HomeMy WebLinkAboutAgenda Report - December 1, 2021 C-04AGENDA ITEM Caa4
CITY OF LODI
COUNCIL COMMUNICATION
TM
AGENDA TITLE: Adopt Resolution Approving Plans and Awarding Contract for Blakely Park Sport
Fields & Irrigation Improvements to Emert Construction, of Stockton ($896,872),
Authorizing City Manager to Execute Change Orders ($135,000), and Transfer
Funds ($120,000)
MEETING DATE:
PREPARED BY:
December 01, 2021
Public Works Director
RECOMMENDED ACTION: Adopt resolution approving plans and awarding Contract for Blakely
Park Sports Fields and Irrigation Improvements to Emert
Construction, of Stockton, in the amount of $896,872, authorizing
City Manager to execute change orders in an amount not to exceed $135,000, and transferring funds in
the amount of $120,000.
BACKGROUND INFORMATION: In 2017, the City was awarded a grant from the State Parks, Office
of Grants and Local Services in the amount of $882,340 for the
Blakely Park Sports Fields and Irrigation Improvements (Project).
The grant is contingent on the Project including water conservation measures and construction being
completed by June 30, 2025. With construction costs increasing every year, Staff recommends
proceeding with the project at this time.
This project provides for new turf, irrigation system, basketball court, soccer field, and baseball diamond
renovations at Blakely Park. The new irrigation system, including a booster pump, is estimated to save
approximately 1 million gallons of water per year.
The specifications for this project were approved on August 18, 2021. The City received the following
bids for this project on November 03, 2021:
The bid received from Marina Landscape failed to include Addendum No. 1 and was deemed non-
responsive.
APPROVED: Steve SchWabaUer
Stephen Schwabauer, City Manager
\\cvcfilv02\pubwks$\WP\PROJECTS\PARKS\Blakely Park\Ball Field\CAward,docx
11117/2021
Above/(Below)
Bidder
Location
Bid
Engineer's Estimate
Engineer's Estimate
$864,910.00
*Marina Landscape
Orange
$864,105.00
$(805.00)
Emert Construction
Stockton
$896,872.00
$31,962.00
A.M. Stephens Construction
Lodi
$1,035,889.00
$170,979.00
Stockbridge General Contracting
Clovis
$1,215,068.00
$350,158.00
Suarez & Munoz Construction
Hayward
$1,237,340.00
$372,430.00
"non-responsive
The bid received from Marina Landscape failed to include Addendum No. 1 and was deemed non-
responsive.
APPROVED: Steve SchWabaUer
Stephen Schwabauer, City Manager
\\cvcfilv02\pubwks$\WP\PROJECTS\PARKS\Blakely Park\Ball Field\CAward,docx
11117/2021
Adopt resolution approving plans and awarding Contract for Blakely Park Sports Fields and Irrigation Improvements to Emert Construction, of Stockton, in the amount
of $896,872, authorizing City Manager to execute change orders in an amount not to exceed $135,000, and transferring funds in the amount of $120,000.
December 01, 2021
Page 2
The lowest responsive bid received from Emert Construction, came in higher than the Project grant
amount, not including contingencies. Staff proposes to offset the funding deficit by transferring funds
allocated for the Legion Park Community Room Renovation, as that project is of lower priority.
Staff recommends approving plans and awarding contract for Blakely Park Sports Fields and Irrigation
Improvements to Emert Construction, of Stockton, in the amount of $896,872, authorizing City Manager
to execute change orders in an amount not to exceed $135,000, and transferring funds in the amount of
$120,000.
FISCAL IMPACT: The current adopted budget is insufficient to complete the Blakely Park project
as currently scoped. An additional $120,000 is needed to cover contingency
and internal staff costs for project related work. Staff recommends transferring
$120,000 of the $140,000 that is allocated for the Legion Park Community
Room Renovation project which intended to bring it up to rentable conditions.
While the community room has the potential to be a source of revenue for the
department its overhaul is not critical to the immediate improvement of the
parks system. The majority of the Blakely project will be funded through a
state grant and has a project deadline of March of 2025. The improvements
will make Blakely a more usable park for the residents of Lodi, enhancing
quality of life for the neighborhood. Should Council accept staff's
recommendation, PRCS plans to use the remaining $20,000 allocated for
Legion for immediate cosmetic repairs and anticipates requesting additional
funding in the future to complete the originally intended project.
