HomeMy WebLinkAboutAgenda Report - January 16, 2019 C-03TM
CITY OF LODI
COUNCIL C O M MUNICATION
AGENDA ITEM
C-3
AGENDA TITLE: Approve Plans and Specifications and Authorize Advertisement for Bids for Lodi
Station Parking Garage Elevator Structural Repair Project
MEETING DATE: January 16, 2019
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Approve plans and specifications and authorize advertisement for bids
for Lodi Station Parking Garage Elevator Structural Repair Project.
BACKGROUND INFORMATION: The Lodi Station Parking Garage, located at 50 North Sacramento
Street, has two elevators to convey patrons to all three floors of the
parking structure. On May 15, 2018, a patron, driving a vehicle, hit the
north elevator shaft, located on the third floor. The impact caused substantial damages to the elevator
equipment and elevator shaft.
Staff contracted Siegfried Engineering, Inc., of Stockton, to perform a structural assessment of the elevator
structure after the incident. The assessment report (Exhibit A) determines the elevator structure to be safe
but needs structural repair and new elevator equipment to make it operable.
This project consists of performing structural repair to the damaged elevator shaft and exterior wall of the
parking structure. The work will prepare the elevator shaft for a separate elevator contractor to perform the
elevator equipment repair after the structural repair work is complete.
The plans and specifications are on file in the Public Works Department. The planned bid opening date is
February 21, 2019. The project estimate for the structural repair $100,000. Staff will enter into a separate
agreement with an elevator contractor, at a later date, to perform the elevator equipment repair work.
FISCAL IMPACT:
The cost to make the necessary repairs to the structure, elevator replacement,
and all engineering and Staff time spent on this incident will initially be funded
by Transit Capital and recovered through insurance claims.
FUNDING AVAILABLE: Funding will be identified at project award.
C
Charles E. Swimley, Jr.
Public Works Director
Prepared by Lyman Chang, Deputy Public Works Director/ City Engineer
CES/LC/tdb
Attachment
cc: Siegfried Engineering, Inc.
Deputy Public Works Director/City Engineer
Transportation Manager
Facility Supervisor, Sanford
APPROVED: 1117_,F‘
mp
ep en Sch
K:\WP\PROJECTS\TRANSIT\Lodi Station Parking Structure\2018 Elevator Repair\CC PS&A.doc
, City Manager
12/18/2018
Page 1
August 22, 2018
Lyman Chang
City of Lodi
Public Works Department
221 W. Pine Street
Lodi, CA 95240
Dear Mr. Chang:
Subject: Lodi Station Parking Garage North Elevator Damage
Structural Investigation
■
■
SIEGFRIED
As requested, we conducted an investigation of the Lodi Station Parking Garage building located on the east side of
Sacramento Street between East Elm and East Pine Streets. This investigation focused on the structural damage to the
elevator on the north side of the facility as a result of vehicular damage that occurred on May 5th 2018. The purpose of this
investigation was to provide structural engineering observations of the elevator and surrounding structural elements to
identify structural damage or dangerous conditions, and to provide general recommendations for further investigations
and/or repairs. This investigation did not include testing, destructive examinations or analysis of the structure. The following
is a summary of our observations, findings and recommendations.
General Information
The vehicle damage occurred on the third (top) level of the parking structure at the north elevator. The vehicle accelerated
through the third level elevator shaft door for the third level parking deck. The vehicle came to rest halfway into the elevator
shaft and was removed later with a tow truck. The impact from the vehicle knocked the third level door into the elevator
shaft, damaging the glass paneling on the north side of the elevator shaft. The vehicle also struck the masonry (CMU) wall
adjacent to the elevator door and blew out blocks and reinforcing bars. The impact to the elevator door and door frame
assembly also caused additional damage to the CMU at the floor deck anchoring points. This damage was evident at the
third and second level elevator landings.
