HomeMy WebLinkAboutAgenda Report - December 1, 2021 C-05AGENDA ITEM Cw5
CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Adopt Resolution Awarding Contract for Lodi Lake Riverbank Stabilization
Project, to Asta Construction Company Inc., of Rio Vista ($541,013), Authorizing
City Manager to Execute Contract Extensions and Change Orders ($50,000),
and Appropriating Funds ($134,000)
MEETING DATE:
PREPARED BY
December 1, 2021
Public Works Director
RECOMMENDED ACTION: Adopt resolution awarding contract for Lodi Lake Riverbank
Stabilization Project to Asta Construction Company, of Rio Vista,
in the amount of $541,013.00, authorizing City Manager to
execute contract extensions and change orders in an amount not to exceed $50,000, and appropriating
funds in the amount of $134,000.
BACKGROUND INFORMATION: A portion of the riverbank on the Mokelumne River that runs along
the northern boundary of Lodi Lake Park, has become severely
eroded in past years and is threatening adjacent park facilities.
The erosion has exposed irrigation lines, tree roots, and is causing the collapse of concrete retaining
wall structures.
The project includes clearing, grubbing, selective tree removal and trimming, concrete slope protection
removal and replacement, sod installation, tree planting, and other miscellaneous and related work as
shown on the plans and specifications for the project.
As noted on the approved plans, approximately 25 non-native, unhealthy trees will be removed with this
project. These trees slated for removal represent either small volunteer undergrowth that grew under
existing trees, or trees that are at risk of falling into the river. Thirty-five new native trees will be planted to
replace those removed. (Exhibit A).
Specifications for this project were approved on October 20, 2021. The City received the following 10
bids for this project on November 17, 2021:
Bidder Location Bid Above/(Below) Estimate
Engineer's Estimate
$ 550,750.00
Asta Construction
Rio Vista
$ 541,013.00
$ (9,737.00)
Suulutaaq Inc.
Suisun City
$ 561,934.00
$ 11,184.00
AM Development Inc.
EI Dorado Hills
$ 579,395.00
$ 28,645.00
Marshall Brothers Enterprise
Livermore
$ 596,221.50
$ 45,471.50
Ford Construction
Lodi
$ 677,575.00
$ 126,825.00
AM Stephens Construction
Lodi
$ 754,091.20
$ 203,341.20
Diede Construction
Woodbridge
$ 757,155.00
$ 206,405.00
Hanford ARC
Petaluma
$ 819,110.00
$ 268,360.00
Wood Bros.
Lemoore
$ 916,395.00
$ 365,645.00
Innovative Construction
Costa Mesa
$ 943,535.00
$ 392,785.00
Steve Schwabauer
APPROVED;
Stephen Schwabauer, City Manager
\Ncvcfilv02\pubwks$\WP\COUNCIL\2021 PDF's\120121\Editing\CAward_Lodi Ake Riverbank.doc 11/22/2021
Adopt Resolution Awarding Contract for Lodi Lake Riverbank Stabilization Project, to Asta Construction Company Inc„ of Rio Vista ($541,013), Authorizing City
Manager to Execute Contract Extensions and Change Orders ($50,000), and Appropriating Funds ($801,000)
December 1, 2021
Page 2
Staff obtained all the permits and agreements for the project, except for the land lease agreement from
State Land Commission (SLC). The no -cost land lease agreement is scheduled to be on the February
2022 State Land Commission board meeting for approval. The work along the riverbank under the
normal water level cannot be started until the lease agreement is fully executed.
This requirement has placed a significant constraint on our project schedule since the work below the
normal water level must be performed while the Woodbridge Irrigation District (WID) lowers the water
level in the river to perform its annual maintenance on their facilities. The WID annual maintenance
activities are generally completed in late February of early March. At this time the river water level is
returned to normal. If the proposed work under the normal water level is not complete before WID
raises the river water level, the remaining work would need to be postponed and completed in February
2023. Staff is working closely with SLC and WID to make the schedule.
Staff recommends awarding contract for Lodi Lake Riverbank Stabilization Project, to Asta Construction
Company Inc., of Rio Vista, in the amount of $541,013, authorizing City Manager to execute contract
extension and change orders in an amount not to exceed $50,000, and appropriating funds in the
amount of $134,000.