FUNDING AVAILABLE: Budgeted Fiscal Year 2021/22 -
State Grant Funds (20599000.77020): $ 882,340
Parks Capital (43299000.77020): $ 30,000
Requested Transfer:
From PKCP-22001. Contracts (Legion Park Project)
To PKCP-20003. Contracts (432) $ 120,000
TOTAL: $ 1,032,340
Susan Bjork, Budget Manager for:
Andrew Keys
Deputy City Manager/Internal Services Director
J_j� LLD
Charles E. Swimley, Jr.
Public Works Director
Prepared by Alice Bernardino, Associate Civil Engineer
CES/AB/cd
Attachments
cc: Parks Project Coordinator
PRCS Director, Jaromay
\\cvcfilv02\pubwks$\WP\PROJECTS\PARKS\Blakely Park\Ball Field\CAward.docx 11/17/2021
BLAKELY PARK SPORT FIELDS & IRRIGATION IMPROVEMENTS
1050 South Stockton Street CONTRACT
CITY OF LODI, CALIFORNIA
THIS CONTRACT made by and between the CITY OF LODI, State of California, herein referred
to as the "City," and EMERT CONSTRUCTION, INC., a California Corporation, herein referred
to as the "Contractor."
WITNESSETH:
That the parties hereto have mutually covenanted and agreed, and by these presents do
covenant and agree with each other, as follows:
The complete Contract consists of the following documents which are incorporated herein by this
reference, to -wit:
Notice Inviting Bids
Information to Bidders
General Provisions
Special Provisions
Bid Proposal
Contract
Contract Bonds
Plans
The July 1992 Edition,
Standard Specifications,
State of California,
Business and Transportation Agency,
Department of Transportation
All of the above documents, sometimes hereinafter referred to as the "Contract Documents," are
intended to cooperate so that any work called for in one and not mentioned in the other is to be
executed the same as if mentioned in all said documents.
ARTICLE I - That for and in consideration of the payments and agreements hereinafter
mentioned, to be made and performed by the City and under the condition expressed in the two
bonds bearing even date with these presents and hereunto annexed, the Contractor agrees with
the City, at Contractor's cost and expense, to do all the work and furnish all the materials except
such as are mentioned in the specifications to be furnished by the City, necessary to construct
and complete in a good workmanlike and substantial manner and to the satisfaction of the City
the proposed improvements as shown and described in the Contract Documents which are
hereby made a part of the Contract.
ARTICLE II - The City hereby promises and agrees with the Contractor to employ, and does
hereby employ, the Contractor to provide all materials and services not supplied by the City and
to do the work according to the terms and conditions for the price herein, and hereby contracts
to pay the same as set forth in Section 5.600, "Measurement, Acceptance and Payment," of the
General Provisions, in the manner and upon the conditions above set forth; and the said parties
for themselves, their heirs, executors, administrators, successors and assigns, do hereby agree
to the full performance of the covenants herein contained.
ARTICLE !I! - The Contractor agrees to conform to the provisions of Chapter 1, Part 7, Division 2
of the Labor Code. The Contractor and any Subcontractor will pay the general prevailing wage
rate and other employer payments for health and welfare, pension, vacation, travel time, and
subsistence pay, apprenticeship or other training programs. The responsibility for compliance
with these Labor Code requirements is on the prime contractor.
CONTRACT 4.1 11/04/21
ARTICLE IV - And the Contractor agrees to receive and accept the following prices as full
compensation for furnishing all materials and for doing all the work contemplated and embraced
in this agreement; also for all loss or damage arising out of the nature of the work aforesaid or
from the action of the elements, or from any unforeseen difficulties or obstructions which may
arise or be encountered in the prosecution of the work until its acceptance by the City, and for all
risks of every description connected with the work; also for all expenses incurred by or in
consequence of the suspension or discontinuance of work and for well and faithfully completing
the work, and the whole thereof, in the manner and according to the Plans and Contract
Documents and the requirements of the Engineer under them, to -wit:
The work consists of renovating 5.5 acres of existing park property. The existing turf must be
stripped, and regraded for new park improvements. Work shall also include the installation of a
new 4 -inch water service, new electrical, removal, replacement and installation of new concrete
and chain link fencing. Other new work shall include re -construction of (2) ball diamonds, new
basketball court, sports field amenities, VFD irrigation booster pump, automatic irrigation system,
hybrid Bermuda sod, hydro -seeded turf, underground utilities and other incidental and related
work, all as shown on the plans and specifications for the project.
See Section 6-07 "Description of Bid Items" for additional information.
