thomas & Company, Inc., to prepare the design work for the Kettleman Lane Widening Project. After the design consultant and staff evaluated the project, it was determined that the project limits could be expanded within the project budget. The project was expanded to include the 0.5 -mile segment between Cherokee Lane and Stockton Street. This segment has had several collisions involving turning vehicles. To eliminate these types of collisions, the additional work includes a raised median within the existing right of way. In addition, dual left -turn lanes on the Kettleman Lane eastbound approach at Cherokee Lane will be designed to accommodate the high turning volume and improve the intersection operations. The design consultants will prepare plans and specifications, as well as provide the environmental documentation for this segment. In addition, the scope of the project will include the landscape design of the proposed raised median for both segments. The consultant, along with staff, will conduct a public information meeting on February 20, 2001, to gather public input from the community. Notices were distributed to all the property owners and tenants along these segments, and ads were placed in the local newspaper. Staff recommends City Council adopt a resolution authorizing the City Manager to execute the attached work order. FUNDING: Requested Appropriation: Measure K funds $152,650 Funding Available: a I C 1 - Vicky Richard C. Prima, Jr Public Works Director Prepared by Paula J. Fernandez, Associate Traffic Engineer RCP/PJF/pmf Attachment cc: Randy Hays, City Attorney Carlos Tobar, Transportation Manager Paula Fernandez, Associate Traffic Engineer Rob Himes, Mark Thomas & Company, Inc. Diane Nguyen, SJCOG APPROVED: H. Dixon Flynn -- City Manager CWorkOrder � 01/31/01 CITY OF LODI PUBLIC WORKS DEPARTMENT WORK ORDER NO. 1 Sheet 1 of 1 Date 2-07-01 Account No. 325088.7323 PROJECT: Kettleman Lane Widening Project, WID to Tienda Drive, and Cherokee Lane to Stockton Street CONSULTANT: Mark Thomas & Co., Inc. You are directed to make the following changes or do the following work not included in the Agreement For Consulting Services dated December 11, 2000. ---------------------------------------------------------------------- Description of work: To provide design and envrionmental work for an expanded project segment between Cherokee Lane to Stockton Street, median landscape and irrigation design for both segments, and expanded traffic analysis as described in the attached scope of services. Justification: After the consultant and staff evaluated the project, it was determined that project limits could be expanded within the project budget. The project was expanded to include the 0.5 -mile segment between Cherokee Lane and Stockton Street. This segment has had several collisions involving turning vehicles. To eliminate these types of collisions, the additional work includes a raised median within the existing right of way. In addition, dual left turn lanes, on the Kettleman Lane eastbound approach at Cherokee Lane, will be designed to accommodate the high turning volume and improve the intersection operations. The design consultants will prepare plans and specifications as well as provide the environmental documentation for this segment. In addition, the scope of the project will include the landscape design of the raised median for both segments. The consultant will also provide additional traffic analysis for the environmental documentation. PERCENT OF CONTRACT Original Contract Price $ 236,962 Total Cost of This Work Order NOT TO EXCEED $ 152,649 64.4% Previous Work Orders NA Total Cost of All Work Orders to Date $ 152,649 64.4% Contract Price, Including All Work Orders, Will Be: $ 389,611 Time of completion will be adjusted as follows: None ---------------------------------------------------------------------- Submitted By Paula Fernandez Approval Recommended Date Approved, Public Works Director Date Approved, City Manager (Per Public Works Policies and Procedures, Administration 4. 