AGENDA TITLE: Adopt Resolution Authorizing City Manager to Execute Change Orders to 2018
Pavement Crack Sealing Project ($30,000) and Appropriating Funds ($19,000)
MEETING DATE: April 17, 2019
PREPARED BY: Public Works Director
RECOMMENDED ACTION:
BACKGROUND INFORMATION:
Adopt resolution authorizing City Manager to execute change orders
to 2018 Pavement Crack Sealing Project, in an amount not to
exceed $30,000, and appropriating funds in the amount of $19,000.
On November 7, 2018, Council awarded the contract for the 2018
Pavement Crack Sealing Project to Pavement Coatings, Co., of
Woodland, in the amount of $38,870.
While originally not planned for crack sealing until a later date, Beckman Road, from Pine Street to
Kettleman Lane, has developed extensive cracking, as shown in Exhibit A, and should be addressed as
soon as possible. Staff requested a proposal from the contractor to include Beckman Road into the
scope of work before further degradation requires more costly pavement resurfacing or replacement.
The location of the proposed work is shown in Exhibit B.
The contractor provided a proposal for additional crack sealing, including traffic control, in the amount of
$26,614 (Exhibit C). Staff recommends authorizing the City Manager to execute change orders up to
$30,000 to cover any minor changes that may arise during the additional work. If approved, the new
contract amount will be $65,484. The difference between the new contract amount and the requested
appropriation ($69,000) is to account for minor unforeseen changes in the remaining work.
Staff recommends authorizing City Manager to execute change orders to 2018 Pavement Crack Sealing
Project, in an amount not to exceed $30,000, and appropriating funds in the amount of $19,000.
FISCAL IMPACT: By increasing the crack sealing effort, the useful life of Beckman Road will
be extended. This project does not impact the General Fund.
APPROVED:
ep en Sch
uer, City Manager
K:\WP\PROJECTS\STREETS\2018 Crack Seal\CAppropriate.doc 4/8/2019
Adopt Resolution Authorizing City Manager to Execute Change Orders to 2018 Pavement Crack Sealing Project ($30,000) and Appropriating Funds ($19,000)
April 17, 2019
Page 2
FUNDING AVAILABLE Fiscal Year 2018/19 Budget (Original Budget Amount):
TDA Streets (30599000.77020) $50,000
Requested Additional Appropriation:
Pavement Maintenance (PWST-0018. Const.ExtLabor.TDA ST): $19,000
TOTAL: $69,000
n is
)61-71
Andrew Keys
Deputy City Manager/Internal Services Director
Charles E. Swimley, Jr.
Public Works Director
Prepared by Jimi Billigmeier, Associate Civil Engineer
CES/JB/tdb
Attachments
cc: Utility Superintendent
K:\WP\PROJECTS\STREETS\2018 Crack Seal\CAppropriate.doc 4/8/2019
Exhibit A
2018 Crack Sealing Project
Change Order 1 — Beckman Road
■
II,
W. TI rn IrIRd.
Is
Air
n
Exhibit B
2018 Crack Seal Locations
Change Order 1
2018 Crack Seal Contract Locations
Change Order 1
Turner Rd.
Elm
St.
Turner Rd.
III"
d
Q Locke
fLiI Elm
St.
••.`'. L-� =i=
o nnnrbH dl Ave
.
N
S
0 0.25 0.5 1
Miles
E•/Turner Rd.
C$co F-1
co
Lockeford St.
Vine
St
e11111
■
Kettleman Ln. 111
traria 11 ro
Century Blvd. o Century
RIENbotr-ii Mr rim..
co�Blvd.
K:\WP\PROJECTS\STREETS\2018 Crack Seal\Exhibit B.mxd
I l
_100 d
O
m
U
1
■
U
Victor
Rd.(HWY
12)
Gui
—Lodi Ave.
2 ce
Pine St-
Pavement Coatings Co
2150 Bell Ave, Ste 125
Sacramento, CA 95838
Phone: (916) 642.1751 1 Fax (916) 313.3438
CA Lic. #303609
NV Lic. #79452 A
CONTRACT CHANGE ORDER REQUEST
TO: City of Lodi
ATTN: Jimi Billigmeier DATE: 3/13/2019
Public Works Department Associate Civil Eng.