BID ITEMS
Item
Description
QTY
Ut i
LS
LS
LS
Unit Price
$ 40,400.00
$ 17,641.00
$ 92,234.00
Total
1
Furnish and Install SWPPP
1
$ 40,400.00
$ 17,641.00
i.
$ 92,234.00
2
Mobilization Traffic Control and Temporary
Facilities
1
1
3
Demolition, Clearing, Grubbing and Grading
4
Concrete Walkways
Construct Fencing and Man -gate for Irrigation
Enclosure
5,650
SF
$ 14.26
$ 80,569.00
5
1
LS
$ 18,370.00
$ 18,370.00
6
Water and Irrigation System
1
LS
$ 220,242.00
$ 220,242.00
7
Concrete Basketball Court and Accessories
1
LS
$ 66,432.00
$ 66,432.00
8
Baseball Backstops, Infield, and Accessories
1
LS
$ 110,150.00
$ 110,150.00
9
Furnish Non -Tip Soccer Goals
1
LS
$ 5,000.00
$ 5,000.00
10
Big Roll Hybrid Bermuda Sod
98,000
SF
$ 1.53
$ 149,940.00
11
Hydro -seeded Turf
126,200
SF
$ 0.45
$ 56,790.00
12
90 Day Landscape Maintenance Period
1
LS
$ 39,104.00
$ 39,104.00
TOTAL $ 896 872.00
ARTICLE V - By my signature hereunder, as Contractor, I certify that I am aware of the
provisions of Section 3700 of the Labor Code, which requires every employer to be insured
against liability for workers' compensation or to undertake self-insurance in accordance with the
provisions of that code, and I will comply with such provisions before commencing the
performance of the work of this contract.
ARTICLE VI - It is further expressly agreed by and between the parties hereto that, should there
be any conflict between the terms of this instrument and the Bid Proposal of the Contractor, then
CONTRACT 4.2 11/04/21
this instrument shall control and nothing herein shall be considered as an acceptance of the said
terms of said proposal conflicting herewith.
ARTICLE VII - The City is to furnish the necessary rights-of-way and easements and to establish
lines and grades for the work as specified under the Special Provisions. All labor or materials
not mentioned specifically as being done by the City will be supplied by the Contractor to
accomplish the work as outlined in the specifications.
ARTICLE VIII - The Contractor agrees to commence work pursuant to this contract within 15
calendar days after the City Manager has executed the contract and to diligently prosecute to
completion within 100 CALENDAR DAYS.
ARTICLE IX - State of California Senate Bill 854 requires the following
No contractor or subcontractor may be listed on a bid proposal for a public works project
unless registered with the Department of Industrial Relations pursuant to Labor Code
section 1725.5 [with limited exceptions from this requirement for bid purposes only under
Labor Code section 1771.1(a)].
No contractor or subcontractor may be awarded a contract for public work on a public
works project unless registered with the Department of Industrial Relations pursuant to
Labor Code section 1725.5.
This project is subject to compliance monitoring and enforcement by the Department of
Industrial Relations.
ARTICLE X - Counterparts and Electronic Signatures
This Agreement and other documents to be delivered pursuant to this Agreement may be
executed in one or more counterparts, each of which will be deemed to be an original copy and
all of which, when taken together, will be deemed to constitute one and the same agreement or
document, and will be effective when counterparts have been signed by each of the parties and
delivered to the other parties. Each party agrees that the electronic signatures, whether digital
or encrypted, of the parties included in this Agreement are intended to authenticate this writing
and to have the same force and effect as manual signatures. Delivery of a copy of this
Agreement or any other document contemplated hereby, bearing an original manual or
electronic signature by facsimile transmission (including a facsimile delivered via the Internet), by
electronic mail in "portable document format' (".pdf") or similar format intended to preserve the
original graphic and pictorial appearance of a document, or through the use of electronic
signature software will have the same effect as physical delivery of the paper document bearing
an original signature.
WHEN SIGNING THIS CONTRACT, THE CONTRACTOR AGREES THAT THE TIME OF
COMPLETION FOR THIS CONTRACT IS REASONABLE AND THE CONTRACTOR AGREES
TO PAY THE CITY LIQUIDATED DAMAGES AS SET FORTH IN SECTION 6-04.03 OF THE
SPECIAL PROVISIONS. CONTRACTOR AGREES THAT THIS AMOUNT MAY BE
DEDUCTED FROM THE AMOUNT DUE THE CONTRACTOR UNDER THE CONTRACT.
CONTRACT 4.3 11/04/21
IN WITNESS WHEREOF, the parties to these presents have hereunto set their hands the year
and date written below.