FISCAL IMPACT: The current adopted budget is insufficient to complete the Lodi Lake Riverbank
Stabilization project as currently scoped. An additional $134,000 is needed to
cover various contract costs, contingencies, staff time and permitting fees. In
review of PRCS current capital projects, only two projects were deemed low
priority from which funding could be reallocated. First is the Legion Park
Community Room project. On a previous item, Staff recommended reallocating
funding from this project to cover the shortfall in the Blakely Park project. The
other project is the Small and Large Dog Park Separation and Watering Station
project. Staff is not recommending reallocating any of the $100,000 funding
from this project at this time, however doing so would not greatly impact the
current park system or create any additional risk to park operations. Instead,
staff is recommending utilizing General Fund reserves in Fiscal Year 2021 that
are in excess of the fund balance requirement of 16%. These reserves are
made possible by revenues above estimates and expenses below budget in
Fiscal Year 2020/21, primarily Measure L. Without Measure L, staff would have
to recommend delaying this project or reducing its scope.
FUNDING AVAILABLE: Requested Appropriation:
10095000.76220 General Fund Transfer Out - $134,000
43199000.50001 Capital Outlay Transfer In - $134,000
43199000.77020 Capital Outlay Capital Expense
(PKCAP-0047. Contracts. GF) - $134,000
Susan Bjork, Budget Manager for:
Andrew Keys
Deputy City Manager/Internal Services Director
01�)UD
Charles E. Swimley, Jr.
Public Works Director
Prepared by Lyman Chang, Deputy Public Works Director/City Engineer
CES/LC/cd
cc: Public Works Management Analyst Parks/Recreation and Cultural Services Director
Senior Civil Engineer KSN Consulting Engineer Asta Construction
\\cvcfilv02\pubwks$\WP\COUNCIL\2021 PDF's\120121\Editing\CAward_Lodi Ake Riverbank.doc 11/22/2021
rEtr T—� - uca�i iY
��r 5 u � N awl IIIL
will a—j- e
i
L11
v
EXHIBITA
0 MMES WIIHNMaJE1CTMEATDR_hW3 I'SVol
1REE5 W11HN HlD.F1CT AREdTO BE F4 kG'i:: N
11FEES w1HN FFai1CT AREATE1 ff 1RM14 L1
NIX[ ELLIEII TREE TO 1£ PLANTED
VAI LEY UKTREES TD W PUNTED
hol" 5
1. �.MfNG55WLL AE I�:ILLY9C1.N2GFGf Y.1MA
NL.RiI AY S�GRNIhC N NSTNE?hk'I5. � IAS
.DFN�LGiYFA FRAYS. PlAN17NGS5WI. LGNSSfa
'Dh fhNl FII: ] Sf CKJ{ B: PA} I h 1 MD 5 GN lCM
1411 X21 :ISF �I# f ING .021 OhS *L. B: 51A('3
NfbI I FL]BY TbI PRDNE.FBOIDGSI 1H1
FNGI{G.ISSWLFf SAF%:AY'dl:]"DET
1'Ar.E 11l f3W "ERAN] 1'ALCE' 1H1 71 P111D1 RIF
'0h fdN. -I{I IIC.IS SWI PA Pdf ILL. Y:11IFB
Yf 11 I d !TtSC N% x : %.A4'd I I I: Wd1F RA AN, A
ail W4i Kri N-WBFT14 �. Th"SAWLIII
LMS. Y: G I AGh11: 1 .Dh I w FS AN: Ih51 N I E D Ih g
IHF 4PD.1 5. 11-: 117L:5S V.1 71 BAGh 1 1 .: ]'A1114
D{P -ZxW MIX ANG GI N1. Y -APL D DfAh 1G• 51 .D
DII S.MFkGS
s.