We conducted our site investigation on July 31st & August 2"d, 2018. In addition, you had previously provided an electronic
copy of the asbuilt construction documents. These plans refer to an "Issued for Bid" date of September 29, 2000 and an
"asbuilt" date of April 28, 2003. Therefore, we assume the structure was built between 2001 and 2003. The structural
design was performed in accordance with the 1997 Uniform Building Code as noted on sheet S0.1. Siegfried also recently
investigated and designed repairs for the entire parking structure as part of an elective maintenance project. The
construction documents for this maintenance project are titled "Repair/Maintenance Plan for: Lodi Station Parking Structure"
dated August 22, 2017. Construction for this maintenance project was completed in May 2018.
The primary garage structure consists of post tensioned concrete floor slabs and beams, cast in place concrete walls,
columns, slab on grade and foundations, and masonry walls. The portion of the structure constructed over the occupied
museum section facing Sacramento Street has a steel framed roof with steel metal decking.
The north elevator shaft consists of reinforced masonry walls with portions of glass glazing on the north and west side.
There is a 4 -foot -deep masonry pit at the bottom of the elevator shaft. There is an adjacent equipment room to the east that
is also open to the roof above the third level of the parking structure. The roof structure consists of roofing over corrugated
metal decking. The decking is supported on the face of the elevator shaft walls by steel angle ledgers. There is a metal
canopy that covers the entrance to the elevator on the third level.
Stockton
3244 Brookside Rd., Ste. 100
Stockton, CA 95219
t: 209.943.2021 f: 209.942.0214
San Jose
111 N. Market St., Ste. 300
San Jose, CA 95113
t: 408.754.2021
Sacramento
109 Scripps Drive
Sacramento, CA 95825
t: 916.520.2777
Modesto
100 Sycamore Ave, Ste. 100
Modesto, CA, 95354
t: 209.762.3580
Page 2
Observations
■
■
SIEGFRIED
The following is an itemized list of damaged items we observed which are depicted on the attached Exhibit A;
1. Brick Veneer
The vehicle swiped and damaged the brick veneer adjacent to the elevator shaft on the third level (Photo 1). This
veneer covers the masonry wall as is only aesthetic in nature.
2. Masonry Walls
The vehicle blew out a portion of the south shaft wall adjacent to the opening for the elevator door on the third level
(Photo 2). The remaining portion of the masonry below the metal canopy that was not destroyed has significant
cracking and exposed reinforcing (Photo 3). We did not observe any structural damage to the masonry wall above
the lintel of the elevator door on the third level (Photo 4). The damage to the masonry extends down the wall below
the third level landing down to the second level door opening. The spalling of the masonry does not extend below
the lintel of the elevator door on the second level. We found no apparent damage to the masonry on the first level.
The damage also appears to be limited to the south wall of the elevator shaft only.
3. Elevator Thresholds
The elevator entrance threshold on the third level shows minor spalling (Photo 5). We also observed signs of lateral
separation, up to 3/4" inch, of the elevator shaft from the third level slab at the ledger to deck connection from the
second level looking up (Photo 6A).
4. Glazing/Aluminum Mullion
Upon impact, the elevator doors on the third level blew off and struck the back (north side) of the elevator shaft.
The cab of the elevator is assumed to have been on the first level at this time. The masonry portion of the wall was
not significantly damage. However, there were multiple panes of glazing that were either shattered or severely
cracked (Photo 7). Upon further inspection, the surrounding aluminum mullion does not appear to be significantly
bent or damaged.
5. Elevator Frame Connections
This report does not include an evaluation of elevator components, however we did observe additional damage to
the masonry walls from the elevator frame anchors pulling out of the wall (Photo 8). The guide rail connection to the
masonry walls appear to remain in good condition (Photo 9) throughout the elevator shaft.
Findings and Repair Recommendations
The following is a summary of our recommendations for repair of the damage identified. The item numbers correspond to
the item numbers listed in the "Observation" section above.
Item 1
The portions of damaged brick veneer can be replaced. This is an aesthetic issue and does not represent structural
damage or hazards.
