HomeMy WebLinkAboutAgenda Report - June 21, 2000 E-12AGENDA TITLE: Grape Bowl Restroom Improvement Project
MEETING DATE: June 21, 2000
PREPARED BY: Parks and Recreation Director
RECOMMENDED ACTION: That the City Council approve the above project, authorize bids and
specifications, and allocate funding.
BACKGROUND INFORMATION: This project will address upgrading the restrooms located on the
north and south sides of the Grape Bowl. Work will include the
removal of the existing vitreous china toilets, urinal troughs, and
sinks. Staff will solicit bids for new stainless steel toilets, urinals
and sinks. The restrooms will receive new interior paint, new restroom partitions, and repairs to the roof
as needed. Lighting in the stairways and restroom areas will be upgraded through the Public Benefits
Program and Energy Masters International. Project items will be handled in-house with the assistance
of outside contractors. Staff recommends funding for this project from the contingency fund.
Specifiations are available for review in the Parks and Recreation Department.
FUNDING:
1999/00 Contingency Fund
Project Estimate: $25,000,
Funding Available: —LJ -h-
Prepared by Steve Virrey, Project Coordinator
RW/SV/sb
Parks and Recreation Director
APPROVED:
H. Dixon Flynn -- City Manager
06/1 5/00
e -ta-
GRAPE RESTROOM IMPROVEMENTS
PROJECT BUDGET: $25,000.00
STAINLESS STEEL TOILETS / STAINLESS STEEL URINALS / TOILET & URINAL PARTITIONS / INTERIOR
PAINTING / ROOF REPAIRS:
1. DEMOLITION WORK: (NO COST / IN-HOUSE: PARKS DEPARTMENT STAFF)
2. PAINTING:
SOUTH SIDE RESTROOM -1,072 SF @.72 PER SF = $771.84
NORTH SIDE RESTROOM -1,072 SF @.72 PER SF = $771.84
SUB -TOTAL: $1,54-3.68
10% CONTINGENCY: $154.36
TOTAL ESTIMATE: $1,698.04
3. TOILET PARTITIONS:
SOUTH SIDE RESTROOM - (7 TOILET - 320.00 EA / 8 URINAL - 275.00 EA)
$2,240.00 TOILET PARTITIONS / $2,200.00 URINAL PARTITIONS
NORTH SIDE RESTROOM - (7 TOILET - 320.00 EA / 8 URINAL - 275.00 EA)
$2,240.00 TOILET PARTITIONS / $2,200.00 URINAL PARTITIONS
SUB -TOTAL: $10,580.00
10% CONTINGENCY: $1,058.00
TOTAL ESTIMATE: $11,638.00
4. ROOFING REPAIR ALLOCATION:
$1,000.00
5. STAINLESS STEEL TOILETS & URINALS
SOUTH SIDE RESTROOM - (8 TOILETS - 400.00 EA 16 URINALS - 300.00 EA) - $5,000.00
NORTH SIDE RESTROOM - (8 TOILETS -400.00 EA 16 URINALS - 300.00 EA) - $5,000.00
SUB - TOTAL: $10,000.00
10% CONTINGENCY: $1,000.00
TOTAL ESTIMATE: $11,000.00
TOTAL PROJECT COST ESTIMATE: $25,336.04