1) The undersigned, having carefully considered the change proposed, agrees, if this proposal is approved, to perform all services necessary for the work above specified, and accept as full payment the prices shown above. ACCEPTED: Date By, Consultant Title RESOLUTION NO. 2001-21 A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING THE CITY MANAGER TO EXECUTE A WORK ORDER WITH MARK THOMAS & COMPANY FOR DESIGN OF KETTLEMAN LANE WIDENING PROJECT FROM WOODBRIDGE IRRIGATION DISTRICT CANAL TO TIENDA DRIVE AND STOCKTON STREET TO CHEROKEE LANE, AND FURTHER APPROPRIATING FUNDS FOR THIS PROJECT WHEREAS, at their November 1, 2000 Council meeting, the City Council authorized the City Manager to execute the Professional Services Agreement with Mark Thomas & Company, Inc., to prepare the design work for the Kettleman Lane Widening Project; and WHEREAS, after the design consultant and staff evaluated the project, it was determined that the project limits could be expanded within the project budget; and WHEREAS, the project was expanded to include the 0.5 -mile segment between Cherokee Lane and Stockton Street. This segment has had several collisions involving turning vehicles, and in order to eliminate these types of collisions, the additional work includes a raised median within the existing right-of-way. In addition, dual -left turn lanes on the Kettleman Lane eastbound approach at Cherokee Lane will be designed to accommodate the high turning volume and improve the intersection operations. The design consultants will prepare plans and specifications, as well as provide the environmental documentation for this segment. The scope of the project will include the landscape design of the proposed raised median for both segments. NOW, THEREFORE, BE IT RESOLVED, that the Lodi City Council does hereby authorize the City Manager to execute a Work Order with Mark Thomas & Company for design of Kettleman Lane Widening Project from the Woodbridge Irrigation District Canal to Tienda Drive and Stockton Street to Cherokee Lane; and BE IT FURTHER RESOLVED that Measure K funds in the amount of $152,650.00 be appropriated for this project. Dated: February 7, 2001 ----------------------------------------- I hereby certify that Resolution No. 2001-21 was passed and adopted by the Lodi City Council in a regular meeting held February 7, 2001 by the following vote: AYES: COUNCIL MEMBERS — Hitchcock, Howard, Land and Pennino NOES: COUNCIL MEMBERS — None ABSENT: COUNCIL MEMBERS — Mayor Nakanishi ABSTAIN: COUNCIL MEMBERS — None SUSAN J. BLACKSTON City Clerk 2001-21 CITY COUNCIL ALAN S. NAKANISHI, Mayor PHILLIP A. PENNINO Mayor Pro Tempore SUSAN HITCHCOCK EMILY HOWARD KEITH LAND CITY OF LODI PUBLIC WORKS DEPARTMENT CITY HALL, 221 WEST PINE STREET P.O. BOX 3006 LODI, CALIFORNIA 95241-1910 (209)333-6706 FAX (209) 333-6710 EMAIL pwdept@lodi.gov http:k%www.lodi.gov February 1, 2001 Mr. Rob Himes Mark Thomas & Company, Inc. 7300 Folsom Blvd., Ste. 203 Sacramento, CA 95826 H. DIXON FLYNN City Manager SUSAN J. BLACKSTON City Clerk RANDALL A. HAYS City Attorney RICHARD C. PRIMA, JR. Public Works Director Ms. Diane Nguyen San Joaquin Council of Governments 6 South EI Dorado St., Ste. 400 Stockton, CA 95202 SUBJECT: Adopt a Resolution Authorizing the City Manager to Execute a Work Order for Mark Thomas & Company, Inc. for Design of Kettleman Lane Widening Project from Woodbridge Irrigation District Canal to Tienda Drive and Stockton Street to Cherokee Lane; and Appropriate $152,650 Enclosed is a copy of background information on an item on the City Council agenda of Wednesday, February 7, 2001. The meeting will be held at 7 p.m. in the City Council Chamber, Carnegie Forum, 305 West Pine Street. This item is on the consent calendar and is usually not discussed unless a Council Member requests discussion. The public is given an opportunity to address items on the consent calendar at the appropriate time. If you wish to write to the City Council, please address your letter to City Council, City of Lodi, P. O. Box 3006, Lodi, California, 95241-1910. Be sure to allow time for the mail. Or, you may hand -deliver the letter to City Hall, 221 West Pine Street. If you wish to address the Council at the Council Meeting, be sure to fill out a speaker's card (available at the Carnegie Forum immediately prior to the start of the meeting) and give it to the City Clerk. If you have any questions about communicating with the Council, please contact Susan Blackston, City Clerk, at (209) 333-6702. If you have any questions about the item itself, please call Paula Fernandez, Associate Traffic Engineer, at (209) 333-6800, extension 2667. Richard C. Prima, Jr. Public Works Director RCP/pmf Enclosure / cc: City Clerk✓ NCWORKORDER