HomeMy WebLinkAboutResolutions - No. 2020-70RESOLUTION NO. 2O2O-70
A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING THE
CITY MANAGER TO EXECUTE PROFESSIONAL SERVICES
AGREEMENT WITH CAROLLO ENGINEERS, INC., OF WALNUT
CREEK, FOR PROGRESSIVE DESIGN BUILD CONSTRUCTION
DOCUMENTS FOR WHITE SLOUGH WATER POLLUTION CONTROL
FACILITY SOLIDS HANDLING EQUIPMENT PROCUREMENT AND
INSTALLATION PROJECT; AND FURTHER APPROPRIATING FUNDS
WHEREAS, biosolids are anaerobically digested and then directed to a concrete-lined
sludge stabilization lagoon at the City's White Slough Water Pollution Control Facility
(WSWPCF) and dewatered to a solids content of about 12 percent and stockpiled in an
enclosed facility then applied to approximately 700 acres of the City's agricultural fields; and
WHEREAS, recently, applied biosolids occasionally exceeded the vector attraction
reduction rate because the volatile solids reduction requirement was not achieved in the
anaerobic digestion process, primarily resulting from operational challenges associated with the
current biosolids dewatering system which translates into a downstream lack of digester
capacity to adequately treat solids loading from the treatment plant processes; and
WHEREAS, the proposed Solids Handling Equipment Procurement and lnstallation
Project is intended to improve solids treatment processes; and
WHEREAS, staff recommends authorizing the City Manager to execute a Professional
Services Agreement with Carollo Engineers, lnc., of Walnut Creek, for progressive design build
construction documents for White Slough Water Pollution Control Facility Solids Handling
Equipment Procurement and lnstallation Project, in the amount of $162,500; and
WHEREAS, staff also recommends the City Council appropriate funds in the amount of
$162,500, from the fund balance of Wastewater Capital (53199000.77020) for Fiscal Year
2019t20.
NOW, THEREFORE, BE lT RESOLVED that the Lodi City Council does hereby
authorize the City Manager to execute a Professional Services Agreement with
Carollo Engineers, lnc., of Walnut Creek, California, for progressive design build construction
documents for White Slough Water Pollution Control Facility Solids Handling Equipment
Procurement and lnstallation Project, in the amount of $162,500; and
BE lT FURTHER RESOLVED that the Lodi City Council does hereby authorize an
appropriation for the project, in the amount of $162,500, as set forth above; and
BE lT FURTHER RESOLVED, pursuant to Section 6.3q of the City Council Protocol
Manual (Res. No. 2019-223), the City Attorney is hereby authorized to make minor revisions to
the above-referenced document(s) that do not alter the compensation or term, and to make
clerical corrections as necessary.
3::"=1===fj]ji=393:=====================================================
I hereby certify that Resolution No. 2020-70 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held April 15, 2020, by the following vote:
AYES: COUNCIL MEMBERS - Chandler, Mounce, Nakanishi, and Mayor Kuehne
NOES:
ABSENÏ:
ABSTAIN
COUNCIL MEMBERS - None
COUNCIL MEMBERS - None
COUNCIL MEMBERS - None A-r."/øW|trñ'''1/¿t'
PAMELA M. FARRIS
Assistant City Clerk
2020-70