_ I
NON
rr
E10d1! vs
rtto.o ,n.E_w imar r � LIIf ,A
n -
i
.rJ .Y}i�•1. ;M
LODI LAKE RIVERBANK STABILIZATION PROJECT
1101 W TURNER ROAD CONTRACT
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein
referred to as the "City," and ASTA CONSTRUCTION, CO., INC., a California Corporation,
herein referred to as the "Contractor."
WITNESSETH. -
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by
this reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 1992 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents,"
are intended to cooperate so that any work called for in one and not mentioned in the other
is to be executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the
two bonds bearing even date with these presents and hereunto annexed, the Contractor
agrees with the City, at Contractor's cost and expense, to do all the work and furnish all the
materials except such as are mentioned in the specifications to be furnished by the City,
necessary to construct and complete in a good workmanlike and substantial manner and to
the satisfaction of the City the proposed improvements as shown and described in the
Contract Documents which are hereby made a part of the Contract.
ARTICLE 11 - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractor to provide all materials and services not supplied by the City
and to do the work according to the terms and conditions for the price herein, and hereby
contracts to pay the same as set forth in Section 5.600, "Measurement, Acceptance and
Payment," of the General Provisions, in the manner and upon the conditions above set forth;
and the said parties for themselves, their heirs, executors, administrators, successors and
assigns, do hereby agree to the full performance of the covenants herein contained.
ARTICLE III - The Contractor agrees to conform to the provisions of Chapter 1, Part 7,
Division 2 of the Labor Code. The Contractor and any Subcontractor will pay the general
prevailing wage rate and other employer payments for health and welfare, pension, vacation,
4.1 11/17/21
"r.vrfilvn2\niihwkc&\WP\PRO.IFrTR\PARKS\I onil AKRRivarhank Stahili7atinn PmiArtkrr)NTRArT Mr.
travel time, and subsistence pay, apprenticeship or other training programs. The
responsibility for compliance with these Labor Code requirements is on the prime contractor.
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and
embraced in this agreement; also for all loss or damage arising out of the nature of the work
aforesaid or from the action of the elements, or from any unforeseen difficulties or
obstructions which may arise or be encountered in the prosecution of the work until its
acceptance by the City, and for all risks of every description connected with the work; also
for all expenses incurred by or in consequence of the suspension or discontinuance of work
and for well and faithfully completing the work, and the whole thereof, in the manner and
according to the Plans and Contract Documents and the requirements of the Engineer under
them, to -wit:
The Work includes clearing, grubbing, and selective tree removal and trimming, concrete
slope protection removal and disposal, 18 -inch minus quarry stone riprap, 6 -inch minus
quarry stone riprap, import fill, sod installation, tree planting, and other miscellaneous and
related work as shown on the plans and specifications for the project.
CONTRACT ITEMS
Item
Description
QtY
Unit
Price
Total
1
Mobilization
Grading, Grubbing, Tree
1
LS
$ 20,840.00
$ 20,840.00
2
Trimming and Tree Removal
1
LS
$ 55,901.00
$ 55,901.00
3 Concrete Slope Protection
Removal and Disposal
1,250
LF
$ 41.00
$ 51 250.00
4
18 -Inch Minus Quarry Stone
Riprap
6,440
TON
$ 43.30
$ 278,852.00
5
6 -Inch Minus Quarry Stone
Riprap
1,250
TON
$ 42.94
$ 53,675.00
6
Import Fill
1,200
TON
$ 48.45
$ 58,140.00
7
Sod Installation
2,200
SF
$ 3.05
$ 6,710.00
8
Tree Planting
35
EA
$ 447.00
$ 15,645.00
TOTAL $ 541, 013.00
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with
the provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
4.2 11/17/21
\\rvrfilvn9\niihwkaR\WP\PRn.IFr.TS\PARKS\I onll AKF\Rivarhank Stahili7atinn Prniart\rnNTRArT Anr.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should
there be any conflict between the terms of this instrument and the Bid Proposal of the
Contractor, then this instrument shall control and nothing herein shall be considered as an
acceptance of the said terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to
establish lines and grades for the work as specified under the Special Provisions. All labor
or materials not mentioned specifically as being done by the City will be supplied by the
Contractor to accomplish the work as outlined in the specifications.
ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract within 15
calendar days after the City Manager has executed the contract and to diligently prosecute to
completion within 40 CALENDAR DAYS.
ARTICLE IX - State of California Senate Bill 854 requires the following:
No contractor or subcontractor may be listed on a bid proposal for a public works
project unless registered with the Department of Industrial Relations pursuant to
Labor Code section 1725.5 [with limited exceptions from this requirement for bid
purposes only under Labor Code section 1771.1(a)].
No contractor or subcontractor may be awarded a contract for public work on a public
works project unless registered with the Department of Industrial Relations pursuant
to Labor Code section 1725.5.
This project is subject to compliance monitoring and enforcement by the Department
of Industrial Relations.
4.3
\\rvrfilvn9\rnihwkcR\WP\PRn.IFrT.R\PARKS\I nnll AKF\Rivarhank StaNU7,ltinn PrniP.rtU;nNTRA(T Mr.
11/17/21
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR
AGREES TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-
04.03 OF THE SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT
MAY BE DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE
CONTRACT.
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the
year and date written below.
CONTRACTOR: CITY OF LODI, a municipal corporation
0
Title
as
STEPHEN SCHWABAUER
City Manager
Date:
Attest:
JENNIFER CUSMIR
City Clerk
(CORPORATE SEAL) Approved As To Form
JANICE D. MAGDICH
City Attorney �K
4.4
\\rvrfivn9\rnihwkq$\WP\PRO.IFrTS\PARKS\I ODII AKF\Rivarhank Stahili7atinn PmiP..r.t\r0NTRArT rinr.
11/17121
Capital Improvement Plan
FY 2021-2022
Project Title:
Lodi Lake Park Erosion Repair
Munis Project Code: PKCAP-0047
#18
Section I: Description
District Nos:
1 Project Length Priority
Normal
State grant and potential City funds to repair eroded riverbank at Lodi Lake Park.
Justification/factor driving project
Loss of parkland to erosion.
Additional Information
Specified State grant in FY 2018/19 budget. - in fiscal year 2022, it was determined that the existing budget was not enough to cover the cost of the contract, contingencies, and stafftime.
Section II: Estimated Project Costs
Expenditure
Prior Years FY 20121 FY 21122 FY 22123
FY 23124 FY 24125 FY 25126 Future Yrs
Total
Estimate Budget
Contracts
$ 1,000,000 $ - $ 134,000
$
1,134,000
Total Capital Costs
$ 1,000,000 $ - $ 134,000 $ -
$ - $ - $ - $ -
$
1,134,000
Section III: Funding Sources/Methods of Financing
Funding Source(s)
Prior Years FY 20121 FY 21122 FY 22123
FY 23124 FY 24125 FY 25126 Future Yrs
Total
Estimate Budget
205 - Parks State Grants
$ 1,000,000 $ -
$
1,000,000
431 - Capital Outlay/General Fund
$ - $ 134,000
$
134,000
$ -
$
-
$ -
$
-
Total Project Financing
$ 1,000,000 $ - $ 134,000 $ -
$ - $ - $ - $ -
$
1,134,000
Section IV
Operating Budget Impact
Operating Cost or (savings)
Prior Years FY 20121 FY 21122 FY 22123
FY 23124 FY 24125 FY 25126 Future Yrs
Total
Estimate Budget
Personnel
$
$
-
Other Operating Costs
$ -
$
-
Total Operating Impact
$ - $ - $ - $ -
$ - $ - $ - $ -
$
-
RESOLUTION NO. 2021-316
A RESOLUTION OF THE LODI CITY COUNCIL AWARDING THE CONTRACT
FOR THE LODI LAKE RIVERBANK STABILIZATION PROJECT TO
ASTA CONSTRUCTION COMPANY, INC., OF RIO VISTA; AUTHORIZING THE
