HomeMy WebLinkAboutMinutes - June 25, 2019 SSLODI CITY COUNCIL
SHIRTSLEEVE SESSION
CARNEGIE FORUM, 305 WEST PINE STREET
TUESDAY, JUNE 25, 2019
A. Roll Call by City Clerk
An Informal Informational Meeting ("Shirtsleeve" Session) of the Lodi City Council was held
Tuesday, June 25, 2019, commencing at 7:04 a.m.
Present: Council Member Nakanishi, Mayor Pro Tempore Kuehne, and Mayor Chandler
Absent: Council Member Johnson, and Council Member Mounce
Also Present: City Manager Schwabauer, City Attorney Magdich, and City Clerk Ferraiolo
B. Topic(s)
B-1 Receive Information Regarding White Slough Water Pollution Control Facility Update (PW)
Public Works Director Charlie Swimley provided a PowerPoint presentation regarding White
Slough Water Pollution Control Facility (WSWPCF) update. Specific topics of discussion
included WSWPCF location, WSWPCF property, treatment plant, project history, 2016 corrosion
repair project, corroded concrete channel repair, replacement of 24-inch aeration pipe, repairs to
Digester No. 3 cover, 2017 SCADA upgrade project, arc-flash study, SCADA system upgrade,
recycled water pond storage project, recycled water permit for new storage pond, visual
examples, and planned capital projects.
Mr. Swimley introduced Mark Kindelberger with Schneider Electric to explain the Energy Service
Company (ESCO) procurement process, something the City of Lodi has not yet participated in but
could benefit greatly from in the form of savings.
Mr. Kindelberger explained that his division with Schneider Electric operates as an ESCO, which
provides energy solutions including designs and implementation of energy savings projects. The
California Government Code allows municipalities to enter into contracts with such providers, and
the projects pay for themselves with the savings. Both the design and construction of a project is
contracted to a single entity, which makes the design to build delivery time faster because there is
an intense collaboration between the City and the partners in the design phase. The project
would be offered for a fixed bid with no change orders, and because it is a single entity, his
company would be responsible for everything and the City would have a guarantee of utility
savings that could be used to service any debt on the project. There are three phases: design;
construction; and customer support, measurement, and verification. He stated that, between the
design and construction phase, if the City determined it could not accomplish a viable project, it
could cancel the project, and the City would only be accountable for any design to date fees
incurred.
In response to Council Member Nakanishi, Mr. Kindelberger stated that, if the City borrows
money for the project, the City would have a guaranteed utility savings that could pay for the debt.
Mr. Swimley added that the City's plan is to pay for the project on a pay-as-you-go basis.
In response to Mayor Pro Tempore Kuehne, Mr. Swimley stated the savings would be roughly
$100,000 a year.
Council Member Nakanishi questioned if this savings would offset rate increases. Mr. Swimley
stated that installation of the blower project will help the City control rates better and reduce the
overall operations of the facility. Mr. Schwabauer added that it will help provide cash for the
remaining improvements once the payback period is ended.
1
C. Comments by Public on Non-Agenda Items
None.
D. Adjournment
No action was taken by the City Council. The meeting was adjourned at 8:00 a.m.
ATTEST:
Jennifer M. Ferraiolo
City Clerk
2
White Slough Water Pollution
Control Facility Update
Shirtsleeve Meeting
June 25, 2019
Outline
•Facility Overview
•Project History
•Planned Capital Projects
•Questions
WSWPCF Location
Discharge Point BISHOP CUT
WSWPCF Property
Municipal Wastewater
Industrial Wastewater
Recycled
Water
Storage
Pond
Treatment Plant
Biosolids
Lagoons
Secondary
Clarifiers
Primary
Clarifiers
Sludge
Digesters
Tertiary Filters and
UV Disinfection
Secondary
Aeration Basins
Project History
•July 2016 – Corrosion Repair Project
•May 2017 – SCADA Upgrade Project
- Arc Flash Study
- SCADA System Upgrade
- Predesign of Future Improvements
•April 2018 - Recycled Water Pond Storage Project
- 300 AF Recycled Water Storage Pond
- Title 22 Tertiary Water
- Proposition 84 Grant Funded (75%)
•Scope of Work:
–Repaired corroded concrete channels upstream of aeration
basins;
–Replaced corroded steel 24-inch diameter aeration pipeline
–Repaired corroded steel cover of Digester No. 3
–Installed water level sensors in storage pond
–Installed temperature sensors on digester heat-exchanger piping
•Schedule – July 2016 to September 2017
•Construction Cost - $1,989,872
2016 Corrosion Repair Project
Corroded Concrete Channel Repair
Typical channel following
cleaning and sand-blasting,
prior to repair.
Channel following repairs
and application of both
epoxy-mortar and
polyurethane coatings.
Replacement of 24-Inch Aeration Pipe
Pipe that was replaced. New concrete-encased
stainless steel pipe.
Repairs to Digester No. 3 Cover
Corrosion created holes
and pitted areas in the
interior of the steel
cover.
Steel plates were
welded over the holes
and pitted areas and
the cover was coated
with chemical-resistant
epoxy coating.
