Loading...
HomeMy WebLinkAboutAgenda Report - June 6, 2018 C-10TM CITY OF LODI COUNCIL COMMUNICATION AGENDA ITEM C to AGENDA TITLE: Accept Improvements Under Contract for Harney Lane Grade Separation Project MEETING DATE: June 6, 2018 PREPARED BY: Public Works Director RECOMMENDED ACTION: Accept improvements under contract for Harney Lane Grade Separation Project. BACKGROUND INFORMATION: The Harney Lane Grade Separation Project was awarded to DeSilva Gates Construction, LP, of Dublin, in the amount of $14,313,075, on November 18, 2015. The contract has been completed in substantial conformance with the plans and specifications approved by City Council on July 15, 2015. Pictures of the completed work are provided in Exhibit A. The project consisted of constructing, widening, and realigning Harney Lane, including the construction of a new three -span, cast -in-place, post -tensioned concrete box girder, approximately 248 feet long and 88 feet wide, to grade separate Harney Lane at the Union Pacific Railroad (UPRR) track. Work included signal modifications (temporary and permanent), drainage and utility installation, street lighting, landscaping, constructing raised medians, curbs, gutters, and sidewalks, and other incidental and related work, all as shown on the plans and specifications for the project. The contract completion required the work to be completed in 535 calendar days, and the actual completion was 502 calendar days, 33 days ahead of contract schedule. The roadway was open to public use on December 22, 2017. The final cost of the contract was $15,067,228.89. The difference between the original contract amount and final contract was due to 14 change orders, totaling $851,541.79, which is six percent of the original contract amount. Change Order No. 1 included cost associated with expediting the vineyard survey and demolition work to meet contract requirements with the land owner ($8,285.00). Change Order No. 2 included costs associated with Drainage System No. 9 changes, Sound Wall No. 1 pile changes, and lowering the bore pit for utilities under the UPRR tracks due to elevation of existing petroleum pipeline ($75,327.32). Change Order No. 3 included costs associated with time and materials work due to conflicts with existing utilities requiring changes at the Valley Iron Works access road and installation of a new 10 -inch water main ($92,133.18). Change Order No. 4 included a new footing at the Valley Iron Works gate, increased demolition costs related to the transite water main in Harney Lane, drainage system changes for temporary drainage, City requested changes to traffic signal controls, and added north -slope protection ($170,065.86). Change Order No. 5 included removing the contract and payment for UPRR flagging from the construction contract, as requested by UPRR. Costs were paid directly by the City to UPRR ($168,000.00 CREDIT). Change Order No. 6 included work related to the saturated slide of the north -slope soil onto Harney Lane. Slope protection, additional traffic control, and protection modifications were required due to abnormally wet weather conditions ($51,387.14). APPROVED: Step en Sc K:\WP\PROJECTS\STREETS\HarneyGradeSeparation\Project\CAccept HLGS.docx uer, City Manager 5/24/2018 Accept Improvements Under Contract for Harney Lane Grade Separation Project June 6, 2018 Page 2 Change Order No. 7 included continued north -slope protection measures, added two strands of barbed wire to the temporary cherry orchard security fence, additional grading at Sound Wall No. 1 footings and additional Stage 2B Traffic Control requested by City traffic engineer ($53,351.28). Change Order No. 8 included removal and replacement of unsuitable soil near Winchester Drive, additional Stage 2C Traffic Control, and removal of two small trees near Banyan Drive, conflicting with electrical lines ($78,241.53). Change Order No. 9 included the extension of Sound Wall No. 2 to the bridge deck, a total of approximately 214 lineal feet of footings and 1,430 square feet of concrete masonry unit wall, as requested by City staff ($173,662.35). Change Order No. 10 included changes to the Stage 1A/1C Roadway Structural Section, additional pavement on South Stockton Street to Rocky Lane, grading changes at Driveway No. 8, and premium time costs for asphalt placement on Sunday November 19, 2017, to stay ahead of forecast wet weather ($154,961.18). Change Order No. 11 included adding approximately 2,300 lineal feet of chain link fence at the back of sidewalk, as requested by City staff, and replacement of Valley Iron Works decorative fence posts ($62,706.65). Change Order No. 12 included time -and -materials work, including grading under the bridge structure adjacent to the UPRR tracks, as required by UPRR, completion of temporary drainage related work, and various other items of work to complete the project, as requested by City staff ($147,091.64). Change Order No. 13 included a credit for revised curb detail at existing asphalt locations ($25,567.34 CREDIT). Change Order No. 14 included a credit for City incurred costs related to Public Utility Easements associated with six utility vault installation locations ($22,104.00 CREDIT). There were also adjustments to the quantities of unit items installed, totaling a reduction in the final contract amount by $97,387.65. A complete breakdown, and supporting documentation, of each change order is on file in the Public Works department. Following acceptance by the City Council, as required by law, the City Engineer will file a Notice of Completion with the County Recorder's office. The notice serves to inform vendors and subcontractors that the project is complete and to initiate the 30 -day period to file a stop notice requiring the City to withhold payments from the prime contractor in the event of a payment dispute. FISCAL IMPACT: FUNDING AVAILABLE: There will be a slight increase in the long-term maintenance of the streetlights, landscape, and streetscape, and a short-term decrease in street maintenance costs. This project was funded with Regional Surface Transportation Program (30799000), State Transportation Improvement Program (30799000), Section 190 (30799000), Union Pacific Railroad Contribution (30799000), Regional Transportation Impact Fee (31499000), and Measure K (30399000) Funds. Charles Swimley Public Works Director P Prepared by Gary Wiman, Construction Project Manager CES/GW/tdb Attachment K:\WP\PROJECTS\STREETS\HarneyGradeSeparation\Project\CAccept HLGS docx 5/16/2018 HARNEY LANE GRADE SEPARATION EXHIBIT A BEFORE AFTER BEFORE AFTER