CONTRACTOR: CITY OF LODI, a municipal corporation
By:
Title
STEPHEN SCHWABAUER
City Manager
Date:
Attest:
JENNIFER CUSMIR
City Clerk
(CORPORATE SEAL) Approved As To Form:
JANICE D. MAGDICH
,,KCity Attorney
CONTRACT 4.4 11/04/21
Capital Improvement Plan
FY 2021-2022
Project Title: Blakely Park Sports Fields
I Munis Project Code:
PKCP-20003
#6
Section I: Description
District Nos: 4 Project Length
11/19-8/21 Priority
Normal
Renovation of Blakely Park ball fields, construction of new basketball
court,
installation of irrigation equipment, including booster pump. Work also includes up -dating electrical
and water
infrastructure, new chain link fencing and concrete flat work.
Justification/factor driving project
Awarded State grant of $882,340. Must be completed by 2025.
Additional Information
Grant YR -39-001 Blakely Park Sports Fields; $60,000 appropriated in FY 18/19 in Parks Capital for City staff/permitting costs not expended. Rolling that forward to FY 19/20.
Section II: Estimated Project Costs
Expenditure Prior Years
FY 20/21
FY 21/22
FY 22/23 FY 23124 FY 24/25
FY 25/26 Future Yrs
Total
Estimate
Budget
Contracts $ - $
882,340
$ 120,000
$ 1,002,340
Internal Staff $ - $
30,000
$ 30,000
Total Capital Costs $ - $
912,340
$ 120,000 $
_
- $ - $ -
$ - $ -
$ 1,032,340
Section III: Funding Sources/Methods of Financing
Funding Source(s) Prior Years
FY 20121
FY 21/22
FY 22/23 FY 23124 FY 24125
FY 25/26 Future Yrs
Total
Estimate
Budget
205 - Parks State Grants $ - $
882,340
$ 882,340
432 - Parks&Rec Capital $ - $
30,000
$ 120,000
$ 150,000
Total Project Financing $ - $
912,340
$ 120,000 $
- $ - $ -
$ - $ -
$ 1,032,340
Section IV
Operating Budget Impact
Operating Cost or (savings) Prior Years
FY 20121
FY 21/22
FY 22/23 FY 23124 FY 24125
FY 25/26 Future Yrs
Total
Estimate
Budget
Personnel $ -
$ -
Other Operating Costs $ -
$ -
Total Operating Impact $ - $
-
$ - $
- $ - $ -
$ - $ -
$ -
Capital Improvement Plan
FY 2021-2022
Project Title:
Legion Park Comm Building Renovation
I Munis Project Code: #187
Section I: Description
District Nos: 3 Project Length 60 Days Priority HIGH
This is a revenue generating rental space that has been taken offline due to poor conditions. Project scope includes renovating the interior of the community building to include: new
windows, doors, flooring, cabinetry work,
electrical upgrades, restroom fixtures and sewer line improvements. In addition, new tables and chairs are also included in this scope of this
renovation project.
Justification/factor driving project
Due to its prime, centalized location - Legion Park and it's amenities are heavily used and in high demand. This is a rentable space that has become a lost revenue opportunity due to
unacceptable facility conditions. No improvements to this space have been conducted in over 30 years.