221 W. Pine Street
P.O. Box 3006
Lodi, CA 95241
PROJECT : 2018 Pavement Crack Sealing
PCC Job #:
PJC000672
RE: Potential Additional Work -
Crack Seal - Beckman Rd
GAP Mastic - Cluff Ave
PCC Change Order # : CCOR-001
Contract Change Order #:
ITEM DESCRIPTION QTY UNIT UNIT PRICE TOTAL AMOUNT
1
Crack Seal Beckman Rd from Lodi Ave to Kettleman Ln
234,600
SF
$ 0.09
$ 21,114.00
2
Additional Traffic Control - Beckman Rd Crack Seal
1
LS
$ 5,500.00
$ 5,500.00
$ -
3
Apply Mastic - GAP Mod 201 in oversized cracks on
1100
LF
$ 25.50
$ 28,050.00
Cluff Ave from Pine St to Lodi Ave - Not Used
$ _
$ -
$ -
$ -
$ -
TOTAL CHANGE ORDER REQUEST
$ 54,664.00
$26,614.00
CONTRACT TIME EXTENSION REQUEST I 4
(ADD'L WORKING DAYS)
:ONDITIONS/SCOPE:
Please see attached for General Conditions, Job Inclusions, and Exclusions.
NAME/ TITLE (PRINTED):
SIGNED:
DATE:
PCC REPRESENTATIVE
NAME/ TITLE (PRINTED):
SIGNED:
DATE:
OWNER/PRIME REPRESENTATIVE
Pavement Coatings Co
2150 Bell Ave, Ste 125
Sacramento, CA 95838
Phone: (916) 642.1751 1 Fax (916) 313.3438
CA Lic. #303609
NV Lic. #79452 A
Gomm, Conditions
1 Pavement Coatings Ca is Signatory to the Master Labor Agreement
2 All work described is based on estimated quantity listed above and shall be a minimum, overruns to be paid at unit price.
3 The work listed above i5 CCO 44 l which is to crack seal and apply Gap Mastic to areas identified on job walk.
Job inclusions
1 All *ark per Provisions & Contract Documents. Tax Included
2 This Quote is to become part of the Contract Documents
Job Exclusions
1 Asphalt repair, weed spray. heavy cleaning, removal or replacement of striping, markings or markers, bonds, fees, permits or inspection.
2 Traffic Control Plans
3 Portable Changeable Message Boards, Contruction Area Signs, Arrow Boards
General Conditions
teem- MN 30 days.
Any indcrnndy arra jefense obI ahpn requ.ed from PCC shall be pnvoroanal and Wiwi ra the ealoat PCC'f aCr%, or t 3iont Faun, W neghnence contribute tow* alleged or actual
claims or damages Insurance included in this &d: Cpmmerodt Laabrluy 31MM per occvrarxe 1 S2MM aggregate, SAM Products and Complied Operatigms Agyreyare, 51MM Personal
and Ad.ertts ng Injury, 51MM Commercial Auto, workers Compensation coverage per statute
RESOLUTION NO. 2019-53
A RESOLUTION OF THE LODI CITY COUNCIL AUTHORIZING
THE CITY MANAGER TO EXECUTE CHANGE ORDERS TO
2018 PAVEMENT CRACK SEALING PROJECT; AND
FURTHER APPROPRIATING FUNDS
WHEREAS, on November 7, 2018, Council awarded the contract for the 2018 Pavement
Crack Sealing Project to Pavement Coatings Company, of Woodland, in the amount of $38,870;
and
WHEREAS, contract change orders are generally used to formalize changes in
construction and maintenance contracts to add to or subtract from the scope of work; and
WHEREAS, staff recommends authorizing the City Manager to execute change orders
to the 2018 Pavement Crack Sealing Project, in an amount not to exceed $30,000; and
WHEREAS, staff recommends the City Council appropriate funds in the amount of
$19,000 from the fund balance of Pavement Maintenance (30599000.77020) for Fiscal Year
2018/19.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby
authorize the City Manager to execute change orders to the 2018 Pavement Crack Sealing
Project, in an amount not to exceed $30,000; and
BE IT FURTHER RESOLVED that the Lodi City Council does hereby authorize an
appropriation for the 2018 Pavement Crack Sealing Project, in the amount of $19,000, as set
forth above.
Dated: April 17, 2019
I hereby certify that Resolution No. 2019-53 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held April 17, 2019, by the following vote:
AYES: COUNCIL MEMBERS — Johnson, Kuehne, Mounce, Nakanishi, and
Mayor Chandler
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — None
ABSTAIN: COUNCIL MEMBERS — None
2019-53