CITY MANAGER TO EXECUTE CONTRACT EXTENSIONS AND CHANGE
ORDERS; AND FURTHER APPROPRIATING FUNDS
WHEREAS, a portion of the riverbank on the Mokelumne River
northern boundary of Lodi Lake Park has become severely eroded in
threatening adjacent park facilities, exposing irrigation lines and tree roots
collapse of concrete retaining wall structures; and
that runs along the
past years and is
and is causing the
WHEREAS, the project includes clearing, grubbing, selective tree removal and trimming,
concrete slope protection removal and replacement, sod installation, tree planting, and other
miscellaneous and related work as shown on the plans and specifications for the project; and
WHEREAS, the plans and specifications for this project were approved on October 20,
2021. The City received the following 10 bids for this project on November 17, 2021:
Bidder
Location
Bid
Above/(Below) Estimate
Asta Construction
Rio Vista
$ 541,013.00
$ (9,737.00)
Suulutaaq Inc.
Suisun City
$ 561,934.00
$ 11,184.00
AM Development, Inc.
EI Dorado Hills
$ 579,395.00
$ 28,645.00
Marshall Bros. Enterprise
Livermore
$ 596,221.50
$ 45,471.50
Ford Construction
Lodi
$ 677,575.00
$ 126,825.00
AM Stephens Const.
Lodi
$ 754,091.20
$ 203,341.20
Diede Construction
Woodbridge
$ 757,155.00
$ 206,405.00
Hanford ARC
Petaluma
$ 819,110.00
$ 268,360.00
Wood Bros.
Lemoore
$ 916,395.00
$ 365,645.00
Innovative Construction
Costa Mesa
$ 943,535.00
$ 392,785.00
WHEREAS, the bid received from Asta Construction was found to be responsive; and
WHEREAS, staff recommends awarding the contract for the Lodi Lake Riverbank
Stabilization Project to Asta Construction Company, Inc., of Rio Vista, in the amount of
$541,013; and
WHEREAS, staff further recommends authorizing the City Manager to execute the
contract, contract extensions, and change orders in an amount not to exceed $50,000; and
WHEREAS, staff further recommends authorizing the following appropriations:
10095000.76220 General Fund Transfer Out - $134,000
43199000.50001 Capital Outlay Transfer In - $134,000
43199000.77020 Capital Outlay Capital Expense (PKCAP-0047. Contracts. GF) - $134,000
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby award
the contract for the Lodi Lake Riverbank Stabilization Project to Asta Construction Company,
Inc., of Rio Vista, California, in the amount of $541,013; and
BE IT FURTHER RESOLVED that the Lodi City Council does hereby authorize the
City Manager to execute the contract, contract extensions, and change orders in an amount not
to exceed $50,000; and
BE IT FURTHER RESOLVED that the Lodi City Council does hereby authorize
appropriation of funds as set forth above; and
BE IT FURTHER RESOLVED, pursuant to Section 6.3q of the City Council Protocol
Manual (Res. No. 2019-223), the City Attorney is hereby authorized to make minor revisions to
the above -referenced document(s) that do not alter the compensation or term, and to make
clerical corrections as necessary.
Dated: December 1, 2021
I hereby certify that Resolution No. 2021-316 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held December 1, 2021, by the following vote:
AYES: COUNCIL MEMBERS — Chandler, Hothi, Khan, Kuehne, and
Mayor Nakanishi
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
�2JENNIFIEC USMIR
City Clerk
2021-316