Additional Information
Section II: Estimated Project Costs
Expenditure
Prior Years FY 20121 FY 21122 FY 22123 FY 23124 FY 24125 FY 25126 Future Yrs Total
Estimate Budget
Contracts
$ - $ 5,000 $ 5,000
Internal Staff
$ - $ 15,000 $ 15,000
Total Capital Costs
$ - $ - $ 20,000 $ - $ - 1 $ - $ - $ - $ 20,000
Section III: Funding Sources/Methods of Financing
Funding Source(s)
Prior Years FY 20121 FY 21122 FY 22123 FY 23124 FY 24125 FY 25126 Future Yrs Total
Estimate Budget
432 - Parks&Rec Capital
$ $ 20,000 $ 20,000
Total Project Financing
$ - $ - $ 20,000 $ - $ - $ - $ - $ - $ 20,000
Section IV
Operating Budget Impact
Operating Cost or (savings)
Prior Years FY 20121 FY 21122 FY 22123 FY 23124 FY 24125 FY 25126 Future Yrs Total
Estimate Budget
+
Personnel
$ - $ -
Other Operating Costs
$ - $ -
Total Operating Impact
$ - $ - $ - $ - $ - $ - $ - $ - $ -
RESOLUTION NO. 2021-315
A RESOLUTION OF THE LODI CITY COUNCIL APPROVING PLANS AND
AWARDING THE CONTRACT FOR BLAKELY PARK SPORT FIELDS AND
IRRIGATION IMPROVEMENTS TO EMERT CONSTRUCTION, OF
STOCKTON; AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE
ORDERS; AND TRANSFERRING FUNDS
WHEREAS, in 2017, the City was awarded a grant from the State Parks, Office of
Grants and Local Services in the amount of $882,340 for the Blakely Park Sports Fields and
Irrigation Improvements; and
WHEREAS, this project provides for new turf, irrigation system, basketball court, soccer
field, and baseball diamond renovations at Blakely Park. The new irrigation system, including a
booster pump, is estimated to save approximately 1 million gallons of water per year; and
WHEREAS, the specifications for this project were approved on August 18, 2021, and
the City received the following bids for this project on November 03, 2021:
WHEREAS, the bids for this project came in higher than the grant amount awarded for
the project, therefore, staff proposes to offset the funding deficit by transferring funds allocated
for the Legion Park Community Room renovation (PKCP-22001. Contracts) which was approved
in the FY 22 CIP Program; and
WHEREAS, staff recommends approving plans and awarding the contract for Blakely
Park Sports Fields and Irrigation Improvements to Emert Construction, of Stockton, in the
amount of $896,872; and
WHEREAS, staff further recommends authorizing the City Manager to execute change
orders in an amount not to exceed $135,000; and
WHEREAS, staff further recommends transferring funds in the amount of $120,000 from
the Legion Park Community Room Project (PKCP-22001. Contracts) to the Blakely Park Sports
Field Improvements Project (PKCP-20003. Contracts. Parks).
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby approve
the plans and award the contract for Blakely Park Sports Fields and Irrigation Improvements to
Emert Construction, of Stockton, California, in the amount of $896,872; and
BE IT FURTHER RESOLVED that the Lodi City Council does hereby authorize the
City Manager to execute the contract and change orders in an amount not to exceed $135,000;
and
BE IT FURTHER RESOLVED that the Lodi City Council does hereby authorize the
transfer of funds in the amount of $120,000 as set forth above; and
Above/(Below)
Bidder
Location
Bid
Engineer's Estimate
Marina Landscape*
Orange
$864,105
$(805)
Emert Construction
Stockton
$896,872
$31,962
A.M. Stephens Construction
Lodi
$1,035,889
$170,979
Stockbridge General Contracting
Clovis
$1,215,068
$350,158
Suarez & Munoz Construction
Hayward
$1,237,340
$372,430
*non-responsive
WHEREAS, the bids for this project came in higher than the grant amount awarded for
the project, therefore, staff proposes to offset the funding deficit by transferring funds allocated
for the Legion Park Community Room renovation (PKCP-22001. Contracts) which was approved
in the FY 22 CIP Program; and
WHEREAS, staff recommends approving plans and awarding the contract for Blakely
Park Sports Fields and Irrigation Improvements to Emert Construction, of Stockton, in the
amount of $896,872; and
WHEREAS, staff further recommends authorizing the City Manager to execute change
orders in an amount not to exceed $135,000; and
WHEREAS, staff further recommends transferring funds in the amount of $120,000 from
the Legion Park Community Room Project (PKCP-22001. Contracts) to the Blakely Park Sports
Field Improvements Project (PKCP-20003. Contracts. Parks).
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby approve
the plans and award the contract for Blakely Park Sports Fields and Irrigation Improvements to
Emert Construction, of Stockton, California, in the amount of $896,872; and
BE IT FURTHER RESOLVED that the Lodi City Council does hereby authorize the
City Manager to execute the contract and change orders in an amount not to exceed $135,000;
and
BE IT FURTHER RESOLVED that the Lodi City Council does hereby authorize the
transfer of funds in the amount of $120,000 as set forth above; and
BE IT FURTHER RESOLVED, pursuant to Section 6.3q of the City Council Protocol
Manual (Res. No. 2019-223), the City Attorney is hereby authorized to make minor revisions to
the above -referenced document(s) that do not alter the compensation or term, and to make
clerical corrections as necessary.
Dated: December 1, 2021
I hereby certify that Resolution No. 2021-315 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held December 1, 2021, by the following vote:
AYES: COUNCIL MEMBERS — Chandler, Hothi, Khan, Kuehne, and
Mayor Nakanishi
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
w
N FE U MIR
City Clerk
2021-315