HomeMy WebLinkAboutAgenda Report - May 6, 2020 C-06c-b
Crrv or Loor
CouNcIl, CovTMUNICATIoN
TM
AGENDA TITLE:
MEETING DATE:
PREPARED BY:
Adopt Resolution Approving 202012021 Pavement Resurface Project for Road
Repair and Accountability Act of 2017 Funding
May 6, 2020
Public Works Director
RECOMMENDED ACTION Adopt resolution approving 202012021 Pavement Resurface Project
for Road Repair and Accountability Act of 2017 funding.
BACKGROUND INFORMATION The Road Repair and Accountability Act of 2017, Senate Bill 1
(SB1), will provide the City with State transportation funding through
an increase in the Gas Tax.
SB1 guidelines require that prior to receiving an apportionment of funds for this fiscal year, agencies
must prepare and submit a list of proposed SB1-funded projects to the California Transportation
Commission. All proposed projects must also be included or amended into the City's adopted budget
each year. The City is proposing to use the FiscalYear 2020121 allocation (estimated $1,289,442), and
a portion of the previous year apportionment, for the 202012021 Pavement Resurface Project.
The 202012021 Pavement Resurfacing Project, programmed for Fiscal Year 2020121, includes pavement
repairs and installing rubberized cape seal and slurry seal on various streets, as shown on Exhibit A.
The pavement resurfacing will prevent further deterioration of the streets before they have structural
damage. The work will also include pavement repair, pavement striping, and other miscellaneous and
related work.
Staff will later request Council action to approve plans and specifications and authorize advertisement for
bids and to award the contract, once the plans, specifications, and estimates are complete. The
preliminary project estimate is $1,330,000.
The pavement repair project will include pavement repairs and installing rubberized cape seal and slurry
seal in the neighborhoods bound by Lockeford Street to the north, Cherokee Lane to the east, Vine
Street to the South, and Virginia Avenue to the west. The pavement resurfacing project will extend the
pavement life for 10 years. The work will be performed from July 2020 through June 2021.
Staff recommends approving 202012021 Pavement Resurface Project for Road Repair and
Accountability Act of 2017 funding.
FISCAL IMPACT:Not applicable
APPROVED
K:WVP\COUNCIL\2020\CSBl project.doc
n uer, City Manager
4t2312020
Adopt Resolution Approv¡ng 202012021 Pavement Resurface Project for Road Repa¡r and Accountability Act of 2017 Funding
May 6,2O2O
Page 2
FUNDING AVAILABLE Funding will be budgeted in FiscalYear 2020121 Road Repair and
Accountability Act (30499000.77 020).
Charles E. Swimley, Jr
Public Works Director
CES/LC/tc
Attachment
cc:Senior Civil Engineer
Public Works Management Analyst
K:\\ /P\COUNCIL\2020\CSBl projec{.doc 4t2312020
KettlemanLn.
Lockeford St.Hutchins St.Century Blvd.Church St.Pine St.
Elm St.
L o d i A v .Ham Ln.Cherokee Ln.Stockton St.Virginia Av.Central Av.V i n e S t .Lee Av.Washington St.Garfield St.Pleasant Av.O a k S t .
W a l n u t S t .
Locust St.
Railroad Av.
Exhibit AProject Locations µ
0 0.25 0.50.125
Miles
Legend
Cape Seal
Slurry Seal