AGENDA TITLE: Adopt Resolution Rejecting All Bids for Cluff Avenue (Northeast) Sewer Lift Station
Improvements
MEETING DATE: June 20, 2018
PREPARED BY: Public Works Director
RECOMMENDED ACTION: Adopt resolution rejecting all bids for Cluff Avenue (Northeast) Sewer
Lift Station Improvements.
BACKGROUND INFORMATION: Council approved the original specifications and authorized the
advertisement for bids on May 2, 2018. This project included
replacing 72 feet of ductile iron pipe with new PVC piping that is
designed to be extremely resistant to corroding. This project also included replacing miscellaneous pipe
valves and fittings, installing a flow meter, and other incidental work.
The City received the following bid on May 23, 2018
Bidder Location Bid
Engineer's Estimate $49,877
RTC Construction Mgmt. Merced $204,277
Above/(Below)
Engineer's Estimate
$154,400
Following the bid opening, staff contacted RTC Construction Management, Inc. to ascertain the reason for
the high bid price. The contractor indicated the small, utility congested site, did not have adequate space for
the excavation equipment and the electrical panels and one of the utility vaults and generator would have to
be temporarily removed and reinstalled after construction. Staff is currently investigating trenchless pipe
rehabilitation alternatives to address the corroding pipe.
FISCAL IMPACT: Not applicable.
FUNDING AVAILABLE: Not applicable.
c�a
Charles E. Swimley, Jr.
Public Works Director
Prepared by Jimi Billigmeier, Associate Civil Engineer
CES/JB/tdb
cc: City Engineer/Deputy Public Works Director
Utilities Superintendent
APPROVED:
Schwa
K:\WP\PROJECTS\SEWER\Cluff Ave (Northeast) Sewer Lift Station\CReject.doc
, City Manager
6/6/2018
RESOLUTION NO. 2018-120
A RESOLUTION OF THE LODI CITY COUNCIL REJECTING
ALL BIDS FOR CLUFF AVENUE (NORTHEAST) SEWER LIFT
STATION IMPROVEMENTS
WHEREAS, in answer to notice duly published in accordance with law and the order of
this City Council, sealed bids were received and publicly opened on May 23, 2018, at
11:00 a.m., for the Cluff Avenue (Northeast) Sewer Lift Station Improvements, described in the
plans and specifications therefore approved by the City Council on May 2, 2018; and
WHEREAS, said bids have been checked and tabulated and a report thereof filed with
the City Manager as follow:
Bidder
RTC Construction Mgmt.
Above/(Below)
Bid Engineer's Estimate
$204,277 $154,400
WHEREAS, the bid received exceeded the engineer's estimate by over 400 percent due
to lack of space in the construction site; and
WHEREAS, staff recommends that the City Council reject all bids for Cluff Avenue
(Northeast) Sewer Lift Station Improvements.
NOW, THEREFORE, BE IT RESOLVED that the Lodi City Council does hereby reject all
bids for Cluff Avenue (Northeast) Sewer Lift Station Improvements.
Dated: June 20, 2018
I hereby certify that Resolution No. 2018-120 was passed and adopted by the City
Council of the City of Lodi in a regular meeting held June 20, 2018 by the following vote:
AYES: COUNCIL MEMBERS — Johnson, Kuehne, Mounce, and Mayor Nakanishi
NOES: COUNCIL MEMBERS — None
ABSENT: COUNCIL MEMBERS — Chandler
ABSTAIN: COUNCIL MEMBERS — None