•Scope of Work
–Arc-Flash Study
–SCADA System Upgrade
–Investigate UV System Communication Problem
–Preliminary Design of Future Improvements
•Schedule – May 2017 to October 2019
•Cost - $770,010
2017 SCADA Upgrade Project
•Arc-flash is not shock (current flow through a body).
•Arc-flash is physical energy (heat, pressure wave, sound)
released by a short circuit; an arc-welder is a controlled
arc-flash.
•Arc-flash study complete.
•On-going safety effort.
Arc-Flash Study
Arc-Flash Study
•Findings
- Existing electrical equipment is aging, spare parts difficult to find.
- Arc-flash exposure risk varies throughout the plant.
•Actions taken
- Arc-flash exposure data base.
- Settings on equipment protective devises modified to reduce arc
flash risk.
- Conducted OSHA certified training for WSWPCF staff.
•Scope of Work:
–Replace existing / aging server with pair of modern / redundant
servers in dedicated server rack
–Replace existing obsolete graphical control system
–Replace obsolete graphics.
•Benefits:
–Increased reliability – regulatory compliance
–Simplify treatment process troubleshooting and plant diagnostics
–Increased data acquisition
–Increased security
–Allows for wireless support (tablets, etc.) for monitoring and
process control
SCADA System Upgrade
•Scope of Work:
–Construct 300 acre-ft. Storage Pond
–Install pump station and conveyance piping
–Install electrical instrumentation
–Modify existing structures
•Benefits:
–Minimizes discharge to Delta
–Expands recycled water opportunities
–Benefits groundwater recharge – Sustainable Groundwater
Management Act (SGMA)
•Schedule – April 2018 to July/August 2019
•Cost - $5,125,000
Recycled Water Pond Storage Project
Recycled Water Pond Storage Project
Recycled Water Pond Storage Project
Recycled Water Permit for New Storage Pond
•December 2018: Regional Water Board
issued the City a permit under the
Recycled Water General Order
–Storage and use of high-quality recycled
water (Disinfected Tertiary) in the new pond
–Providing recycled water for offsite, public
use
–Specific offsite uses not yet identified, but
could include:
•Landscape irrigation
•Construction activities
•Dust control
•Crop irrigation
•Aeration Blower Upgrade Project
–Install 2 new variable speed blowers
–Energy savings
–Increased process control
–Cost $750,000
–FY 2019/20
•Considering Energy Service Company (ESCO)
procurement
Planned Capital Projects
•South Electric Building Replacement Project
–Relocate existing electric building
–Upgrade obsolete electric infrastructure
–Building components reaching useful life
–Coarse screen and septage receiving improvements
–Aeration diffuser improvements
•Schedule: Design FY19/20 > 20/21 = $1.5M
• Construction FY21/22 > 23/24 = $13.5M
•Cost: $15,000,000
Planned Capital Projects
•Fan Press Installation Project
–Install additional fan press
•Schedule: Construction FY23/24
•Cost: $1,000,000
Planned Capital Projects
Visual Examples
Visual Examples
Planned Capital Projects
FY 19-20 FY 20-21 FY 21-22 FY 22-23 FY 23-24
Irrigation Improvements $750,000
Electrical/Screen Design $900,000 $600,000
Electrical/Screen Construction $1,000,000 $7,000,000 $5,500,000
Miscellaneous Future Projects $100,000
Cloth Filter Media Replacement $30,000 $30,000 $30,000 $30,000 $30,000
Primary Chain Flights $40,000 $40,000 $40,000
NCPA Maintenance Generator $150,000 $150,000 $150,000 $150,000 $150,000
Emergency Generator Maintenance $30,000 $30,000 $30,000 $30,000 $30,000
Compliance Studies and Reports $200,000 $200,000 $200,000 $200,000 $200,000
Upgrade Blowers $750,000
Aeration Diffuser Replacement $500,000
Pond Gates $15,000 $15,000
Band Screen Rebuild $75,000
Primary Skimmers $20,000
Secondary Scum Trough Drives $20,000
DWP-H2 Replacement $15,000 $15,000
Fan Press Replacement $1,000,000
$2,215,000 $1,120,000 $2,200,000 $7,960,000 $6,950,000
Planned Capital Projects
FY 24-25 FY 25-26 FY 26-27 FY 27-28 FY 28-29 FY 29-30
Irrigation Improvements $1,000,000 $1,750,000
Cloth Filter Media Replacement $30,000 $30,000 $30,000 $30,000 $30,000 $30,000
Primary Chain Flights $40,000 $40,000 $40,000
NCPA Maintenance Generator $150,000 $150,000 $150,000 $150,000 $150,000 $150,000
Emergency Generator Maintenance $30,000 $30,000 $30,000 $30,000 $30,000 $30,000
Compliance Studies and Reports $200,000 $200,000 $200,000 $200,000 $200,000 $200,000
UV Design/Replacement $450,000 $4,000,000
DWP-H2 Replacement $15,000
Unspecified Treatment Plant Rehab $1,000,000 $1,000,000 $1,000,000
$1,425,000 $900,000 $6,160,000 $1,450,000 $1,410,000 $1,450,000
Questions???