HomeMy WebLinkAboutAgenda Report - January 20, 2021 C-07AGENDA ITEM Cw7 CITY OF LODI COUNCIL COMMUNICATION TM AGENDA TITLE; Accept Improvements Under Contract for Citywide Bicycle Facilities Detection Improvement Project MEETING DATE: January 20, 2021 PREPARED BY: Public Works Director RECOMMENDED ACTION: Accept improvements under contract for Citywide Bicycle Facilities Detection Improvement Project. BACKGROUND INFORMATION: This project included installing 13 bike/traffic video detection systems on existing traffic signals, painting 6,775 linear feet of green bike stripe, and other incidental and related work. The contract was awarded to St Francis Electric, LLC, of San Leandro, in the amount of $740,795, on April 15, 2020. The final cost of the project is $643,494.82. The difference between the original contract amount and the final contract amount is due to three contract change orders. Change Order No.1 was to modify the originally proposed green bike lane configurations to green bike stripes as indicated in the project award staff report with a net saving of $108,975. Change Order No. 2 ($10,437.61) was to add video detection cameras on Lodi Avenue at Crescent Avenue to replace the damaged traffic detection loops in Lodi Avenue, Change Order No. 3 ($1,237.21) was to repair a damaged traffic signal pole at Lower Sacramento Road and Sunwest Plaza intersection. All work was completed in substantial conformance with the plans and specifications approved by City Council. The contract was completed on December 18, 2020 which is later than the expected date of October 25, 2020. This is due to another City project on Lower Sacramento Road which caused delays in the final striping operation. The project location map is shown on Exhibit A and photos of the completed work are shown in Exhibit B. Following acceptance by the City Council, as required by law, the City Engineer will file a Notice of Completion with the County Recorder's office. The notice serves to notify vendors and subcontractors that the project is complete and begins their 30 -day period to file a stop notice requiring the City to withhold payments from the prime contractor in the event of a payment dispute. FISCAL IMPACT: There will be an increase in future maintenance cost to maintain the new green bicycle striping. APP K:\WP\PROJECTS\STREETS\Cltywide Bike Detection\CAccept.doc Manager 115/2021 Ar:c:c:pi Improvements Under Contract for Citywide Bicycle Facilities Detection Improvement Project .Januafy 20, 2021 Page 2 FUNDING AVAILABLE: This project was funded by Active Transportation Program Grant, TDA Streets, and Street Fund. CharI6"s E. SWlmIey, Jr. Public Works Director Prepared by Lyman Chang, City Engineer/Deputy Public Works Director CES/LC/tc Attachments cc: Utilities Manager Engineering Technician, Mangrich Public Works Management Analyst St Francis Electric, LLC KIWMPROJECT&STREETS01tywide Bike Detection\CAccept.doc 1/5/2021 r aj v En C) n a CL CD o v �m v 3� -< Op rn In r M M �m M z C JIMN IF 01000 III no I no a mom W HO well EXHIBIT B CITY WIDE BICYCLE FACILITIES DETECTION PROJECT VIDEO DETECTION CAMERA sv; �p,N.,o�r± . }• ra