Item 2
The damage to the masonry walls was caused by direct vehicle impact and the breakout of the anchors from the
elevator door frames. This damage appears to be limited to portions of the south wall at the second and third levels.
The masonry will require saw cutting and replacement. The new masonry reinforcing will need to be doweled into
the adjacent portion of sound walls.
Stockton
3244 Brookside Rd., Ste. 100
Stockton, CA 95219
t: 209.943.2021 f: 209.942.0214
San Jose
111 N. Market St., Ste. 300
San Jose, CA 95113
t: 408.754.2021
Sacramento
109 Scripps Drive
Sacramento, CA 95825
t: 916.520.2777
Modesto
100 Sycamore Ave, Ste. 100
Modesto, CA, 95354
t: 209.762.3580
Page 3
■
■
SIEGFRIED
Item 3
The elevator threshold on the third level will require structural repair to level with elevator door frame. The lateral
separation between masonry shaft wall and parking deck noted in Picture 6A is significant. However, we compared
this separation to the separation we noted in out 2016 investigation (Picture 6B). There appears to be no significant
difference in the amount of movement of the elevator shaft. Therefore, the overall elevator shaft has not moved.
Item 4
The damaged panes of glass appear to be a direct result of the impact form the separated third level elevator doors.
We recommend replacing these individual panes of glass and verification by the window contractor that the
surrounding aluminum mullion is not damaged and can be reused.
Item 5
The bolts anchoring the elevator door frames to the masonry walls cannot be reused in areas where the walls are
damaged. After the masonry walls are repaired, new anchors will need to be installed per the elevator equipment
manufacturer specifications. Anchors in locations where the frame has not been damage are likely able to be
reused; pending analysis of the existing elevator equipment by a qualified professional.
Overall, we did not find any condition in immediate danger of structural failure or creating a current unsafe condition for the
overall structure. The elevator shaft can be reused with moderate repairs; mainly to the masonry walls and elevator
thresholds. This report does include the evaluation of the condition of the elevator equipment or the feasibility of replacing
required elevator components. We recommend consulting with an elevator equipment manufacturer to determine the most
appropriate course of action in repairing or replacing elevator equipment.
We trust this information will be helpful in evaluating the use, maintenance and repairs for this building. If you should have
any questions or need additional information, please do not hesitate to give us a call.
Sincerely,
SIEGFRIED
Antho ty J. Lopes, P. ., S.E.
1'
Rhett S. Kilgore, P.E.
eRpFESSj0,,
44,
LZ F x
NO. S-4550
EXP. 12/31/19
Srhi1CT o�P�
OF CAL\
DATE SIGNED: 8/22/2018
,,,c)FEss/0N
s Kid q�
cp
-72
cs
No. C 85684
*� Exp: 9/30/18
sT
P1
n1
DATE SIGNED: 8/22/2018
Stockton
3244 Brookside Rd., Ste. 100
Stockton, CA 95219
t: 209.943.2021 f: 209.942.0214
San Jose
111 N. Market St., Ste. 300
San Jose, CA 95113
t: 408.754.2021
Sacramento
109 Scripps Drive
Sacramento, CA 95825
t: 916.520.2777
Modesto
100 Sycamore Ave, Ste. 100
Modesto, CA, 95354
t: 209.762.3580
ITEM 4
ITEM 5
ITEM 5
+39'-5" 1 T.O. PARAPET
ITEM 3
+25'-0" 1 T.O. SLAB
+14'-0" t T.O. SLAB
SECTION
+0'-0" , T.O. SLAB
SHADING
DENOTES
MASONRY TO
BE REPLACED
3rd LEVEL
+25'-0"
T.O. SLAB
ITEM 2
ITEM 1
2nd LEVEL
+14'-0"
T.O. SLAB
ELEVATOR ELEVATION
0-
0 0 0 0 0 0
I 3rd
LEVEL
1B�
1—
LOCATION PLAN
ITEM 4
V
v 9,°°� /
2 SPC' P -c / /`
x
ITEM 1
ELEVATOR PLAN VEIW
ITEM 2
■•
EH'uSEEw a
Ear xeEa x�
• SIEGFRIED •
ARCHE�.Ui.
3244 Brookside Road, Suite 100 Stockton, California 95219
209-943-2021 www.siegfriedeng.com Fx: 209-942-0214
Elevator Shaft Repair
JOB NO. 16053B
DATE Aug. 22 2018
SCALE As Shown
Lodi Station Parking Structure
50 N. Sacramento Street
Lodi, CA
DRAWN BY RJS
DESIGNER RSK
SHEET
EXA
Page 4
Exhibit B
Photo 1 — Third Level Brick Veneer Damage
Photo 2 — Third Level Masonry Wall Damage
■
■
SIEGFRIED
Stockton
3244 Brookside Rd., Ste. 100
Stockton, CA 95219
t: 209.943.2021 f: 209.942.0214
San Jose
111 N. Market St., Ste. 300
San Jose, CA 95113
t: 408.754.2021
Sacramento
109 Scripps Drive
Sacramento, CA 95825
t: 916.520.2777
Modesto
100 Sycamore Ave, Ste. 100
Modesto, CA, 95354
t: 209.762.3580
Page 5
■
■
SIEGFRIED
Photo 3 — Masonry Wall Cracking/Exposed Reinforcing
Photo 4 — Third Level Masonry Wall Damage Extents From Shaft Interior
Stockton
3244 Brookside Rd., Ste. 100
Stockton, CA 95219
t: 209.943.2021 f: 209.942.0214
San Jose
111 N. Market St., Ste. 300
San Jose, CA 95113
t: 408.754.2021
Sacramento
109 Scripps Drive
Sacramento, CA 95825
t: 916.520.2777
Modesto
100 Sycamore Ave, Ste. 100
Modesto, CA, 95354
t: 209.762.3580
Page 6
Photo 5 — Third Level Threshold Damage
■
1 SIEGFRIED
Photo 6A — Third Level Deck Lateral Separation Form Elevator Shaft, Looking From Second Level Up At Steel Ledger
Angle
Stockton
3244 Brookside Rd., Ste. 100
Stockton, CA 95219
t: 209.943.2021 f: 209.942.0214
San Jose
111 N. Market St., Ste. 300
San Jose, CA 95113
t: 408.754.2021
Sacramento
109 Scripps Drive
Sacramento, CA 95825
t: 916.520.2777
Modesto
100 Sycamore Ave, Ste. 100
Modesto, CA, 95354
t: 209.762.3580
Page 7
■
■
SIEGFRIED
Photo 6B — Third Level Deck Lateral Separation Form Elevator Shaft, Looking From Second Level Up At Steel Ledger
Angle From 2016 Siegfried Investigation
Photo 7 — Shaft Glazing Damage From Door impact
Stockton
3244 Brookside Rd., Ste. 100
Stockton, CA 95219
t: 209.943.2021 f: 209.942.0214
San Jose
111 N. Market St., Ste. 300
San Jose, CA 95113
t: 408.754.2021
Sacramento
109 Scripps Drive
Sacramento, CA 95825
t: 916.520.2777
Modesto
100 Sycamore Ave, Ste. 100
Modesto, CA, 95354
t: 209.762.3580
Page 8
Photo 8 — Door Frame Separation At Third Level
Photo 9 — Typical Guiderail Anchorage
•• SIEGFRIED
Stockton
3244 Brookside Rd., Ste. 100
Stockton, CA 95219
t: 209.943.2021 f: 209.942.0214
San Jose
111 N. Market St., Ste. 300
San Jose, CA 95113
t: 408.754.2021
Sacramento
109 Scripps Drive
Sacramento, CA 95825
t: 916.520.2777
Modesto
100 Sycamore Ave, Ste. 100
Modesto, CA, 95354
t: 209.762.3580